James WASHINGTON d/b/a Washington Repair Service, Appellant, v. KINGRIDGE ENTERPRISES, INC., Appellee.
No. CV-14-179
Court of Appeals of Arkansas.
Dec. 10, 2014.
2014 Ark. App. 705
WYNNE and BROWN, JJ., agree.
Stuart Law Firm, P.A., Little Rock, AR, by: Ginger M. Stuart, for appellee.
KENNETH S. HIXSON, Judge.
As part of a renovation project, Kingridge hired Washington to install heating-ventilation-and-air-conditioning (HVAC) units and duct work in a commercial building located on Broadway Street in Little Rock. The parties executed a written contract in October 2012, in which Washington agreed to provide all material, labor, and permits, and to complete the job in a timely and workmanlike fashion for a contract price of $17,500. The
After the September 2013 bench trial, the trial judge concluded that Kingridge sustained $2262 in damages, offset by Washington‘s entitlement to $1000 for unpaid labor. The result was a net judgment
In review of a bench trial, we determine whether the trial court‘s findings were clearly erroneous or clearly against the preponderance of the evidence. Bowen v. Gardner, 2013 Ark. App. 52, 425 S.W.3d 875. Disputed facts and determinations of credibility of the witnesses are within the province of the fact-finder. Id. A trial court‘s conclusions of law, however,
To place these arguments in context, we examine the evidence presented at trial in greater detail. Kingridge was renovating a commercial building. Washington submitted a bid to install new four-ton and five-ton package HVAC units with duct work, and to repair old duct work, for $17,500. Kingridge accepted the bid, and the parties entered into a detailed four-page-typed contract on October 23, 2012. The contract provided in part that Washington had reviewed Kingridge‘s city-approved architectural plans and specifications, and Washington agreed to “furnish all material, equipment and perform all labor necessary to complete” the HVAC “modifications, relocation(s) and installations per the Plans.” The contract attached, as exhibits, Washington‘s one-page proposal bid, as well as Kingridge‘s architectural plans and specifications. In the contract, the parties agreed that “time is of the essence” and that the work was to be “substantially completed on or before” November 26, 2012. The agreed price was to be paid in percentage installments (35%, 40%, and 25%) triggered by defined periods of satisfactory progress on the job. Washington agreed to complete the job “in a workmanship like manner and in compliance with all building codes and other applicable laws” and agreed to obtain at his own expense “all permits necessary for the work to be performed.”
Following discovery, a bench trial was conducted in September 2013, at the conclusion of which the circuit judge announced his decision from the bench. The judge considered the testimony of several witnesses, one of whom was Washington, as well as multiple documents entered into evidence. The judge disallowed Kingridge the $2500 in administrative costs it sought, but he awarded Kingridge damages in the amount of the difference between the contract price and what it cost Kingridge to have the job completed, which totaled $2262. The judge then awarded Washington $1000 for the value of his labor. This computed to a net judgment of $1262 in Kingridge‘s favor. The judge then announced that he would award a reasonable attorney fee to Kingridge. The judgment entered in favor of Kingridge included damages of $1262, costs of $215, and attorney fees in the amount of $5500. Washington filed a timely notice of appeal.
Appellant‘s first two points on appeal are so closely related that they will be considered together. Washington concedes that the contract required him to pay for the permit and the equipment, which he did not do. Washington argues that because Kingridge paid for its own equipment and permit (which were obviously breaches of the agreement), Kingridge waived its right to enforce the contract against Washington. He cites to Clear Creek Oil & Gas Co. v. Brunk, 160 Ark. 574, 255 S.W. 7 (1923), Stephens v. West Pontiac-GMC, Inc., 7 Ark.App. 275, 647 S.W.2d 492 (1983), and Southern Pipe Coating, Inc. v. Spear & Wood, Mfg. Co., 235 Ark. 1021, 363 S.W.2d 912 (1963), as support for this argument. Washington also argues that Kingridge was the materially breaching party that terminated the contract by not allowing him to finish, entitling him to recover on his breach-of-contract claim, citing to Southern Pipe Coating, supra. We disagree that the trial court clearly erred.
Typically, the prevailing party files a posttrial motion for attorney fees under the procedure set forth in
Affirmed.
HARRISON and WOOD, JJ., agree.
