R. Kent WEBB, Petitioner,
v.
NORTH CAROLINA DEPARTMENT OF ENVIRONMENT, HEALTH AND NATURAL RESOURCES, COASTAL RESOURCES COMMISSION, Respondent.
Court of Appeals of North Carolina.
*31 Parker, Poe, Adams & Bernstein by Charles C. Meeker and John J. Butler, Raleigh, for petitioner-appellant.
Atty. Gen. Lacy H. Thornburg by Asst. Atty. Gen. Robin W. Smith, for respondent-appellee.
PHILLIPS, Judge.
In appealing from the Superior Court's affirmance of the Commission's decision, the appellant petitioner in effect makes three contentions. None has merit and we affirm the order of the Superior Court.
Petitioner's first contention is that the Commission's decision rejecting the Administrative Law Judge's recommended decision is erroneous as a matter of law because the reasons stated for rejection are either not specific or manifestly inaccurate. In making this contention, and the next one as well, petitioner fails to take into account the conflicts in the evidence and the Commission's prerogatives to determine the credibility of witnesses and the weight of evidence, and to find facts therefrom. State ex rel. Commissioner of Insurance v. North Carolina Rate Bureau,
1. The greater weight of the evidence in the record as a whole does not support several of the Administrative Law Judge's findings of fact. Some of the findings rely on evidence that was not properly weighted in view of the totality of the evidence; other findings contain selective statements of fact and fail to reflect the record as a whole. One of the key findings of factthe finding that DCM staff relied on the surveyed mean high water line to establish the permitted bulkhead alignmenthas no real basis in the record and directly contradicts the testimony of DCM staff as to the origin of the DCM alignment.
2. The basic premises of the Recommended Decision are flawed in that the Administrative Law Judge framed the issue as a conflict between the surveyed mean high water line and a mean high water line based on natural indicators. The uncontroverted evidence is that CAMA Major Development/Dredge and Fill Permit 181-88 authorized bulkhead construction at an alignment staked by DCM staff based on observation of the high water level on the property and did not authorize construction at the surveyed MHW line; the permitted alignment was approximately one (1) foot landward of the surveyed MHW line and the bulkhead was constructed approximately one foot landward of the permitted alignment.
The court determined that: "In compliance with NCGS 150B-36, the agency's final decision states the specific reasons why the agency did not adopt the Administrative Law Judge's recommended decision." Petitioner argues that the Commission's generalized assertion that the evidence does not support "several" of the Administrative Law Judge's findings of fact is insufficient to comply with the requirements of G.S. 150B-51(a), as the particular findings of fact are not identified and no explanation is given why they are not supported. But the statute does not require a point-by-point refutation of the Administrative Law Judge's findings and conclusions and the reasons stated, the flawed premises of the recommended decision as to the mean high water line, are quite specific indeed and go to the heart of the case.
Petitioner's next contention is that the Commission's findings of fact, conclusions of law and final decision are not supported by substantial evidence in view of the entire record and that the order is arbitrary and capricious. The standard for *32 judicial review is set forth in G.S. 150B-51(b), which states in pertinent part:
[T]he court reviewing a final decision may affirm ... or remand.... It may also reverse or modify the agency's decision if the substantial rights of the petitioners may have been prejudiced because the agency's findings, inferences, conclusions, or decisions are:
. . . . .
(5) Unsupported by substantial evidence... in view of the entire record as submitted; or
(6) Arbitrary or capricious.
In reviewing the Commission's decision for the errors cited, the court properly applied the "whole record" test. Brooks, Commissioner of Labor v. Rebarco, Inc.,
Petitioner's final contention is that the Division's determination of approximate mean high water based on observation of high tide during a single inspection of the site was erroneous as a matter of law. CAMA regulations require only that a bulkhead alignment for the purpose of shoreline stabilization "must approximate mean high water or normal water level." 15A N.C.Admin.Code 7H.0208(b)(7)(A). The term "mean high water" is not defined by the regulations, nor is its method of computation prescribed. In the context of property ownership, our Supreme Court defined the term as "a mean or average high-tide, and not as the extreme height of the water," Carolina Beach Fishing Pier, Inc. v. Town of Carolina Beach,
Affirmed.
EAGLES and WYNN, JJ., concur.
