THEODORE E. WEIMAN еt al., Petitioners, v. THE SUPERIOR COURT OF THE CITY AND COUNTY OF SAN FRANCISCO et al., Respondents; JOHN A. NELSON, INCORPORATED (a Corporation), Real Party in Interest.
S. F. No. 20063
In Bank
Mar. 11, 1959.
710
No appearance for Respondents.
James C. Travis and Carl W. Svenson for Real Party in Interest.
SPENCE, J.—Petitioners, Theodore E. Weiman and Cecelia Weiman, seek a writ of prohibition tо prohibit the respondent court from taking any “further steps to enforce its order for arbitration” under a construction contract, and also a writ of mandate to compel the respondent court to оrder a “summary trial to be set on the jury trial calendar.” The “order
Petitioners contend that they were entitled to a “summary trial” before a jury of issues of fact before any order for arbitration could be made. The consideration of this contention requires a brief analysis of
Thus the word “default,” as used throughout the section, obviously refers only to the “default” of a party in refusing to proceed to arbitration as agreed rather than to a default by a party under the main provisions of the parties’ contract. As was said in Pneucrete Corp. v. United States Fid. & Guar. Co., 7 Cal.App.2d 733, at page 740 [46 P.2d 1000]: “The default mentioned in
Turning to the record before us, we find that the material facts are not disрuted. John A. Nelson, Incorporated, filed a verified petition for an order directing that the Weimans proceed to arbitration in the manner provided by the agreement of the parties. Admittedly, that petition сontained all the allegations required for that purpose. The petition was set for hearing for May 28, 1958, and notice of the hearing was served on the Weimans. They filed no answer denying any allegations of the petition, and they did not “on or before the return day of the notice of application” (
With respect to the first issue of law, the admitted facts showed that John A. Nelson, individually, was at all times a licensed contractor; that he made the construction contract with the Weimans in his individual capacity; that thereafter he incorporated as John A. Nelson, Incorpоrated, and assigned the contract to the corporation; that the corporation was thereafter duly licensed during the course of the construction and has since remained duly licensed at all times, but thаt there was an interval between the time when the assignment was made by John A. Nelson, individually, to John A. Nelson, Incorporated, and the time when the corporation became duly licensed. The parties submitted briefs on this matter between
With respect to the second issue of law, the agreement of the parties was before the court. It made no express or implied reference to any “condition precedent” to arbitration unless the existence of a “disagreement” could be so considered. It contained the customary provision for supervision by the architect and for рayments to become due upon certification by the architect. While it provided that the decisions of the architect should be “final and conclusive,” it also provided in article 18, that “All his decisions are subjеct to arbitration.” As above indicated, the agreement further provided that “Any disagreement arising out of this contract . . . shall be submitted to arbitration.”
In order to understand the Weimans’ position concerning the secоnd issue of law, we may turn to their counsel‘s statements in the trial court. Counsel referred to this contention as the “crux of the problem here,” and after conceding that Nelson had sought arbitration and that the Weimans hаd refused to proceed to arbitration, he said: “We told them that this particular contract does not provide for arbitration except after the condition precedent in said contract is met. And whаt is that condition precedent? The condition precedent is that this particular building must be satisfactorily completed, and that the architect who has been paid must pass on this building.” In other words, counsel was urging the necessity for a judicial determination, as a “condition precedent” to an order for arbitration, of the very questions which were to be presented to the arbitrators under the agreement to arbitrate. Nо such construction can be placed upon the agreement, more particularly in the light of the parties’ express agreement that “any disagreement” should be “submitted to arbitration” and that the architect‘s decisions should be “subject to arbitration.”
It is true that Mr. Weiman testified and endeavored to take the position that the dispute was between the architect and the contractor rather than between the Wеimans and the contractor. It nevertheless was conceded that the contractor had demanded from the Weimans the fourth payment of
Even if it be assumed that the Weimans could have raised appropriate issues of fact requiring a “summary trial” without filing any pleading in the proceeding in the trial court, it appears clеar from what has been said that they failed to raise in any manner any appropriate issue of fact. On the contrary, the making of the agreement for arbitration and their refusal to proceed to arbitration were all admitted facts. Thus there was no appropriate issue of fact to be determined by either a court or jury in any “summary trial” under
In view of our conclusion that petitioners raised no appropriate issue of fact to be determined by a court or jury in any “summary trial,” it becomes unnecessary to discuss the effect оf petitioners’ failure to demand a jury trial “on or before the return day of the notice of application,” as provided in
The petition for a writ of prohibition and a writ of mandate is denied.
Gibson, C. J., Shenk, J., Carter, J., and Traynor, J., concurred.
McComb, J., dissented.
Petitioners’ application for a rehearing was denied April 8, 1959. McComb, J., was of the opinion that the application should be granted.
