*3 job revenues all minus site costs with re- WILKINS, Before WIDENER and spect to this work.” J.A. 40. The Judges, ALARCON, Circuit Senior percentage a sliding increased on scale as Judge, Circuit of the United States Court profit amount of increased. Both Circuit, of Appeals for the Ninth sitting agreements provided that interest would designation. accrue on payments late at an annual rate percent. of 15 OPINION government Griffin was awarded the PER CURIAM. subject contracts that were the of the two Services, Griffin Incorporated appeals In calculating its “Net Prof- in this contract action it” for purpose making payments its WEGCO, brought by WEGCO, Incorporated. Grif- all Griffin identified revenues fin argues primarily that government Seventh from the contracts and then agreement, also executed a third to the issues before us. Agreement,” the "Parr which is not relevant costs, only argued than rather “Net Profit.” WEGCO deducted direct from rev- costs should be subtracted methodology, indirect direct costs. Under this itself and noted Griffin were not deducted. enues costs such overhead law- this before the employed methodology subsequently concluded Employing suit was commenced. perform had failed to some opined methodology, expert required by agreements, services “at least eventually that WEGCO was owed notified WEGCO that New terminating $144,404.97 plus on interest” under the “at Agreement, J.A. basis. $84,284.34 plus least interest” under termination challenged id. at 98. Agreement, *4 and, diversity filed in March revenues evidence Griffin’s in Court action the United States District testimony expert’s and calcu- and costs the of Virginia. for Eastern District As is “Net that data account- lating Profit” here, alleged relevant that Griffin WEGCO period July 1998. ending ed for the to agreements failing pay the breached produced damage no evidence WEGCO sought the fees due. WEGCO mon- period, al- any subsequent calculations declaring, ey damages judgment and a in- the present it did evidence that though (a) alia, to pay ter that failure Griffin’s to in agreements continued be effect. agreements monies under due the consti- contract; (b) prelitigation tuted a was conduct notwithstand- breach Griffin Its obligated pay owing ing, position to the at trial that monies then took Griffin agreements the as well as monies that all costs—both direct and indirect—should (c) future; to would be due the and the from revenues order subtracted methodology Profit.” The agreements continued to be valid and bind- determine “Net yielded possible and could be terminated. advanced two WEGCO Griffin requested agree- agreement: also an the for each was accounting of results WEGCO answer, $16,124 $15,766 allegations ments. In its either for the overpaid Griffin’s or underpaid a claim included that WEGCO had breach- New Alexandria and $20,763.11 $18,962.30 the the agreements. ed Griffin also demanded either jury trial on all City Agreement. issues. Kansas trial, During discovery, sought conclusion of the WEGCO infor- At the the special finding, mation it in determining that would assist returned a here, the due under amount relevant that WEGCO had not Prior that discovery agreement; to the close of on October breached either Griffin 30, 1998, requested agreements by failing had produced Griffin breached both WEGCO; ending July period pay information sums due supplemented never its dis- damage Griffin “the total amount covery responses discovery after close of caused Griffin Services’ fail- WEGCO ure compel. pay and WEGCO never moved to to WEGCO what it was due” was $64,000 Agree- for the New Alexandria trial, ensuing jury During par- $75,000 ment and for the Kansas regarding ties introduced evidence wheth- 1099,1101. Agreement. Id. at had er Griffin breached the dismissed, damages if and how should be calculated After WEGCO Concerning dam- breached. moved for diverging ages, advanced theo- continued to be effect requested accounting ad- regarding interpret ries how to term to determine allegedly ditional due amounts WEGCO cember 1997 for New Alexandria agreements through Agreement) July under the the date of the auditor appropriate WEGCO’s motion. WEGCO further re- could not calculate the sliding- quested that this calculation be percentage made scale needed to calculate an independent using compensation. Accordingly, accountant the meth- WEGCO’s odology advocated at compensa- WEGCO had trial. auditor did not calculate the Finally, tion prayed Griffin be owed to ordered pay City Agreement, monies that and it calculated the the accounting determined to be amount due. owed WEGCO under New motion, opposed maintaining Agreement only for the period granting through additional relief would vio- from December November late its to a trial. period, 1999. As to this the auditor determined that the “Net Profit” was The district court determined that the $274,663.06and Griffin owed award included for the peri- $102,331.53 $4,134.34in plus interest. ending July od and therefore no period recalculation of for that adopted district court the findings However, was necessary. the district in the report supplemented auditor’s *5 granted declaratory court a judg- findings those its own with determinations. ment that Griffin not terminated the The court that concluded Griffin owed they valid, and that were still $5,485.54 $1,371.39 in plus inter- binding, and in The district effect. court est under Alexandria Agreement the New accounting also ordered an of profits 1,1998 net period August for through the by government received Griffin for the 30, November 1998. The district court agreements. underlying contracts the The further that determined Griffin owed district court directed that the method for $27,775.86 $6,131.14 plus in inter- in calculating “Net Profit” the accounting City est under Agreement the Kansas would be that at proposed by trial 1, period the August through of 1998 Feb- expert. The district 28, court stat- ruary 1999. A final was then receiving that upon ed and verifying $286,229.80, the against entered Griffin for accounting, results of $139,000 the it would order represented of which the declaratory relief in the amount due. $147,229.80 The verdict and of which represent- court also ordered Griffin allow ed the supplemental awarded concerning WEGCO access to its records the district court. underlying year
the twice a contracts
the duration of the II. accounting The the ordered district argues Griffin first the district encompassed period from August the court erred in supplementing WEGCO’s 1, 28, February 1998 through 1999 for the damage its breach award on of contract City Agreement August and from failure-to-pay agree. We claims. 1, 30, through 1998 November 1999 for the pro Amendment Seventh New Agreement. Because the vides that auditor could not determine how much of law, damage [i]n the awards the allocated to Suits at common where the controversy in period beginning twenty between the of value shall exceed (March dollars, 1, respective years right by jury of trial shall be contract 1998 preserved, jury, fact tried for the Kansas and De- and no a
73
Wood,
469, 476-77,
Queen,
Inc. v.
369
shall
otherwise reexamined
U.S.
be
(1962);
States,
Wyler
Maryland will not “ordinarily enforce a
service,”
receive unwanted
personal
contract for
advice and services and
the reason
being that
to maintain a
likely
relationship
“the mischief
that would
result
him,
from the enforced continuance of the rela
especially
obnoxious to
considering
tionship incident to the service when it has
present
hostility. A contract for pro
personally
become
obnoxious to one of
advice,
viding
personal
whether it be for
or
great
is so
that the best interests
purposes,
business
will
long
abide
so
society
require
be re
as confidence and trust
remain. When
Michael,
fused.”
Fitzpatrick
See
vanish,
aspects
these
possibility
(1939).
Md.
9 A.2d
Fitz
successful enforcement
a relationship
patrick refused to enforce a
contract
based on them also vanishes
specific
which an
man
elderly
whimsically, arbi
performance is
inappropriate.
therefore
“
trarily
unjustly
refused to honor a
‘It is not for the
society
interest of
contract to provide a home in return for
persons who are not desirous of maintain
personal
long
services of a
time nurse
personal
continuous
relations with one
companion.
The court reasoned that
compelled
another should be
so to do.’”1
specific performance
personal
of the
ser Fitzpatrick,
would
him to accept
personal
personal
contracts, specific perfor
service
employee
service of an
against his wish
will,”
mance and
equivalents
inappropri
are
and his
Fitzpatrick, 9 A.2d at
judicial
ate because
exactly
supervision
per
pertained
situation which
here.
required
formance
agree
Under the terms of the
these services
services
ments,
provide
is to
long
business ad
would be of
duration and
vice and services to Griffin.
It is clear
potential
becoming quite
has the
diffi
1. This
excep-
example,
contract does not fall under the
tracts.
For
the New allowing specific performance
tion
Agreement
of some
states that “this
shall
personal
party
service contracts where the
any gov-
remain in effect for the duration of
contract,
rendering
substantially
fully
the service
including any
has
or
ernment
and all ex-
less,
tensions,
performed.
modifications,
Ledingham
Bay
options,
change
See
extra
(1958)
orders, novations,
(enforcing
Md.
145 A.2d
or follow-on con-tracts.”
contract
example,
to make will to devise one half inter-
For
should Griffin seek an extension
contract,
plaintiff
fully
est in land where
government
rendered
or
renewal
personal
agree-
required
Agree-
services in accordance with
WEGCO would be
ment);
Stubbs,
Snodgrass v.
negotiating
op-
189 Md.
to “assist
renewal
(Md.1947).
circumstances,
A.2d
See also Stama-
Under
tions.”
these
"
Service,
'[cjontracts
tiades v. Merit Music
210 Md.
follows the Illinois rule that
(1956) (granting injunction
stipulate
77
Estate,
526, 129
212 Md.
Storch,
In In re Carlin’s
had to future Fed.R.Civ.P. recognizing its mistake fail-
Perhaps argue for future prove, or even preserve seeks to
damages, WEGCO although split it has its cause
position Maryland prohibited
action as law. excluding by the court as and B-16 which was treated district Instructions number B-15 given objection, un- jury, proof were without if future certain reading any ordinary law der either future it has damages. contemplate the award of future waived them or received them. Micrographics Systems, Inc. v. See National and cold at not be allowed to blow hot should Inc., OCE-Industries, Md.App. time, same indeed it offered instructions (1983). special The fact that A.2d 862 B-15 and B-16. form, to, objected which also was not
