Welles v. Portuguese-American Bank of San Francisco

215 F. 81 | 9th Cir. | 1914

GILBERT, Circuit Judge.

In aid of its petition for a rehearing the appellee was permitted to bring before this court certain portions of the record in the court below which were not contained in the transcript on the appeal, the same being certain provisions of the specifications which were referred to and made a part of the contract which was involved. The appellants, answering the petition, object to the consideration of the new matter so brought before us, on the ground that the same was not read to nor brought to the attention of the court below. It is unnecessary to discuss that objection, for in our opinion the new matter so presented is not of such a nature as to affect the decision of the case on the appeal. The provisions of the specification so added to the record are as follows:

“All conditions of tills contract are considered material and failure to comply with any of said conditions on the part of contractor -shall be deemed a breach of the contract. Should the contractor neglect or fail to perform any of the conditions of the contract, the board of public works shall have the right, whether any alternative right is provided or not, to declare the contract terminated.”

Then follow provisions as to the manner in which the contract may he terminated, and the provision that upon such termination the contractor shall forfeit all sums due him under the contract, and that both he and his surety shall he liable upon his bond for all damages caused to the city by reason of his failure to complete the contract. These provisions, in brief, give to the board of public works the option to terminate the contract upon the failure or neglect of the contractor te perform any of the conditions thereof. It is not declared that the *82right to terminate the contract is the only remedy against the contractor for breach thereof, or of any of its provisions. On the contrary, it is declared that the board of public works shall have that right, “whether any alternative right is provided or not.” The provision that without the consent of the board of public works the contractor “shall not either legally or equitably assign any of the moneys payable under this contract, or his claim thereto,” is in no way affected by the provisions of the specifications above quoted. By no principle of reasoning can it be concluded that the provision for the termination of the contract upon breach of condition is tantamount to assent by the board to the transfer of any of the moneys payable under the contract, or the contractor’s claim thereto, nor would the act of terminating the contract, if resorted to, be an adequate remedy, or any remedy, for such a breach, and indeed the board of public works might have no means of knowing that an assignment had been made. That breach of the contract is tinlike all other possible breaches thereof, in that the latter are open and visible upon an inspection of the work. The maxim, “Expre'ssio unius es't exclusio alterius,”-invoked by the appellee, is not applicable. The question is not one of the construction of a statute, but it is what was the intention of the parties as expressed in a contract. We find neither authority nor reason for applying the maxim to the provisions of a contract relating to the remedies to be pursued for default therein. The reverse has been held in a well-considered opinion in Straus v. Yeager, 48 Ind. App. 448, 93 N. E. 881.

The petition for a rehearing is denied.

midpage