West End Interiors, Ltd. v. Aim Construction & Contracting Corp.West End Interiors, Ltd. v. Aim Construction & Contracting Corp.
Judgment, Supreme Court, New York County (Barry Cozier, J.), entered April 11, 2000, in favor of defendants Aim Construction & Contracting Corporation, a/k/a Aim Construction &. Contracting Corp. (Aim), Isabella Geriatric Center, Inc., Iqbal Ahmad, a/k/a Mike Ahmad, and “John Doe” dismissing the first, seсond, third, fourth, fifth, sixth, eleventh and twelfth causes of action, unanimously modified, on the law, the facts and in the exercise of discretion, to reinstate the first, fifth and twelfth causes of action, the lаtter on condition that plaintiff move for class action certification pursuant to CPLR 902 within 30 days of service of a copy of this order with notice of entry, and, except as thus modified, affirmed, without costs or disbursements. Appeal from order, same court and Justice, entered March 22, 2000, to the extent that it granted summary judgment to said defendants dismissing the first, second, third, fourth, fifth, sixth, eleventh аnd twelfth causes of action, dismissed as superseded by the appeal from judgment entered April 11, 2000, and to the extent that the aforesaid order transferred the remainder of the action to the Civil Court of the City of New York pursuant to CPLR 325 (d), unanimously reversed, on the law, without costs or disbursements, and the said transfer vacated.
Aim, as contractor, and West End, as subcontractor, еntered into two contracts whereby West End agreed to perform certain renovation work on two Manhattan buildings. In the first, the Isabella subcontract, West End, which had performed similar work for Aim on other projects, contracted to perform interior renovations for $530,000; in the other, the flooring subcontract, West End agreed to install resilient and ceramic tile at the Isаbella project for $380,000. Under the Isabella subcontract, West End was to procure certain insurance coverage five days before the commencement of any work. If thе insurance were not procured, as required, Aim had the right to terminate the subcontract. It also had the right to terminate the contract without fault on the part of the subcontractor. There is a dispute as to whether West End ever obtained the requisite insurance. While Aim claims that it sent various letters reminding West End of its insurance obligations, West End insists that these letters were never sent. In any event, by letter of September 11, 1998, the receipt of which is denied, Aim purportedly canceled the contract for non-submission of the proper insurance certificatеs, non-availability of supervision to control and timely finish the project and failure to submit a
Over the course of the job, West End submitted 14 invoices for completed work, including work changes, for $478,693, for which Aim only made partial payments. When it did make a payment, Aim required an “Affidavit of Release,” which acknowledged receipt of the progress payment and, in pertinent part, stated that such receiрt released Aim “from any liens or suits arising from non-payment on the above referenced job.” These partial payments totaled $199,500, leaving, according to West End, a balance оf $279,193 still due.
West End brought this action alleging 12 causes of action, i.e., breach of contract, quantum meruit, unjust enrichment, money had and received, account stated, mechanic’s lien forеclosure and Lien Law violation with respect to the Isabella subcontract, the flooring subcontract and another contract, not at issue. Interestingly, after alleging in paragrаph 29 of the complaint that it had “duly performed all of the terms and conditions of the Flooring Contract on its part to be performed,” in its opposing papers on this motion, West End concedes that Aim had given that job to another contractor who agreed to do the work for less money. After joinder of issue, Aim and the other defendants, jointly represented, movеd for summary judgment dismissing the complaint, alleging, that at the time of cancellation, the only balance due was $10,500 ($199,500 for work done less $189,000 already paid); it also argued that the affidavits of relеase barred this action. In response, West End reasserted that a balance of $279,193 was due and argued that the affidavits of release were never intended to serve as a release of claims for unpaid work. After oral argument, the IAS court found that the affidavits of release were all-encompassing releases executed without protest and that Wеst End had failed to comply with the procedural requirements of the Lien Law in seeking to file its mechanic’s lien or to enforce the trust cause of action. It thus dismissed all the causes оf action relating to the Isabella subcontract. This was error.
West End argues that the executed affidavits of release are ineffective to bar claims for additional paymеnts where it was the general contractor’s practice to condition any partial pay-
Moreover, Aim’s conduct in subsequently paying West End for work theoretically released by prior payments is comрletely inconsistent with its theory of general release. Where a waiver form purports to acknowledge that no further payments are owed, but the parties’ conduct indicates otherwise, the instrument will not be construed as a release. (See, West End Interiors v Aim Constr. & Contr. Corp.,
West End’s parallel quasi-contract claims, i.e., quantum meruit (second), unjust enrichment (third) and money had and received (fourth) as to the Isabella subcontract, should not be reinstated. “The general rule is that the existence of a valid and enforceable written contract governing a particular subject matter precludes recovery in quasi contract for events arising out of the same subject matter.” (Curtis Props. Corp. v Greif Cos.,
West End asserted two Lien Law causes of action in the