Wentink v. Board of Chosen Freeholders

66 N.J.L. 65 | N.J. | 1901

The opinion of the court was delivered by

Collins, J.

It is unquestionable that the recitals of the resolution awarding a contract to the plaintiff, if legally established against derelict bidders, would have fully justified the action reprobated by the court. This is declared in the *67opinion read on the decision of the certiorari. The only reason for not upholding such action was that, being quasi-judicial in its nature, it could not lawfully be taken without notice to Stanley & Shire, who would be directly affected thereby. Stanley v. Passaic, 31 Vroom 393.

There was, therefore, no lack of power to make the contract with the plaintiff. The fatal defect was in an irregular exercise of such power. It would be too much to hold every contractor with a public body to a scrutiny, at his peril, of the corporate proceedings. All that he need look to is the power to make the ostensible contract. Bigelow v. Perth Amboy, 1 Dutcher 297; Knapp v. Hoboken, 9 Vroom 371; Tappan v. Long Branch Commission, 30 Id. 371; Moore v. Mayor, &c., of New York, 73 N. Y. 338.

The question in this case, then, is as to what must befall one whose contract, through no fault of his own, is, by force of law, annulled while yet unperformed. Clearly he cannot sue on the contract, for it has no longer legal existence. This disposes of any claim of the present plaintiff for profits. But, until set aside, the contract was, as between the parties to it, entirely valid, and its annulment subjected those parties to all just equities. Where there is a prevention of performance of a valid contract, through the fault of a defendant, the measure of the plaintiff’s damages is generally, for the Avork done, such a proportion of the entire price as the fair cost of that Avork bears to the fair cost of the whole work, and in respect to the Avork not done, such profit as he Avould have realized by doing it. Kehoe v. Rutherford, 27 Vroom 23. In the case in hand the performance of the contract was not prevented by the fault of the defendant, but by vis major. The making of the contract was, however, induced by such fault; and, on its annulment, the defendant should answer, as on a quantum meruit, for the work (done thereunder. This obviates the difficulty existing in thatj class of cases where a blameless party is entitled to recover for what has been done or furnished under a contract, not’legally enforceable, that the other party refuses to perform. In- such cases recovery depends upon benefit and, perhaps, is limited to benefit. *68Banker v. Henderson, 29 Id. 26. , In such a case as the present, benefit is entirely aside.

The implied assumpsit on which we rest our decision will arise against a public corporation as well as against an individual dr a private corporation. Dill. Mun. Corp., § 383; Louisiana v. Wood, 102 U. S. 294. The cases that bar recovery against a public corporation, on ,an implied assumpsit, rest either on a lack of power to make an express contract or a failure to exercise it. Town of Hackettstown ads. Swackhamer, 8 Vroom 191; Car Spring and Rubber Co. v. Jersey City, 35 Id. 544.

As to the measure of the quantum meruit for the work done the contract rate should govern. In the absence of an}' contrary proof, fair cost will be deemed an equivalent. The present plaintiff is, therefore, entitled to recover on that, basis, and, by parity of reasoning, he should be allowed his expenditure in attempting to secure the materials that had been furnished, when his contract was stayed. That expense was a mere incident to the other. The plaintiff could not abandon his contract because it was challenged. It was his duty to preserve the status of the work pending the litigation. His obligation to perform his contract was not removed until the final determination of the cause. It might be that he would be called on to perform it. He should, therefore, recover for all the expenditure and interest. The total, by the special finding, appears to be $730. Let judgment be entered accordingly.