Weeks Marine Inc v. Fireman's Fund InsWeeks Marine Inc v. Fireman's Fund Ins
Plaintiff-Appellant Weeks Marine, Inc. (“Weeks“) appeals the district court‘s order denying its motion for summary judgment and granting Defendant-Appellee Fireman‘s Fund Insurance Company‘s (“FFIC“) motion for summary judgment. We reverse and remand for entry of judgment in favor of Weeks.
I. FACTS AND PROCEEDINGS
This surety contract dispute arises from dredging work that Weeks Marine completed for now-bankrupt shipbuilder Friede Goldman Offshore Texas, L.P. (“Friede Goldman“). In April 1998, Petrodrill Construction, Inc. (“Petrodrill“) contracted with Friede Goldman (“the shipbuilding contract“) for the construction of a semi-submersible drilling vessel (“Hull 1829“). In conjunction with the
one having a direct contract with the Principal or with a Subcontractor of the Principal for labor, material, or both, used or reasonably required for use in the performance of the Contract, labor and material being construed to include that part of water, gas, power, light, heat, oil, gasoline, telephone service or rental of equipment directly applicable to the Contract.
Friede Goldman began construction of Hull 1829 at its shipyard in Pascagoula, Mississippi but eventually elected to complete construction at another shipyard in Orange, Texas. The parties vigorously dispute the cause of the move: FFIC maintains that Friede Goldman merely wanted to “keep that [Texas] yard busy“; Weeks asserts that the move was “necessary,” but offers no further explanation. It is undisputed, however, that all parties (including FFIC) expressly approved the move. In fact, Petrodrill and Friede Goldman agreed to a $3 million increase in the contract price, and FFIC consented to a corresponding increase in the amount of the bond. These modifications were memorialized in “Amendment No. 2” to the shipbuilding contract.
In connection with the move, Friede Goldman subcontracted with Weeks to dredge a slip extension at the Texas shipyard. Weeks
Shortly after Friede Goldman filed for bankruptcy protection, Weeks filed suit against FFIC, invoking diversity jurisdiction and alleging that FFIC, as surety, is liable for the “labor performed and materials furnished” to Friede Goldman in connection with its performance of the shipbuilding contract. FFIC denied liability and the parties filed cross-motions for summary judgment. The district court granted FFIC‘s motion, concluding that “making FFIC pay Weeks would not serve the Bond‘s overriding purpose of preventing the attachment of liens to Petrodrill‘s new vessel.” Weeks now appeals the denial of its motion and the grant of FFIC‘s motion.
II. ANALYSIS
A. Standard of Review
We review a grant of summary judgment de novo, applying the same standard as the district court.1 A motion for summary judgment is properly granted only if there is no genuine issue as
B. Merits
The sole issue presented in this appeal is whether Weeks‘s dredging of a slip extension at Friede Goldman‘s Orange shipyard is “labor” “used or reasonably required for use” in building Hull 1829. The construction of an unambiguous surety agreement is a question of law.5 Surety agreements, like other contracts, are “interpreted to ascertain the obligations intended by the parties, gathered from the instrument as a whole.”6 The liability of a surety is determined by the language of the bond.7 When, as here,
With these general rules of contract interpretation in mind, our analysis begins with the written terms of both the shipbuilding contract and the payment bond. The shipbuilding contract called for Friede Goldman to construct Hull 1829 for Petrodrill and perform all associated engineering, launching, and testing of the completed vessel. This contract defines “materials” as “all material and supplies, including without limitation all machinery, equipment, outfittings and spare parts...to the extent that same have been appropriated to, or incorporated in, the Vessel.” The shipbuilding contract does not define “labor.”
The bond prescribes the obligations of FFIC. The bond states expressly that FFIC is liable only if Friede Goldman fails “promptly [to] make payment to all claimants” “for all labor and material used or reasonably required for use in the performance of the Contract.” As noted earlier, the term “claimants” is defined in the bond, which also defines “labor and material” to include “water, gas, power, light, heat, oil, gasoline, telephone service or rental of equipment directly applicable to the Contract.”
Our resolution of this contract dispute rests on the plain language of the bond and the uncontroverted record evidence. We have seen that, under the bond, a “claimant” is “one having a direct contract with the Principal [Friede Goldman]...for labor, materials or both, used or reasonably required for use in the performance” of the shipbuilding contract. The parties do not dispute that Weeks had a direct contract with Friede Goldman or that Weeks provided “labor.” Rather, FFIC contends that the labor Weeks provided was not used “in the performance of the contract.” For at least three reasons, we disagree.
First, in support of summary judgment, Weeks submitted the affidavit of Friede Goldman officer John Haley who stated that “[t]he labor and materials provided by Weeks” were “required by
Finding little support in the express terms of the bond, FFIC relies on cases arising under the Miller Act and analogous state statutes to support its argument that dredging is a capital improvement and is not encompassed by a standard labor and material bond. Under these cases, “material” includes “things which will be incorporated into the project itself, such as steel beams, brick, window frames, flooring and roofing.”10 “Materials” also includes products that are not ultimately integrated into the project, but
FFIC‘s reliance on these authorities is misplaced for several reasons. First, and most importantly, Weeks is seeking payment for “labor,” not “materials.” Weeks agrees that the pipes, tools, and heavy machinery used to dredge the slip are not “materials” covered by the bond; Weeks only seeks payment for labor, and then only labor that was “used or reasonably required for use” in Friede Goldman‘s performance of the shipbuilding contract. Perhaps understandably, FFIC largely ignores this fundamental distinction.13
Second, even if we were to accept FFIC‘s capital-improvement argument, the competent summary judgment evidence reveals that Weeks‘s dredging was not a capital improvement to Friede Goldman‘s
The only evidence that FFIC proffered in support of its argument is the affidavit of FFIC claims adjuster Fred Applewhite, who stated conclusionally that “[m]aking a slip at a shipyard bigger by constructing a slip extension...is a capital improvement to [Friede Goldman]‘s yard and clearly of a nature as to be available for use...for all of [Friede Goldman]‘s projects.” On close examination, however, it is obvious that Applewhite‘s affidavit is merely a reiteration of FFIC‘s legal argument, i.e., that dredging is always a capital improvement. Notably, Applewhite‘s affidavit is bereft of any explanation or reasoning as to how he reached this bald conclusion. It never even indicates that he personally inspected the slip. “[S]uch conclusory, unsupported assertions are insufficient to defeat a motion for
The litany of cases that FFIC cites in support of its argument is equally unpersuasive. All these cases stand for the undisputed proposition that the cost of capital equipment that is not “substantially consumed” during performance of a contract is not recoverable under a typical Miller Act payment bond.16 As we explained, these cases are inapposite for three alternative reasons: (1) A cause of action under the Miller Act is not congruent with a claim under the particular language of a tailor-made bond; (2) Weeks is seeking to recover only for labor, not materials; and (3) the dredging at issue was, according to the uncontradicted statement of Friede Goldman officer John Haley, “substantially consumed” in the construction of Hull 1829. We again emphasize that Weeks, unlike the suppliers in the cases that FFIC cites, does not seek payment for pipes, machinery, tools, or
III. Conclusion
For the foregoing reasons, we reverse and remand for entry of judgment in favor of Weeks in the principal amount of $654,671, together with any and all appropriate ancillary items, such as pre- and post-judgment interest and costs, including attorney‘s fees, if applicable.
REVERSED and REMANDED with instructions.