220 S.W. 857 | Mo. | 1920
Lead Opinion
The defendant Gilsonite Construction Company had a contract with the Anheuser-Busch Brewing Association to erect a large building on Block 884 *632 in the City of St. Louis. The Gilsonite Construction Company thereupon made a contract with the plaintiff, Webb-Kunze Construction Company, to do all the excavating for the building. After the excavation was finished satisfactorily to all parties, the plaintiff and the defendant Gilsonite Construction Company disagreed as to the method of measuring the work done in making the excavation. Thereupon the plaintiff filed its mechanic's lien and sued the original contractor, Gilsonite Construction Company, and the owner, the Anheuser-Busch Brewing Association. A judgment was rendered in favor of the plaintiff, enforcing its lien in the sum of $2,975.64, and interest. This was in accordance with the defendant's theory of the way the work should be measured. The plaintiff claimed that the judgment should be for the full amount sued for $19,470.65, in accordance with the plaintiff's method of measurement. The plaintiff then appealed from the judgment.
The only dispute between the parties is as to the method of measuring the work done by the plaintiff. It is not disputed by respondent that if the method which plaintiff employed was correct it is entitled to judgment for the amount sued for, $19,470.65.
I. The difference arises in the application of the statute, Section 11971, Revised Statutes 1909, to the measurement of trenches and pier holes, as follows:
"Sec. 11971. Whenever measurements of earthwork, stone masonry work, brickwork, stone-cutting work, plastering work or roofing work is in any case hereafter required to be made forany purpose, and no special agreement as to the measurements has been made by the parties, the sameAgreed Measurements. shall be made and the quantity thereof ascertained in the following manner and by the following rules: Earthwork — EARTH EXCAVATION SHALL BE MEASURED BY THE CUBIC YARD. To ascertain the number of cubic yards of excavation made, take the length and multiply the same by the width and by the average height; the result will give the number of *633 cubic feet, which, divided by twenty-seven, will be the amount of cubic yards. For all trenches and pier holes, double measurements shall be allowed. When earth is left in a cellar to protect the adjoining banks or walls, the same may be charged double the amount when required to be removed."
If the pier holes and trenches excavated by the appellant are given double measurements, as provided in that section, then it is entitled to the full amount sued for. The respondents claimed, and the trial court held, that the plaintiff was not entitled to the double measurements, provided in the section because there was a "special agreement as to measurements" as mentioned in the section. That part of the agreement to which the respondent calls attention as to measurements is as follows:
"Article XXI. In consideration of the faithful performance of every provision of this contract, to the satisfaction of Gilsonite Construction Company and the architect, Gilsonite Construction Company will pay to the sub-contractor for all of this work and materials in place, under this contract, complete and accepted, the sum of excavation for all trenches including bracing and shoring, $1.15 per cubic yard.
"Excavation north of present railroad tracks forty cents per cubic yard.
"Excavation for pier holes under outside walls and three lines of piers, running east and west from north end of building with necessary bracing and shoring, two dollars per cubic yard."
It will be observed that the statute has this requirement: "Earth excavation shall be measured by the cubic yard." It then proceeds to provide how a cubic yard shall be determined; the length, breadth and thickness in feet shall be multiplied together and divided by 27 for ordinary excavation; for trenches and pier holes double measurements shall be allowed. That is to say, there shall be twice as many cubic yards in the same number of cubic feet in the excavation of trenches and pier holes *634 as there are in other excavations. Now that portion of the contract quoted above is not in contradiction of the statute. It only provides the price that shall be paid by the cubic yard; $1.15 a cubic yard for trenches and $2 a cubic yard for pier holes; 40c per cubic yard for other excavations. The "cubic yard" mentioned in the contract is controlled by the statute; it is a statutory cubic yard.
The statute necessarily applies to contracts for making earth excavations and must be read as a part of every contract of that character. [Isenhour v. Barton County,
Appellant, however, invokes a statement in the specifications attached to the contract as indicating a special agreement as to measurements. The contract provides, after setting out the work to be done:
"The whole to be in accordance with the drawings and specifications for the work and in strict accordance with the plans and specifications, drawings and details furnished by Widman Walsh, and Klipstein Rathmann, architects, hereafter referred to as architects and engineers, and by the Gilsonite Construction Company. The said plans, specifications, drawings and details in their entirety shall be considered as a part of this contract."
Turning to the specifications which the respondent claims furnished a special agreement as to measurements we find this: *635
"Proposals for the foregoing work are to be based upon the cubic yard:
"(1) For the trenches for retaining walls.
"(2) For the main body of the excavation, including removing old retaining wall on east side of Broadway and all other old walls or rubbish and loose natural rock which may be encountered.
"Estimates are to be based upon the actual amount of material removed according to surveys taken from time to time, and upon completion of the work, by a competent engineer employed by the owner."
We notice that this provision starts with the proposition that "proposals for the foregoing work are to be based upon the cubicyard." So far, we are in strict accord with the statute; a cubic yard, up to this point, must necessarily be a statutory cubic yard. Then follows immediately "(1) for the trenches for retaining walls." That certainly would be a statutory cubic yard for trenches. Pier holes are not mentioned in that part of the specifications. The concluding paragraph of that provision upon which the respondent laid stress is significant:
"Estimates are to be based upon the actual amount of material removed, according to surveys taken from time to time; and upon the completion of the work by a competent engineer employed by the owner."
The proposals are to be "based upon the cubic yard" — a statutory cubic yard, of course. When estimates are made "from time to time" and at the conclusion of the work, these estimates necessarily must be "based" upon the actual amount of material removed; else how could they ever arrive at the statutory cubic yard? The actual amount of material removed first must be ascertained in cubic feet, then all estimates are "based" upon that.
Everything required by those provisions of the specifications necessarily arises in the application of the statute. But the significant part of that passage in the specifications is the making of the estimates "by a competent engineer employed by the owner." The paragraph *636 was not put in for the purpose of indicating how measurements should be made, but for the purpose of providing who shall make the measurements; so that such measurements shall be under the control of the owner. If it had been intended to provide a "special agreement" for measurements, some language inconsistent with the statute as to what constitutes a cubic yard would have been used. The estimates are for the purpose of making payments, and are made after the measurements are furnished. There is no special agreement as to measurements in the specifications.
II. The respondent, however, asserts that the judgment was right because the parties had construed the contract so that pier holes and trenches were to be measured singly and not as provided in the statute. The contract required payments to be made in monthly installments of 85 per cent of the workInterpretation completed in the building, leaving a balance ofby Parties. 15 per cent of all the completed work unpaid, which balance should be paid when the work was entirely completed and delivered.
The defendants introduced a number of exhibits showing the estimates and settlements from time to time which they claim shows a construction of the contract according to their theory. There were several of those introduced in evidence and the following illustrate all:
"Exhibit `A'
Oct. 2, 1916.
"Gilsonite Const. Co. To Webb-Kunze Const. Co., Dr. "Excavation on Bevo Plant for A.B.B. Assoc., approximately as follows: Trench Work, 4,500 Cys. at $1.15 ..................... $5,175.00 Pit Work, 2,700 Cys. at .40 .......................... 1,080.00 Moving Heman's shovel on job, labor .................. 71.05 _________ $6,326.05" *637
"Exhibit `B'
Oct. 20, 1916.
"Gilsonite Const. Co., To Webb-Kunze Const. Co. "Approximate yardage on trench work for October: 2,000 Cys. at $1.15 ......................... $2,300.00 Less 15% ............................................. 345.00 _________ $1,955.00"
"Exhibit `C'
Nov. 1, 1916.
"Gilsonite Construction Co., Dr. To Webb-Kunze Const. Co. "Approximate yardage on Bevo Plant to date: Trench work, 10,203 cu. yds. at $1.15 cu. yd. ....... $11,733.45 Pit work, 2,700 cu. yds. at 40c cu. yd. ............. 1,080.00 Pier holes on 7th St., 160 cu. yds. at $2.00 cu. yd. 320.00 __________ $13,133.45 Less previous estimate ................ 8,528.95 __________ $ 4,604.50 "Extras on Pay Roll, week ending Oct. 19 $119.10 Extras on Pay Roll, week ending Oct. 26 192.92 _______ 312.02 __________ $ 4,916.52"
"Exhibit `D'
Nov. 24, 1916.
"Gilsonite Const. Co., To Webb-Kunze Const. Co. "Approximate yards of trench excavates from Nov 1st to Nov. 24, 1916. On 7th Street 130 ft. trench 1430 cu. yds. On Arsenal Bway. 90 ft. trench 990 cu. yds. _____ 2420 cu. yds. at $1.15 $2,783.00"
It will be noticed in each of these statements there was an estimated payment upon the number of cubic yards. The abbreviation in Exhibit A, "Cys." doubtless means cubic yards, as does the word "yardage"' in Exhibit B, and the expression "cu. yds." in Exhibit C. There is nothing in these statements to indicate that "cubic yards" means anything else than statutory cubic yards. There is nothing in any dimensions given in *638 those exhibits which would indicate that the amount of material taken out was in excess of what the statute provides. In "Exhibit D" the length of one trench, and perhaps the width of another, is given, but that is the only dimension. In one of the exhibits (not copied above) two dimensions of some pier holes are given, but in none are three dimensions given. The exact amount of earth removed in cubic feet cannot be determined; nor is there any evidence that the measurements were made and 27 cubic feet allowed for the cubic yards mentioned in these estimates.
Another provision of the contract is important also in considering the effect of settlements, even if the evidence had been more direct in support of respondent's theory. The contract has the following provision:
"Article XXVI. No payment made for work under this contract except the final payment, shall be conclusive evidence of the performance of this contract either wholly or in part, and no payment shall be construed to mean an acceptance of defective work or improper materials."
While that provision is to the effect that no payment shall be conclusive evidence as to performance, performance would necessarily involve interpretation of the contract, and it may well be doubted whether the exhibits offered were competent evidence, even if they tended to show what appellant claims.
It is true that the interpretation and construction which the parties themselves place upon a contract will be adopted by the court where the contract is ambiguous. That is, where the terms of the contract are reasonably susceptible of different constructions. [Meissner v. Ry. Equipment Co., 211 Mo. l.c. 133; Produce Co. v. Olsen,
The judgment is reversed and the cause remanded with directions to the trial court to enter judgment in *639 accordance with the prayer of the petition. Railey and Mozley,CC., concur.
Addendum
The foregoing opinion by WHITE, C., is adopted as the opinion of the court. All of the judges concur.