51 Ind. App. 379 | Ind. Ct. App. | 1912
— Appellant brought this action to recover a balance alleged to be due him on account of work done and material furnished by him in the construction of a brick building under a contract between him and appellees, Henry and Louis Brandt, doing business under the firm name of “Brandt Brothers”. The complaint also included an item designated an “extra”, for which recovery was asked. The case was tried by the court. There was a finding for appellant as to the one item of “extra”, $5.75, but against him as to his principal claim and for costs.
The facts in the case necessary to show the nature of the question presented are as follows: The firm, of Brandt Brothers was employed by appellee Brown under a general contract for the construction of a certain brick building on real estate situated in the city of Indianapolis and owned by said Brown. Brandt Brothers sublet the brick work to appellant, under the written contract, which is the basis of this action. "While the work was being done, the building inspector of Indianapolis discovered that certain tile partition walls, included in appellant’s contract, were not sufficient under the building regulations of said city, and ordered the metal or fire-proof walls to be substituted therefor. This latter class of work, not being in appellant’s line, was, by mutual consent, elimated from the contract, and the point in dispute in this action is the amount which should be deducted from the original contract price for this omitted work.
On these facts, appellant asked judgment against Brandt Brothers for $500, a foreclosure of his lien against the real estate, and that the same be declared superior to that of other named appellees.
A second paragraph of complaint differed from the first in that it averred that appellee Brown in his settlement with Brandt Brothers retained the full amount due appellant, and agreed to settle with, and to pay him the amount due under his contract with Brandt Brothers, and asked personal judgment against Brown and Brandt Brothers, etc.
To these paragraphs a general denial was the only answer filed. A cross-complaint filed by Brandt Brothers averred the execution of their contract for the erection of the building for Brown, and the completion of the same according to the terms of the contract; that after they had completed the work on said building they made a settlement with Brown of all claims and demands growing out of said building; “that at and prior to such settlement, the said George W. Brown represented to cross-complainants that he had
Appellant filed a motion for a new trial, which was overruled and exceptions properly saved. The ruling on this motion is assigned as error, and is the only ruling of the court below presented for review by appellant’s* brief.
The substance and effect of appellant’s position is that the trial court erred in admitting evidence under the general issue as to an alleged verbal agreement on the part of appellant made subsequent to the date of the original contract to allow a credit of $750 for the omitted work, resulting from the change in plans and specification required by the city building inspector. Appellant contends that such testimony should have been excluded in the absence of a plea of payment, counterclaim or set-off.
It is earnestly insisted, however, that the evidence should not have been considered by the court in any event, because it was outside the issues tendered by the pleadings, and that with this evidence excluded the decision of the court is not sustained by sufficient evidence and is contrary to law.
We agree with appellant in his contention that the decision of the court below must rest on this evidence, otherwise appellant should have recovered in some amount on his contract. We are therefore required to determine (1) whether such evidence was admissible under the issues tendered, and (2) if not admissible under the issues, when properly objected to, did the failure to make such objection, at the time the evidence was offered and admitted, deprive appellant of the benefit, on appeal, of questioning the sufficiency of the evidence to sustain a decision of the court below which necessarily rested in part on such evidence.
Our conclusion, that this evidence was admissible under the issues as tendered, makes unnecessary the decision of the second question above. ¥e may remark, however, in this connection, that there is some conflict in the decided cases on the question of whether the failure to object to evidence outside of the issues authorizes its consideration by the trial court. On this question see the following cases: Denbo v. Wright (1876), 53 Ind. 226, 229; Doherty v. Holliday (1894), 137 Ind. 282, 287, 32 N. E. 315, 36 N. E. 907; Chandler v. Beal, supra; Graves v. State (1889), 121 Ind. 357, 23 N. E. 155; Riehl v. Evansville Foundry Assn. (1885), 104 Ind. 70, 74, 3 N. E. 633; Webb v. Sweeney (1903), 32 Ind. App. 54, 69 N. E. 200; Stephens v. Lawson (1844), 7 Blackf. 275; Stewart v. Goodrich (1880), 9 Mo. App. 125, 127; 2 Elliott, Evidence §881.
Whether this conversation, in appellant’s absence, and standing alone, with the subject-matter of the same in no way brought to the knowledge of appellant, would have been admissible as a part of the res gestae of the agreement or arrangement made between the parties as to the work and material omitted from the contract sued on, we need not decide, because there was other evidence given in the case before this was offered and admitted, to the effect that the architect discussed the same subject with appellant and told him substantially what he told appellee Brandt, and that in response thereto appellant told him, in effect, to go ahead, that he would stand for the credit of $750. This other evidence given in the cause, to say the least, rendered the evidence objected to harmless.
We find no available error in the record.
Judgment affirmed.
Note.- — Reported in 99 N. E. 825. See, also, under (1) 3 Cyc. 388; (2) 38 Cyc. 1378, 1390; (4) 31 Cyc. 693; (5) 40 Cyc. 2687;