This suit was brought in justice’s court on July 3, 1907. The plaintiff filed a written declaration containing a special count alleging a contract, breach and damages, and the common counts, with bill of particulars' attached. The defendant pleaded the general issue and gave notice of justification for the discharge of plaintiff and a set-off. The case was tried in justice’s court before a jury, and on July 17,1907, a judgment was rendered in favor of plaintiff for $190. Defendant appealed the case to the circuit court and on September 25, 1907, it came on for trial before a jury.
Counsel for plaintiff in his openiúg statement said that plaintiff and her daughter, Anna, were employed by defendant as domestics at defendant’s summer home near Muskegon, Michigan, for a period .from about June 21, 1907, to such time as defendant should leave said summer home, but to at least October 1, 1907; that after plaintiff and her daughter had worked for defendant under this contract for about ten days’, they were discharged by defendant without cause; that this suit was then instituted to recover the wages plaintiff and her daughter had already earned and damages for breach-of the contract on the part of defendant.
After the opening statement had been made, and before any evidence had been introduced, the trial court made a ruling that - plaintiff would be limited to recover such damages only as had accrued from the date of her discharge by defendant to the date of trial in justice’s court, a period of 17 days. To this ruling plaintiff’s counsel excepted.
Plaintiff’s counsel contended that, if the rule adopted
The assignments of error are discussed by counsel under two heads:
First. The court erred in holding that plaintiff could not recover damages for the whole contract period, but that she was limited in her recovery to such damages as had accrued at the time of the trial in justice’s court.
Second. The court erred in not allowing plaintiff to recover such damages as had accrued up to the time of the trial in circuit court.
Before proceeding to discuss the two heads presented by counsel for appellants, some attention must be given to the contention of counsel for defendant. It is claimed the verdict was a consent verdict and not appealable. We do not so understand the record. The plaintiff claimed the right to prove her damages in full, but the court ruled she could not make proof of damages later than the date of trial in justice’s court. Exception was duly taken and the action of the court is reviewable.
• It is claimed the special count is not for a breach of the contract, but is an action on the contract to recover plaintiff’s wages. We do not agree with this contention. The special count set out the contract and its breach. A bill of particulars was filed, one item of which reads:
“ To damage by breach of contract being what plaintiff and daughter would have earned if allowed to complete contract, $144.”
Under her plea, defendant gave notice of justification for the discharge of plaintiff and her daughter. The defendant was not misled. See Costello v. Ten Eyck,
We now come to the important question and that is,
In Cutter v. Gillette,
“The remaining question is whether the jury should have been allowed to assess damages for the period of time subsequent to the trial. The plaintiff was hired for five years from April 25, 1892, and was discharged about the middle of July, 1892. He brought suit on November 10,1892, and the verdict was rendered on March 14,1894. The verdict assessed at the sum of $3,180.95 the plaintiff’s whole damages for breach of the contract for hiring, and stated that of the amount $1,392.95 was the damage to the time of trial. The defendant concedes that the plaintiff is entitled to recover damages for an entire breach, so far as such damages can be ascertained, but contends that, as the trial occurred before the expiration of the contract period, it was impossible for the jury to ascertain or assess the damage for the unexpired portion of the contract period subsequent to the time of trial. In support of this contention defendant cites the cases of Colburn v. Woodworth, 31 Barb. (N. Y.) 381, Fowler v. Armour,
/“ Such would seem to be the rule in Pennsylvania. See King v. Steiren,
To the same effect are the following cases: Blair v. Laflin,
The rule of damages stated in these cases is in harmony with the rule approved in Brighton v. Railway Co.,
Judgment is reversed, and new trial ordered.
