3 Wash. 283 | Wash. | 1891
The opinion of the court was delivered by
This action was brought on an alleged violation of a written contract made by the plaintiff and one Hamshaw, whom plaintiff claims to be a general agent of defendant, and as such manager had the authority to bind the defendant by his contract. The contract was signed, “ The Gray’s Harbor Brick Company, by F. T. Hamshaw, manager.”
The respondent moves the court to dismiss the said appeal, and affirm the judgment rendered in the court below, for the reason that there is no assignment of errors. The appellant, however, specified the errors in its motion for a new trial, and cites them in its brief, though not in a very formal way. This appeal was taken before the law of 1891 went into, effect, and under the provisions of the law then in force, we think, is sufficient, and the motion to dismiss will be denied.
Under the contract, the plaintiff agreed to sink a well for defendant, for which service defendant agreed to pay a stipulated price per foot. Plaintiff alleges that in view of
“Upon an examination of the contract during the adjournment,we have cometo the conclusion that this contract is not revokable at the will of the defendant; that under its provisions there is an express agreement that he shall sink at least one well to a depth not to exceed 500 feet. The allegations of the complaint being that the contract was abrogated by the defendant before he had commenced any operations on the sinking of the well, it would constitute a breach of the contract, if proven. The measure of damages, in that instance, is the amount of expense necessarily incurred by the plaintiff in preparing for the work, and a reasonable allowance for his time in so doing, not exceeding the amount claimed in his complaint.”
Whereupon the plaintiff moved to strike out all that part of the testimony of Mr. Watson which did not relate to the expense incurred by him in bringing his machinery and expert workmen from Walla Walla to Gray’s Harbor,
Instruction 8: “If you believe, then, that the company was bound by the contract in the manner as stated in the foregoing instructions, and that the plaintiff made preparation to do the work, and was then prohibited from doing it by the company, they would be liable to him for his expenses and reasonable compensation for Ins time lost, not exceeding the amount claimed in his complaint.”
To which instruction the defendant excepted.
While the measure of damages seems largely to have been the bone of contention at the trial, no authorities are cited by either appellant or respondent on that question. We think there was no error committed by the court in excluding the testimony referred to above. We do not question the general rule that plaintiff cannot recover for avoidable consequences. This is a natural sequence of the principle which confines the damages to direct and immediate consequences, and can be pleaded when the nature of the case will permit; for it is not the policy of the law to permit a man to aggravate his damages by his own neglectful acts. As, for instance, it has been held that where a man’s fence has been knocked down and his crops exposed to the ravages of cattle, that it was his duty to repair the fence as soon as it came to his notice, and that he could not recover damages that were incurred after that time. This rule is made especially applicable to actions by employes to recover for personal services where they have been dismissed by their employers without sufficient cause,
The case at bar is a signal instance of attempting to apply such a rule to this kind of a contract; a voluminous mass of evidence was submitted for the digestion of the jury concerning other contracts performed by this plaintiff; how much profit he made out of this contract, and how much loss he sustained in that; the condition under which he labored in other contracts, compared with the condition under which he would have labored in the performance of the contract sued on; the respective conditions of the soil in different locations, as to the relative amount of clay, gravel, sand, etc.; showing conclusively that it was an introduction of an impracticable element of proof, and had no approximate relation to the contract itself. If the rule was to be observed that the damages proven must be direct and approximate, the same rule must be invoked in the reduction of damages. Mr. Sedgwick says that “while the rule is of very general application, the circumstances of many contracts forbid its application.” This, we think, is one of those cases. The distinction between contracts for piece work and time contracts, according to the phraseology of Mr. Greanleaf, is recognized by that author in his work on Evidence, vol. 2 (14th ed)., § 261a. Prevention by the employer gives the right to damages for loss of the profits.
“ The profits which aro permitted to be recovered are those which are the direct and immediate fruits of the contract. These are part and parcel of the contract itself, entering into and constituting a portion of its very elements, something stipulated for, the right to the enjoyment of which is just as clear and plain as to the fulfillment of any*289 other stipulation. They are presumed to have been taken into consideration and deliberated upon before the contract was made, and formed, perhaps, the only inducement to the-arrangement.^ In an action upon the contract against the employer for' preventing the complete performance, th,e contractor is entitled to recover the contract price for the-work actually done, and, in the absence of other damages, the difference between the contract price and what it would cost to perform the contract as to the residue.” 2. Sutherland on Damages, p. 522.
In Myers v. York & Cumberland R. R. Co., 2, Curt. 28, it is held that in an action of covenant, the plaintiff having been wrongfully prevented by the defendant from completing the work, the measure of damages is the difference between the price agreed to be paid for the work and what it would have cost the plaintiff to complete it. When one conr tracts to perform work for another at a stipulated price, and is prevented by him from entering upon the performance, the measure of damages is the difference-between the cost of performing the work by the party agreeing to do it and the price agreed to be paid for it; or, in other words, the profits the party would have received. George v. Cahawba, et. R. R. Co., 8 Ala. 234. This was a special contract between plaintiff and defendant by which he-was to perform certain work and labor on the road for certain compensation to be paid him. To the same effect is Richmond v. Dubuque & Sioux City R. R. Co., 26 Iowa, 191. In fact, we think that in contracts of this kind the rule of profits is thoroughly established, and as said by the supreme court of the United States, in Philadelphia, etc., R. R. Co. v. Howard, 13 How. 344, that “wherever profits are spoken of as not a subject of damages, it will be found, that something contingent upon future bargains, speculations or states of the market are referred to, and not the difference between the agreed price of something contracted: for and its ascertainable value or cost.” In this case the.-jury evidently acted under
The judgment is reversed and the cause remanded.
.Anders, O. J., and Stiles, Scott and Hoyt, JJ., concur.