Weaver v. AcamporaWeaver v. Acampora
Appeal from an order and judgment of the Supreme Court (Mycek, J.), entered April 6, 1995 in Saratoga County, upon a decision of the court in favor of plaintiff.
Plaintiff contracted to construct a house and barn for defendants Ralph and Isabelle Acampora (hereinafter collectively referred to as defendants), for which they were to pay $210,000. In July 1993 — by which time the project was partially completed and plaintiff had received a total of $57,500 in contract payments — a dispute arose between the parties, as a result of which рlaintiff filed a mechanic’s lien against defendants’ property in the amount of $60,113.38 and defendаnts locked plaintiff out of the building site.
The parties’ adversarial attitude having hardened, plаintiff commenced this action for breach of contract, seeking damages and to fоreclose the lien. Defendants, in their answer, interposed affirmative defenses and cоunterclaims alleging, inter alia, willful exaggeration of the lien, breach of contract, fraud, abuse of process and intentional infliction of emotional distress. After a nonjury trial, Supreme Court fоund plaintiff entitled to recover $53,118.72, plus interest. Judgment was entered accordingly, and defendаnts appeal.
We affirm. The premise underlying much of defendants’ argument on appeal is that Supreme Court erred in declining to find that plaintiff had willfully exaggerated the amount of the liеn, by significantly overcharging for some additional work requested by defendants after constructiоn had begun, and by failing to subtract the cost of materials defendants supplied. While Supreme Court found that the actual cost of implementing defendants’ change orders was somewhat less than that claimed by plaintiff, the value of the changes was the subject of conflicting testimony, and we cannot say that it was unreasonable for the court to conclude that defеndants failed to show that the discrepancy was the result of an intentional or deliberatе overstatement, rather than merely an honest disagreement as to value (see, Jones Constr. Co. v Parklaw Realty,
Also unavailing is defendаnts’ contention that it was plaintiff, not they, who breached the contract first, by failing to abide by its requirement that all change orders be in writing, and by insisting on payment prior to completing the stages of construction set out in an amended payment schedule. Plaintiff’s testimony, which Supreme Court implicitly credited, established that defendants had agreed not to adhere rigidly to the amеnded schedule, had orally requested the changes at issue and had accepted the work performed pursuant thereto. Since the record provides no compelling rеason to discountenance this credibility assessment (see, New Day Bldrs. v SJC Realty,
With respect to the remainder of defendants’ contentions, it suffiсes to note that the filing of a mechanic’s lien, seeking recovery of an amount reasonably believed to be due for work performed on the property that is the subject thereof, does not, without more, constitute abuse of process {see, Key Bank v Lake Placid Co.,
' Mikoll, J. P., Mercure, Crew III and Peters, JJ., concur. Ordered that the order and judgment is affirmed, with costs.