Opinion
INTRODUCTION
Design engineers designed retaining walls for an automobile dealership project. They contracted with the builder of the walls. After a portion of the retaining walls failed and the project suffered damage, the property owner sued the design engineers for negligence. The general contractor sued the design engineers for negligence and equitable indemnity. The trial court granted motions for summary judgment on the ground the design engineers did not owe a duty of care to the property owner or the general contractor. We affirm.
We apply the burden-shifting standards of Code of Civil Procedure section 437c, subdivision (p)(2), and conclude the design engineers met their
*159
initial burden of showing no duty of care existed. The burden then shifted to the property owner and the general contractor to produce evidence showing the existence of a duty or a triable issue of material fact relevant to determining whether a duty existed. The property owner and the general contractor failed to carry this burden, considering the factors set forth in
Biakanja v. Irving
(1958)
Because the design engineers did not owe such a duty to the property owner, the general contractor’s claim for equitable indemnity also fails.
(BFGC Architects Planners, Inc.
v.
Forcum/Mackey Construction, Inc.
(2004)
SUMMARY OF UNDISPUTED FACTS 1
Weseloh Family Limited Partnership (Weseloh) owns property in San Juan Capistrano (the property) which is leased by Weseloh & Sons, LLC, and Weseloh Corporation. (All three entities are collectively referred to as the Weseloh plaintiffs.)
On May 10, 1999, the Weseloh plaintiffs contracted with a general contractor, K.L. Wessel Construction Co., Inc. (Wessel), to construct automobile dealership facilities on the property (the project). Subcontractor Sierra Pacific Earth Retention Corporation (Sierra), which has done business under the name Retaining Wall Company North, built the retaining walls for the project. Charles Randle performed consulting work on the project for Sierra and “ ‘supervised the design work of the design engineers that worked on the Weseloh project at all times.’ ” Randle, who was employed by Owen Engineering Company (Owen) during unspecified time periods, was paid $1,500 or $2,200 for his design of two Keystone walls. Randle was aware that Weseloh owned the property.
Neither Randle nor Owen ever (1) contracted with the Weseloh plaintiffs or Wessel to construct the retaining walls; (2) contracted with the Weseloh plaintiffs or Wessel to prepare any design, engineering, planning, and/or review of construction, grading, manufacture and/or installation of the property or any improvements; or (3) had a role in the construction of the *160 retaining walls. At Sierra’s request, both Randle and Owen inspected the retaining walls following construction. On February 12, 2001, a portion of the retaining walls failed.
PROCEDURAL BACKGROUND
The Weseloh plaintiffs sued Wessel, Sierra, Compaction Plus, Inc., Soils Southwest, Inc., Owen, and Randle. The second amended complaint alleged a claim against Soils Southwest, Owen, and Randle for professional negligence. The Weseloh plaintiffs alleged that Soils Southwest, Owen, and Randle “breached their respective duties of care to Plaintiffs by negligently and carelessly failing to use the care required of their respective professions in the design, planning, engineering and/or review of the construction, grading, manufacture and/or installation of the earth retention system of retaining walls on the SUBJECT PROPERTY and failed to comply with acceptable and applicable design standards, codes and relevant professional engineering customs and practices for the design of earth retention systems or retaining walls, as evidenced by the failure of such earth retention system or retaining wall designed by the Defendants as alleged herein.”
The Weseloh plaintiffs further alleged, “[a]s a result of the negligence of said Defendants, and each of them, as aforesaid, as manifested by the failure of the design and construction of the earth retention system, the SUBJECT PROPERTY and improvements thereon have sustained severe physical and structural property damage, and Plaintiffs are informed and believe and based thereon allege that additional damage to the SUBJECT PROPERTY may continue to occur and may be discovered from time to time in the future.” The Weseloh plaintiffs also alleged, “as a result and proximate cause of the negligence of Defendants SOILS SOUTHWEST, OWEN, RANDLE and DOES 51 THROUGH 90, as described herein, Plaintiffs have sustained and will sustain monetary damages in an amount not less than $6,000,000.”
Wessel’s second amended cross-complaint contained claims for equitable indemnity, total indemnity, contribution, and professional negligence against Randle and Owen. 2 With regard to its professional negligence claim, Wessel alleged it had “sustained and will sustain monetary damages including, but not limited to, litigation costs, contractor’s fees, attorney’s fees and consultants’ fees to inspect, repair and mitigate damages arising out of said negligent design, construction, repair and maintenance and to defend against [the Weseloh plaintiffs’] action herein.”
*161 In October 2002, the Weseloh plaintiffs, Wessel, and Sierra entered into a settlement agreement.
In April 2003, Randle and Owen filed motions for summary judgment on the Weseloh plaintiffs’ second amended complaint and Wessel’s second amended cross-complaint on the following common grounds: (1) Randle and Owen could not be liable to the Weseloh plaintiffs or Wessel for negligence because Randle and Owen had no contractual relationship with the Weseloh plaintiffs or Wessel, and there was no basis to recognize a duty of care; (2) no evidence supported the claim Randle or Owen caused the failure of the retaining walls; and (3) the Weseloh plaintiffs and Wessel released Randle and Owen as part of the release of Sierra in the settlement agreement. Randle and Owen’s motion for summary judgment against Wessel included the additional ground there was no basis for a claim of indemnity.
The trial court granted Randle and Owen’s motions for summary judgment. The order granting summary judgment against the Weseloh plaintiffs stated in relevant part: “After consideration of all of the moving and opposing evidence, the Court concludes that the defendants Owen Engineering Group and Charles J. Randle did not owe a duty to the plaintiffs as a matter of law. The analysis of the moving parties as to the
[Biakanja]
(1958)
Judgment was entered accordingly.
The Weseloh plaintiffs moved to vacate the trial court’s decision granting summary judgment and for a new trial on the ground “[t]he evidence was insufficient to justify the decision and there was an error in law, in that Owen Engineering Group and Charles J. Randle, as the design engineer of the retaining wall which failed, owed a duty of care to Plaintiffs, as the property owner, for whom the wall was designed.” Wessel similarly moved for a new trial on the same ground as asserted by the Weseloh plaintiffs.
*162
The trial court denied the Weseloh plaintiffs’ and Wessel’s motions, stating in relevant part: “Moving Parties raise no new arguments and do not cite any law not previously considered by this Court. The Ruling was and remains correct, [f] One of the cases cited by Moving Parties,
Oakes
v.
McCarthy
[Co.] (1968)
Both the Weseloh plaintiffs and Wessel appealed from the judgment entered against them and in favor of Randle and Owen, and the postjudgment denial of their motions for a new trial.
DISCUSSION
I.
Standard of Review and Applicable Burdens of Proof
“A trial court properly grants summary judgment where no triable issue of material fact exists and the moving party is entitled to judgment as a matter of law. [Citation.] We review the trial court’s decision de novo, considering all of the evidence the parties offered in connection with the motion (except that which the court properly excluded) and the uncontradicted inferences the evidence reasonably supports. [Citation.] In the trial court, once a moving defendant has ‘shown that one or more elements of the cause of action, even if not separately pleaded, cannot be established,’ the burden shifts to the plaintiff to show the existence of a triable issue; to meet that burden, the plaintiff ‘may not rely upon the mere allegations or denials of its pleadings . . . but, instead, shall set forth the specific facts showing that a triable issue of material fact exists as to that cause of action . . . .’
*163
[Citations.]”
(Merrill
v.
Navegar, Inc.
(2001)
Our Supreme Court has explained how the burden of persuasion and/or production and the burden of proof are analyzed in motions for summary judgment. “[H]ow the parties moving for, and opposing, summary judgment may each carry their burden of persuasion and/or production depends on
which
would bear
what
burden of proof at trial. Again, in
Reader’s Digest
[Assn. v.
Superior Court
(1984)
II.
Owen and Randle Satisfied Their Burden Under Code of Civil Procedure Section 437c, Subdivision (p)(2) by Producing Evidence Showing They Did Not Owe a Duty of Care to Either the Weseloh Plaintiffs or Wessel
The California Supreme Court has stated, “ ‘[n]egligence is conduct which falls below the standard established by law for the protection of others.’ [Citation.] ‘Every one is responsible, not only for the result of his willful acts, but also for an injury occasioned to another by his want of ordinary care or skill in the management of his property or person, except so far as the latter has, willfully or by want of ordinary care, brought the injury upon himself.’ [Citation.] [f] The threshold element of a cause of action for negligence is the existence of a duty to use due care toward an interest of another that enjoys legal protection against unintentional invasion. [Citations.] Whether this essential prerequisite to a negligence cause of action has been satisfied in a particular case is a question of law to be resolved by the court. [Citation.] [f] A judicial conclusion that a duty is present or absent is merely ‘ “a shorthand statement . . . rather than an aid to analysis .... ‘[D]uty,’ is not sacrosanct in itself, but only an expression of the sum total of
*164
those considerations of policy which lead the law to say that the particular plaintiff is entitled to protection.” ’ [Citations.] ‘Courts, however, have invoked the concept of duty to limit generally “the otherwise potentially infinite liability which would follow from every negligent act. . . .” ’ ”
(Bily, supra,
In their motions for summary judgment, Randle and Owen produced undisputed evidence showing they did not owe the Weseloh plaintiffs or Wessel a duty of care in designing the retaining walls: (1) the Weseloh plaintiffs contracted with Wessel to construct automobile dealership facilities at the property; (2) Randle worked for Sierra; 3 (3) Sierra built the retaining walls at the project; (4) a portion of the retaining walls failed; (5) neither Randle nor Owen had a “role in the construction” of the retaining walls; (6) neither Randle nor Owen entered into a contract with the Weseloh plaintiffs; (7) neither Randle nor Owen entered into a contract with Wessel; and (8) neither Randle nor Owen was ever compensated by the Weseloh plaintiffs or Wessel for any work performed for the project.
Randle and Owen showed they had no contractual privity with either the Weseloh plaintiffs or Wessel and performed only professional design services for a subcontractor involved in the project. They therefore carried the burden of producing evidence that the Weseloh plaintiffs’ and Wessel’s negligence claims failed because no duty of care existed. As a result, the burden shifted to the Weseloh plaintiffs and Wessel to show such a duty existed or to show there existed a triable issue of material fact relevant to the determination of the duty issue. (Code Civ. Proc., § 437c, subd. (p)(2).)
III.
Summary of Biakanja and Bily
In their opposition to the motion for summary judgment, the Weseloh plaintiffs argued the lack of contractual privity with Randle and Owen did not preclude a finding of a duty and the analyses of the California Supreme Court’s decisions in
Biakanja, supra,
The Supreme Court in
Bily, supra,
In
Biakanja, supra,
In
Bily, supra,
We turn to the record in this case and consider the evidence produced by the Weseloh plaintiffs and Wessel in an effort to carry their burden of proving the existence of either a duty of care or a triable issue of material fact relevant to resolving the question whether a duty existed.
IV.
The Weseloh Plaintiffs and Wessel Failed to Carry Their Burden of Showing Randle and Owen Owed a Duty of Care to Them or a Triable Issue of Material Fact Pertinent to the Determination of the Duty Issue
The Weseloh plaintiffs produced the following additional evidence relevant to the duty question in opposition to Randle and Owen’s motion for summary judgment: (1) Randle performed design work on the project as a consultant for Sierra but “knew that Weseloh was the owner of the project in 1998/1999”; (2) Randle “ ‘supervised the design work of the design engineers that worked on the Weseloh project’ (3) Randle was paid $1,500 or $2,200 for his design work; (4) work performed by Randle and/or Owen on the project was defective; (5) Randle used the soils report prepared by Soils Southwest as a reference, making the decision not to use the values therein because they addressed crib walls and conventional walls and did not apply to the project’s Keystone walls; and (6) Randle “testified in his deposition that he ‘used an accepted standard of the industry, which is the ICBO approved manual for Keystone wall construction.’ ”
The Weseloh plaintiffs and Wessel produced evidence Randle’s signature and stamp appeared on two earth retention calculations submitted to the City of San Juan Capistrano, which identified Retaining Wall Company North (Sierra) as the “preparer,” stated the calculations were “prepared for” Wessel, and identified the “site” as Weseloh Chevrolet.
*167 We next apply the undisputed facts in this case to the Biakanja factors and the Bily factors.
A.
Application of Biakanja Factors
1. Extent to which Randle and Owen’s design was intended to affect the Weseloh Plaintiffs and Wessel
The undisputed evidence showed neither Randle nor Owen worked for, or contracted with, the Weseloh plaintiffs or Wessel. Randle and Owen worked for Sierra by creating a design for the retaining walls, but did not participate in Sierra’s construction of the walls. There was no evidence of an intended beneficiary clause in any contract related to the design of the retaining walls, identifying the Weseloh plaintiffs or Wessel as the intended beneficiary of work performed by Randle and Owen.
Randle was aware the property was owned by Weseloh. Although his name and stamp appeared on the earth retention calculations prepared for Wessel, the calculations themselves identified the preparer as Retaining Walls Company North (Sierra), not Randle or Owen. This evidence bolsters the position that Randle and Owen’s role in the project was to primarily benefit Sierra as the preparer of the calculations. To the extent Randle and Owen’s participation in the project would also benefit Wessel and the Weseloh plaintiffs, it was only through Sierra.
2. Foreseeability of injury
The California Supreme Court gave limited weight to the foreseeability factor in determining whether a duty existed in
Bily, supra,
Here, the Weseloh plaintiffs sought property damages in addition to economic damages. We recognize
Bily, supra,
True, it is generally foreseeable a design defect could result in the failure of a retaining wall. However, as discussed above, the Weseloh plaintiffs and Wessel failed to produce evidence showing how and the extent to which their damages were caused by the asserted design defects. This is a significant fact in light of the absence of evidence showing Randle and Owen’s design was followed without alteration. For the reasons set forth in Bily and the insufficiency of the evidence on causation in this case, we give the factor of foreseeability limited weight.
3. Certainty the Weseloh Plaintiffs and Wessel sustained injury, and the closeness of the connection between Owen and Randle’s conduct and that injury
Randle and Owen appear to agree the Weseloh plaintiffs and Wessel sustained damage as a result of the failure of a portion of the retaining walls. We therefore consider the closeness of the connection between Randle and Owen’s conduct and the damages sustained by the Weseloh plaintiffs and Wessel. Based on the state of the record, the evidence is insufficient to show any such connection. Wessel produced evidence Randle and Owen’s design was defective in various ways, “contributing” to the failure of the retaining walls. Wessel cited the declaration of its geotechnical expert, Walter F. Crampton, in its response to Randle and Owen’s separate statement. In his declaration, Crampton stated that Randle failed to take into consideration the on-site soil conditions, improperly deviated from the original design criteria, and “ultimately underdesigned the wall, contributing to the wall’s failure.” Crampton also stated in his declaration that “the base of the wall, including the wall’s ‘toe,’ was improperly compacted . . . and that improper fill was placed both within the foundation and toe of the wall.” One of Wessel’s attorneys submitted a declaration generally stating the failure of the walls occurred “in large part” due to Randle and Owen’s “participation in the design and repair of the wall.” But the Weseloh plaintiffs and Wessel failed to produce evidence showing how or the extent to which those design defects actually caused their damages.
Although the Weseloh plaintiffs and Wessel state in their appellate opening brief “the wall had been built using his [Randle’s] engineering plans,” there is no evidence in the record that Sierra actually used Randle and Owen’s design without alteration in constructing the retaining walls. There is no dispute Randle and Owen’s role in the project was limited to the design of the
*169
retaining walls, the supervision of the design process, and an inspection of the walls. As discussed above, there is no evidence either Randle or Owen ever participated or supervised any physical work in the construction of the retaining walls; rather, it appears Randle and Owen provided engineering services akin to professional advice and opinion. (See
Oakes
v.
McCarthy Co.
(1968)
4. Moral blame
This case is different from
Biakanja, supra,
In
Ratcliff Architects v. Vanir Construction Management, Inc.
(2001)
Therefore, based on the record before us, no reason appears to assign Randle or Owen any moral blame.
5. Policy of preventing future harm
We next evaluate the degree future harm would be prevented by imposing a duty of care on Randle and Owen. In
Bily, supra,
Here, neither the Weseloh plaintiffs nor Wessel provided any evidence supporting an argument that greater care in design engineering would result from expanded liability. Instead, they argue that not recognizing a duty “would create a special exception to the law of negligence for design engineers that would insulate design engineers from liability for negligence to third parties.” This is not an accurate statement. The Weseloh plaintiffs are not without the remedy of pursuing claims for damages against their general contractor, and Wessel is not without the remedy of pursuing its claims for damages against its subcontractor, Sierra. Randle and Owen, in turn, would be accountable to Sierra for any defects in the design that caused damage. Under the Weseloh plaintiffs and Wessel’s theory, Randle and Owen’s liability to them and to Sierra might be overlapping. Furthermore, the Weseloh plaintiffs and Wessel could have taken steps that would have enabled them to proceed directly against Randle and Owen by, for example, negotiating for the inclusion of a provision in the subcontract identifying the Weseloh plaintiffs and Wessel as the intended beneficiaries. As discussed above, there is no evidence the Weseloh plaintiffs or Wessel did so.
B.
Application of Bily Factors 4
1. Liability out of proportion to fault
In Bily, supra, 3 Cal.4th at pages 401-402, the court noted, “judicial endorsement of third party negligence suits against auditors limited only by *171 the concept of foreseeability raises the spectre of multibillion-dollar professional liability that is distinctly out of proportion to: (1) the fault of the auditor (which is necessarily secondary and may be based on complex differences of professional opinion); and (2) the connection between the auditor’s conduct and the third party’s injury (which will often be attenuated by unrelated business factors that underlie investment and credit decisions).”
The California Supreme Court expressed concern that undue emphasis on the foreseeability of an injury could result in a determination of expanded liability out of proportion to fault.
(Bily, supra,
2. Prospect of private ordering
In evaluating whether to impose on an auditor a duty of care to third persons, the Supreme Court explained an audit report is not the equivalent of a consumer product because (1) “the maker of a consumer product has complete control over the design and manufacture of its product; in contrast, the auditor merely expresses an opinion about its client’s financial statements”; (2) the third parties in question generally possess considerable sophistication in analyzing financial information; and (3) the third parties can privately order the risk of inaccurate financial reporting by contractual arrangements with the client. (Bily, supra, 3 Cal.4th at pp. 402-403.)
Because Randle and Owen had no part in the construction of the retaining walls, they, like the auditor in
Bily,
did not have complete control
*172
over the creation of the product—the retaining walls. As discussed above, there is no evidence in the record showing Randle and Owen’s design was used without alteration. The Weseloh plaintiffs and Wessel are sophisticated parties. Before commencing an extensive construction project, the Weseloh plaintiffs and Wessel had the option of negotiating a clause naming them the intended beneficiaries in contracts related to the project and expressly providing for the right to pursue claims directly against subcontractors. “As a matter of economic and social policy, third parties should be encouraged to rely on their own prudence, diligence, and contracting power, as well as other informational tools.”
(Bily, supra,
3. Effect of professional services provider liability to third persons
For all of the reasons stated above in our discussion of the fifth
Biakanja
factor, there is no evidence supporting a policy “to favor the alleged tortfeasor over the alleged victim as an effective distributor of loss.”
(Bily, supra,
C.
Conclusion
The parties acknowledge there is no California case directly on point, and our research has not found any case, applying the Biakanja factors, which holds that a design engineer who provides only professional services in a commercial construction project owes a duty of care to the property owner of the project or a general contractor, in the absence of contractual privity. As discussed above, Randle and Owen produced sufficient evidence to establish they owed no duty to the Weseloh plaintiffs or Wessel based on the design of the retaining walls for Sierra. The burden therefore shifted to the Weseloh plaintiffs and Wessel to produce evidence to prove the existence of such a duty or of a triable issue of material fact relevant to the determination of the duty issue.
The Weseloh plaintiffs and Wessel failed to produce evidence to satisfy their burden. With regard to the Biakanja factors, while it was foreseeable that design defects could cause a retaining wall to fail, the Weseloh plaintiffs and Wessel failed to produce any evidence showing (1) Randle and Owen’s design was primarily intended to affect the Weseloh plaintiffs and Wessel; *173 (2) the closeness of the Weseloh plaintiffs’ and Wessel’s injury to Randle and Owen’s conduct; (3) any moral blame implicated by Randle and Owen’s conduct; or (4) how, by imposing expanded liability on design engineers under similar circumstances, future harm would be prevented.
With regard to the Bily factors, the imposition of such a duty would result in liability out of proportion to fault. With regard to private ordering, the Weseloh plaintiffs and Wessel could have required subcontractors to name them as intended beneficiaries of their subcontracts. The Weseloh plaintiffs could also have required subcontractors to name them as additional insureds in their insurance policies. Neither of these contract alternatives was accomplished here.
In light of the Weseloh plaintiffs and Wessel’s failure to carry their burden under Code of Civil Procedure section 437c, subdivision (p)(2), the trial court properly concluded Randle and Owen did not owe them a duty of care. Our holding should not be interpreted to create a rule that a subcontractor who provides only professional services can never be liable for general negligence to a property owner or general contractor with whom no contractual privity exists. There might be a set of circumstances that would support such a duty, but it is not presented here. Judgment was properly entered against the Weseloh plaintiffs and Wessel on their claims for negligence against Randle and Owen, and the trial court properly denied the motions for a new trial on the negligence claims.
V.
No Claim for Negligent Misrepresentation Was Asserted
In view of arguments made by the parties, we need to address the difference between negligence and negligent misrepresentation. To the extent the Weseloh plaintiffs or Wessel justifiably relied on the defective design, they might have had a claim against Randle and Owen for negligent misrepresentation. But neither party asserted a claim for negligent misrepresentation against Randle or Owen. The Supreme Court explained in
Bily, supra,
Affirming the Restatement Second of Torts approach as the “only one that achieves consistency in the law of negligent misrepresentation,” the California Supreme Court specifically contemplated the availability of negligent misrepresentation claims to cases involving information provided by engineers: “Accountants are not unique in their position as suppliers of information and evaluations for the use and benefit of others. Other professionals, including attorneys, architects, engineers, title insurers and abstractors, and others also perform that function. And, like auditors, these professionals may also face suits by third persons claiming reliance on information and opinions generated in a professional capacity.”
(Bily, supra,
The Weseloh plaintiffs and Wessel rely on
Huber, Hunt & Nichols, Inc. v. Moore
(1977)
VI.
Wessel’s Equitable Indemnity Claim Fails Because Neither Randle nor Owen Owed a Duty to the Weseloh Plaintiffs
In light of our holding neither Randle nor Owen owed a duty to the Weseloh plaintiffs, Wessel’s equitable indemnity claim, which requires that such a duty exist, necessarily fails. In
Jaffe v. Huxley Architecture
(1988)
In
BFGC Architects Planners, Inc. v. Forcum/Mackey Construction, Inc., supra,
Our case does not involve vicarious liability, strict liability, or any form of contractual indemnity. As discussed above, there is no duty on a general negligence theory owed by Randle or Owen to the Weseloh plaintiffs. Therefore, Wessel’s equitable indemnity claim fails. The trial court properly granted summary judgment as to this claim and denied Wessel’s motion for new trial on this issue.
*176 DISPOSITION
The judgment and postjudgment order are affirmed. Respondents to recover their costs on appeal.
Rylaarsdam, Acting P. J., and Moore, J., concurred.
A petition for a rehearing was denied January 19, 2005, and the petition of appellants Weseloh Family Limited Partnership et al., for review by the Supreme Court was denied March 23, 2005.
Notes
The summary of facts is based on undisputed evidence presented in the moving papers and in the opposition to the motions for summary judgment. Although several objections were made to evidence presented in support of and against the motions, the trial court overruled all evidentiary objections. No party contends the trial court erred by overruling any of the objections.
Wessel’s second amended cross-complaint also contained a claim for breach of contract to obtain insurance against all defendants. This cause of action is not mentioned in Wessel’s appellate briefs, and no argument is made that that claim should have survived. We therefore do not address it further.
Although it is disputed whether Randle worked for Sierra as an employee or as an independent contractor, it is not disputed he performed design services for Sierra.
In the opening brief, the Weseloh plaintiffs and Wessel argue this case is distinguishable from
Bily, supra,
The settlement agreement between the Weseloh plaintiffs, Wessel, and Sierra stated the Weseloh plaintiffs would be paid $1,600,000 by Wessel and $1,200,000 by Sierra under its terms, and stated Soils Southwest had previously agreed to settle for $800,000 which would be paid to the Weseloh plaintiffs. Even if we subtract $3,600,000 (the sum of the above stated settlement amounts) from $6,000,000, Randle and Owen would still face significant liability ($2,400,000) to the Weseloh plaintiffs alone.
We ordered the parties to be prepared to discuss at oral argument the impact of
BFGC Architects Planners, Inc.
v.
Forcum/Mackey Construction, Inc., supra,
