OPINION and ORDER
Plaintiff brought this civil action for damages against defendant in the Circuit Court for Marathon County, Wisconsin, alleging negligence and breach of warranty in connection with a contract for pulp mill improvements. Defendant removed the action to this court pursuant to a timely notice of removal. The case is before the court on defendant’s motion for partial summary judgment with respect to plaintiff’s negligence claim and claim for consequential damages.
*969 Defendant contends that plaintiffs negligence claim must be dismissed because the economic loss doctrine precludes recovery in tort and that the claim for consequential damages must be dismissed because the contract between the parties does not permit recovery of such damages. I agree with defendant that Wisconsin’s economic loss doctrine precludes tort recovery for economic loss where there is a contractual relationship between two sophisticated parties, regardless whether the contract is for products or services. I conclude that the contract terms are not unconscionable and that plaintiff cannot seek consequential damages because such damages are excluded by the contract.
To succeed on a motion for summary judgment, the moving party must show that there is no genuine issue of material fact and that the moving party is entitled to judgment as a matter of law. Fed. R.Civ.P. 56(c);
Celotex Corp. v. Catrett,
For the sole purpose of deciding this motion for summary judgment, I find from the parties’ proposed findings of fact that the following material facts are undisputed.
UNDISPUTED FACTS
Plaintiff Wausau Paper Mills Company is a multi-million dollar corporation organized and existing under the laws of the State of Wisconsin, with its principal place of business located at One Clarks Island, Wausau, Wisconsin. Plaintiff manufactures various types of paper products. Defendant Chas. T.Main, Inc., is a multi-million dollar foreign corporation with its principal office and place of business located at Prudential Center, Boston, Massachusetts. Defendant provides professional engineering and design services.
Between March 1988 and June 1988, plaintiff and defendant entered into arm’s-length negotiations. On March 16, 1988, defendant submitted to plaintiff a proposed contractual agreement and a confidentiality agreement. On March 18, 1988, defendant submitted a proposal for design engineering services for plaintiff regarding plaintiff’s continuing mill modernization and expansion program at its Brokaw Mill facility-
On May 9, 1988, plaintiff requested revisions of the previously proposed contract. Specifically, plaintiff requested changes in the following sections of the contract: Payment for Services, Warranty, Compliance with Laws, Assignments, Reuse of Documents, Termination, and Governing Law.
On June 29, 1988, a contract was signed between the parties, incorporating the majority of plaintiff’s suggested revisions, and including the following provisions:
Section 3:1
WARRANTY — MAIN warrants that the services rendered pursuant to this AGREEMENT shall be performed in accordance with the standards customarily provided by an experienced and competent professional engineering organization rendering the same or similar services and that the PROJECT as designed will be fit for CLIENT’S particular purpose as specified in the Scope of Services and comply with all applicable specifications for the PROJECT set forth in the Scope of Services or otherwise developed and agreed to by MAIN and CLIENT during the performance of the services contemplated by this AGREEMENT. MAIN shall reperform any of said services which were not performed in accordance with this standard provided that MAIN is notified in writing of the non *970 conformity within one (1) year from the date of CLIENT’S acceptance of the PROJECT after final completion of all construction and satisfactory start-up, testing and inspection of all systems connected therewith except that if, through no fault of MAIN, CLIENT has not so accepted the PROJECT within one year of completion of MAIN’S services, this period shall not exceed 18 months from the completion of MAIN’S services. MAIN will perform the remedial services at its own cost; provided however, that the cost of such remedial services shall not exceed an aggregate amount equal to the amount paid by CLIENT to MAIN hereunder. It is further expressly provided that MAIN does not warrant against and shall have no liability for the effects of corrosion, erosion, or wear and tear of equipment and materials or failure of equipment and materials due to faulty operations or conditions of service more severe than specified in the design of the equipment and materials. Except as hereinafter provided in respect of personal injury or property damage, the foregoing are MAIN’S entire responsibilities and CLIENT’S exclusive remedies for services rendered or to be rendered hereunder, and no other warranties, guarantees, liabilities or obligations are to be implied.
Section 3:3
INDEMNITY — MAIN shall indemnify, defend and hold CLIENT harmless from and against claims, liabilities, suits, loss, cost, expense and damages for injury to or death of persons or damage to or destruction of property including, but not limited to, the property of CLIENT, arising in connection with MAIN’S negligent performance of the work and services pursuant to this AGREEMENT except to the extent caused by negligence of CLIENT or its contractors, agents or employees. MAIN’S liability for all of the aforesaid matters is limited to the proceeds recovered from the insurance carried by MAIN and within the coverage limits specified in SECTION 5 below after settling claims of third parties.
Section 3:6
CONSEQUENTIAL DAMAGES — In no event shall MAIN or its subcontractors of any tier be liable in contract, tort, strict liability, warranty, or otherwise, for any special, indirect, incidental or consequential damages, such as, but not limited to, delay, disruption, loss of product, loss of anticipated profits or revenue, loss of use of the equipment or system, non-operation or increased expense of operation of other equipment or systems, cost of capital, or cost of purchased or replacement equipment systems or power.
Section 8
ENTIRE AGREEMENT. This AGREEMENT supersedes any prior AGREEMENT, oral or written, and contains all of the terms and conditions agreed upon by the PARTIES hereto with respect to the subject matter hereof. No other AGREEMENTS, whether oral or written, not specifically referred to or included herein, shall be deemed to exist or modify this AGREEMENT or bind the PARTIES hereto. It is specifically agreed that MAIN’S services will be rendered in accordance with the terms and conditions of this AGREEMENT and that any standard or preprinted terms appearing on or made a part of any Purchase Order, Task Authorization or similar document shall not apply.
Section 6
GOVERNING LAW. This AGREEMENT shall be governed by the laws of the State of Wisconsin.
Plaintiff received professional engineering and other services from defendant on the Brokaw Mill project. Defendant did not supply equipment or other manufactured products to plaintiff on this project. Pursuant to a budget change request, defendant agreed to assume responsibility to interface, coordinate with, and assist the supplier of the new computer system on the project. These services did not involve design work in the conventional sense. There is nothing defendant or anyone else can do with respect to redesign work that will in any way reduce or eliminate the losses incurred by plaintiff with respect to defendant’s involvement in the computer programming.
*971 Defendant also agreed to assume responsibility for coordinating the flushing of the new pulp production system. A substantial delay of time occurred in the flushing of the system, and excess costs and production losses were incurred by plaintiff. The obligations defendant assumed with regard to the flushing were not for design services. The flushing procedures were completed eventually. Redesign work from defendant or anyone else will not reduce any of the losses sustained by plaintiff in connection with the flushing operation.
Also, plaintiff experienced a problem in connection with the start-up and processing of the pulp related to the hypofiltrate tank. A pipe connecting the outer tank to the inner tank was missing. Defendant’s employee reviewed the shop drawings supplied by the tank’s manufacturer and did not discover that the inner tank connection had been omitted from the drawings. Once this omission was discovered, no redesign services supplied by defendant or anyone else would reduce the losses sustained by plaintiff as a result of defendant’s failure to discover the error. 1
The limitations provisions in the contract purport to leave plaintiff without a damages remedy for any of its breach of contract claims.
OPINION
This suit is premised on plaintiff’s contention that defendant’s negligence and breach of warranty caused plaintiff substantial loss, including “costs to repair or replace the improperly designed piping, pumps and equipment, engineering costs to evaluate the design and engineering deficiencies and recommend corrective action, down time costs and lost production, and internal administrative and engineering costs ...” Plaintiff’s complaint, ¶ 7. Plaintiff does not deny that the damages it seeks are for “economic loss,” which has been defined as
‘damages for inadequate value, costs of repair and replacement of the defective product, or consequent loss of profits— without any claim of personal injury or damage to other property ... ’ as well as ‘the diminution in the value of the product because it is inferior in quality and does not work for the general purposes for which it was manufactured and sold.’
Chicago Heights Venture v. Dynamit Nobel of America,
“Economic loss” is not the most felicitous term for the kind of damage it describes. Economic loss does not refer to every kind of loss or every diminution in the value of property; rather, it refers to a diminution in the value of a particular product caused by the product itself or by the failure of the product to function as represented, in other words, to failed economic expectations. If a lawnmower fails to work as intended and throws off a piece of metal that lands in the operator’s eye, causing him to miss work and incur medical losses, those are economic injuries that can be recovered in a tort action. They are not covered by the term “economic loss.” If the lawnmower’s malfunctioning causes it to wear out in a short time, requiring replacement, that is economic loss. Where such a loss is the only loss involved, the lawnmower’s owner may sue only in contract. Injury to the product itself is the kind of harm that is left entirely to the law of contracts. Claims for negligent design or defective manufacturing are barred; the economic loss doctrine makes tort remedies unavailable for persons whose only injury is a loss in their expectations for a product.
See East River S.S. Corp. v. Trans-america Delaval,
East River
was a suit brought by charterers of supertankers against turbine manufacturers for alleged design and manufacturing defects that caused the supertankers to malfunction. The Court concluded that public policy precluded a tort remedy for economic loss caused by a defective product because repair costs, decreased value and lost profit are “essentially the failure of the purchaser to receive the benefit of its bargain — traditionally the core concern of contract law.”
East River,
Contract law, and the law of warranty in particular, is well suited to commercial controversies of the sort involved in this case because the parties may set the terms of their own agreements. The manufacturer can restrict its liability, within limits, by disclaiming warranties or limiting remedies. In exchange, the purchaser pays less for the product. Since a commercial situation generally does not involve large disparities in bargaining power, ... we see no reason to intrude into the parties’ allocation of risk.
Id.
at 872-73,
Although
East River
involved manufactured products, courts have used its broad policy rationales to extend its application.
See PPG Industries, Inc. v. Sundstrand Corp.,
As a general rule, Wisconsin has allowed tort recovery for loss of profits. In
A.E. Investment Corp. v. Link Builders, Inc.,
However, in
Sunnyslope Grading, Inc. v. Miller, Bradford and Risberg, Inc.,
Plaintiff contends that
Sunnyslope
is inapplicable because it deals with manufactured products and because the Uniform Commercial Code formed the basis for the court’s decision. Although the court relied in part on the legislative protections of the Uniform Commercial Code as a justification for denying tort recovery, the court did not cite the Uniform Commercial Code as the only method of protection: “The question of product value and quality is intended to be addressed by warranties and the Uniform Commercial Code. Contract law, the law of warranty and the Uniform Commercial Code are designed to allow the parties to allocate the risk of product failure.”
Sunnyslope,
In addition,
Sunnyslope
and the cases cited therein are not based on a distinction between products and services. Rather, the important distinctions appear to be whether the parties are in privity of contract or parties to a warranty. The court distinguished
La Crosse v. Schubert & Asso.,
In
Sunnyslope
the state court distinguished
A.E. Investment
in part on the basis of services and relied to some extent on the Uniform Commercial Code. In addition, it placed great weight on the existence of a warranty and a contractual relationship. It is doubtful that it would continue
*974
to do so.
See Midwest Knitting Mills, Inc. v. United States,
Plaintiff points to Wis.Stat. § 895.49 as additional support for its contention that Wisconsin’s intent is to permit tort claims in the context of a construction dispute. That section provides in pertinent part:
(1) Any provision to limit or eliminate tort liability as a part of or in connection with any contract, covenant or agreement relating to the construction, alteration, repair or maintenance of a building, structure, or other work related to construction, including any moving, demolition or excavation, is against public policy and void.
Defendant contends this statute does not apply unless plaintiff asserts a viable tort claim. Because § 895.49 voids agreements in construction contracts that limit or eliminate tort liability, thereby limiting the parties’ common law right to contract freely, the statute must be interpreted narrowly, placing the least possible restriction on the common law right.
Gerdmann v. U.S. Fire Ins.,
I am persuaded that Wisconsin’s economic loss doctrine covers contracts for services where there is a warranty and a contractual relationship between two sophisticated parties. Plaintiff’s claim does not allege injury to a person or to other property. Its loss “due to repair costs, decreased value, and lost profits is essentially the failure of the purchaser to receive the benefit of its bargain — traditionally the core concern of contract law.”
East River,
Partial Summary Judgment Motion to Strike Consequential Damages
The contract between plaintiff and defendant provides that defendant will not be liable in tort, contract or warranty “for any special, indirect, incidental or consequential damages, such as, but not limited to, delay, disruption, loss of product, loss of anticipated profits or revenue, loss of use of the equipment or system ... or cost of purchased or replacement equipment systems or power.” Plaintiff is pursuing damages for “costs to repair or replace the improperly designed piping, pumps and equipment, engineering costs to evaluate the design and engineering deficiencies and recommend corrective action, down time costs and lost production and internal administrative and engineering costs.... ” Plaintiff’s complaint If 7. Thus, plaintiff is attempting to recoup damages prohibited by the contract.
Plaintiff contends that the provisions in the parties’ agreement are unconscionable and therefore unenforceable because they
*975
fail to provide plaintiff with a fair remedy. “Unconscionability has generally been recognized to include an absence of meaningful choices on the part of one of the parties together with contract terms which are unreasonably favorable to the other party.”
Discount Fabric House v. Wis. Telephone Co.,
Plaintiff and defendant are multimillion dollar corporations; plaintiff does not contend that their bargaining power was unequal. Plaintiff does not contend that it did not understand the terms of the contract; indeed, plaintiff requested revisions to several sections of the contract. Because the procedural aspects of the parties’ contract appear to have been reasonable, the unconscionability determination will turn on the substantive question: whether the terms of the contract are commercially reasonable.
The contract excludes consequential damages for commercial loss only. An indemnity clause holds defendant responsible for any “claims, liabilities, suits, loss, cost, expense and damages for injury to or death of persons or damage to or destruction of property.” The warranty clause makes re-performance plaintiff’s exclusive remedy, with the cost of the remedial services not to exceed an aggregate amount equal to the amount paid by plaintiff under the contract.
Policy concerns disfavor stipulated damages clauses. “Stipulated damages substantially in excess of injury may justify an inference of unfairness in bargaining or an objectionable
in terrorem
agreement to deter a party from breaching the contract, to secure performance, and to punish the breaching party if the deterrent is ineffective.”
Wassenaar v. Panos,
In this case the parties’ contract terms are commercially reasonable. The contract did not bar plaintiff from seeking damages for losses in general, only for economic loss. Defendant was not in a more powerful position than plaintiff when the parties were engaging in arm’s-length negotiations for three months. If plaintiff thought the remedial provisions inadequate, it could have requested revisions just as it did with other contractual terms it found unsatisfactory. The contract terms are reasonable. That plaintiff’s losses went beyond what can be remedied by reperformance is a byproduct of risk allocation, not a result of unconscionability. Plaintiff must abide by the terms and cannot seek consequential damages. Defendant’s motion for partial summary judgment to strike plaintiff’s consequential damages claim will be granted.
ORDER
IT IS ORDERED that defendant’s motions for partial summary judgment as to plaintiff’s negligence claim and for partial summary judgment as to plaintiff’s claim for consequential damages are GRANTED.
Notes
. Defendant stated that it "rebutted" the proposed facts in the last three paragraphs but stated that for purposes of the summary judgment motion, the facts were irrelevant. However, defendant did not rebut the facts properly because it did not point to any evidence in the record that would put plaintiffs proposed facts into dispute. Because I find the facts to be material, they have been included.
