47 Md. 177 | Md. | 1877
delivered the opinion of the Court.
When the case of Heise & Company, and others, against the present appellees was before this Court at the October Term, 1875, reported in 44 Md., we declined passing upon the question, then discussed by counsel, as to whether the sureties in the bond of Siegman & Jones, the contractors, were discharged by reason of the facts there alleged ; those facts depending as they did upon a conflict of evidence. We declined deciding the question, supposing it to he more appropriate that the conflicting evidence should be passed upon by a jury; and there was also the further reason, that all the parties obligated by the bond were not then before the Court. As no definitive order or decree could then be passed against the bond, to bind all the parties thereto, we deemed it proper to remit the whole question of the liability of the bond to a Court of law. That question has been properly raised by an action on the bond, and has been decided adversely to the defendants, the present appellants, and from that decision they have taken this appeal.
The case was tried in the Court below before the Judge, acting in the double capacity of Court and jury. Each party, at the close of the evidence, tendered certain legal propositions, which they prayed to be affirmed by the Court and- taken as rules for its decision upon the facts that might be found. The Court filed in the case a written opinion, which appears in the record, and in which are discussed both law and fact; and in the conclusion the several propositions offered by the parties are ruled upon
The bond sued on recites that Siegman & Jones, by their contract of the same date of the bond, had contracted with the appellees to erect and complete a church, according to the plans and specifications, and upon the terms and conditions mentioned in the said contract; and the condition of the bond is, that the contractors should well and faithfully fulfil said contract, and in all respects perform and keep all and singular the stipulations on their part to be done and performed under the same. The breaches assigned are, that the contractors failed to erect, finish and complete the building and works in the time, with the materials, and in the manner provided for by the contract, or according to the plans and specifications in the contract referred to ; and further, that the contractors did not find, provide and deliver at their own cost and charge, free from all claims, liens, and charges whatsoever, all the work and materials necessary and proper for the complete execution of the building, as they were bound to do by their contract.
The sureties resist recovery on the bond, and take the defence that they have been discharged, by reason of cer
These matters were all made subjects of legal propositions submitted to the Court by the appellants, but which were refused.
With respect to the general principle relied on by the appellants, there'is really no question. All the difficulty consists in its application to the particular facts of this case.
It is perfectly well settled that a surety has the right to' stand upon the very terms of his contract; and if such contract be altered or varied in any material point without his consent, so as to constitute a new agreement varying substantially from the original, he is no longer bound. Mayhew vs. Boyd, 5 Md., 102; Miller vs. Stewart, 9 Wheat., 680 ; Whitcher vs. Hall, 5 B. & Cr., 269 ; Bonar vs. Macdonald, 3 H. L. Cas., 226, 239. And any subsequent addition to, or deviation from the contract, is such an alteration as will discharge the surety. But if, by the terms of the original contract, additions to or alterations in the work are provided for, or left to the judgment and discretjon of the other contracting party, either without limit or within certain limits, then the variation, if within the limits prescribed, is allowed by the contract itself, and the surety cannot complain of a variation which
The original contract referred to in the bond, provided, among other things, that the contractors should find, provide and delivery at their own cost and charge, free from all claim, liens and charges whatsoever, all and every kind of material, and work and labor which might “ be necessary and proper for the complete execution of the building, and erect, build, finish and complete, in a good and perfect manner, (to the entire satisfaction of the architects,) the buildings and works, agreeably and conformably, in all and every respect, to the specifications, drawings, dimensions, and explanations which may become necessary, according to the true intent and meaning of the drawings, and specifications.” It is further provided, that if it should appear that any of the work intended to be done, was not fully explained and detailed in the specifications and drawings, the contractors should apply to the architects for such further detailed explanations, and perform their orders as part of the contract. Then follow these important provisions : —
“And it is distinctly understood and hereby agreed, that should the building committee appointed by said congregation desire to make any change from the drawings or specifications at any time during the progress of the works, the same shall be carried out by said Siegman & Jones without making void or in any manner affecting this contract.
“Such changes, whether in addition to or deduction from the original works, shall be specified in writing, signed by the contractors, the architects, and the building committee. The sum to be paid or allowed for. such
In another paragraph, it is stipulated that the work should be commenced immediately after signing the contract, and that the basement portion of the building should be completed and delivered up to the appellees on or before the 1st of July then next, and that the entire building should be completed and delivered up on or before the 1st of November then next, under penalty of $25 per day for every day the work should be delayed beyond the time specified; “and this condition not to be made void by any alterations, or additional works being performed, but, in such case, the time shall be extended as shall be deemed proper by the architects, and specified in the written agreement for the additional works; and an additional month be allowed in reference to the completion of basement and entire building, in case piling is necessary.”
The contract containing these provisions was executed on the 22nd of January, 1812, by the contractors, and by the appellees by their building committee, consisting at that time of twelve members.
We fully concur with the Court below in its construction of the contract. We think it clear that the additions and alterations were all within the contemplation of those provisions of the original contract to which we have referred. The power to make additions and alterations, as we have seen, was plainly reserved, and was of the most comprehensive nature; and to say that the additions and alterations that were actually made were not within the reservation, would be placing such a restriction upon the terms of the contract, as is neither justified by any rational rule of construction, nor consistent with the manifest design of the parties. As is well observed by
And then, as to the manner of executing the specifications or supplemental contracts, in regard to the additions and alterations, we think they were substantially in compliance with the original contract. Those in regard to the extension of the building, and the change in tbe foundation, were signed by the contractors, the architects, and eight persons as a building committee. The price to be allowed for the work was fixed in both; and, as we must suppose, by the judgment and approval of the architects. But it is contended, that inasmuch as the original contract was signed by a building committee consisting of twelve persons, the contractors and their sureties had a right to expect that the committee would continue to be composed of the same number; and that, as the supplemental contracts or specifications were signed by only eight of such committee, instead of twelve, such supple
Then, as to the specification in regard to the moveable pews, that was signed by the contractors, the architects and the building committee by their secretary. The price was also fixed in this specification; and the only question is, whether it was signed by the committee as required by the contract. If the secretary signed for the committee, and by their authority, as the Court was required to find,
The other small modifications that occurred in the mere detail of the work as it progressed, have not been seriously pressed; but the only prayer of the appellants that refers to them is the third, and that prayer, being objectionable upon several grounds, was properly refused. It was specially objectionable, because it concluded against the appellees’ right to recover, if the Court should find that such modifications were made, without any reference whatever to the evidence given in explanation of them, and the circumstances under which they occurred.
The only remaining question is that in regard to the failure of the appellees to extend the time for the additional work. But upon examination of the contract, we find that that matter was left exclusively to the architects, and if they did not deem the extension of time necessary or proper, of course there was no extension given; and as the supplemental contracts are silent upon the subject, we may suppose that such extension was not asked for or deemed necessary.
It follows from what has been said that the Court below was correct in affirming the legal propositions offered by the appellees, and in rejecting those on the part of the appellants; and the judgments appealed from must he affirmed.
Judgments affirmed.