162 A. 829 | Pa. | 1932
Argued May 10, 1932. Appellant sued defendant for breach of defendant's contract with Arey Hauser Company (herein called the builder) to which appellant was not a party. Defendant filed an affidavit raising questions of law; after hearing, the court entered judgment for defendant. Has plaintiff a cause of action? *354
The builder had a contract to erect a building and on November 28, 1930, made a subcontract with Ockman Haberman Company (herein called subcontractor) to "furnish all materials, as and when needed, and fully construct, perform and in every respect complete the reënforcing, concrete fireproofing and cement work" required in the building. It provided that the subcontractor "will promptly begin said work as soon as it is notified by the [builder] that the ground is clear or that the structure is far enough advanced" to allow the beginning of the subcontractor's work. When it was commenced does not appear and is probably not important. It could not have been far advanced, even if begun, when the defendant wrote to the builder the letter hereinafter quoted.
On December 2, 1930, the subcontractor made a contract with plaintiff by which plaintiff agreed, in consideration of $28,200 to be paid to it at various periods specified in the contract, to furnish certain concrete-form work for the fireproofing, etc. It provided that "Shipment and deliveries under this contract shall at all times be subject to the approval of [plaintiff's] credit department and in case [plaintiff] shall have any doubt as to the contractor's responsibility, [plaintiff] may decline to make any shipments or perform any service hereunder except upon receipt of satisfactory security or for cash."
Defendant's letter to the builder, above referred to, is as follows: "Ockman, Haberman Co., who have the subcontract for reinforcing, fireproofing and cement work on your Medical Tower Building job at 17th and Latimer Streets, desire to assign this contract with us as collateral security for a loan. Under this procedure, we would pay out all sums due by him on this work on his vouchers and we will receive all payments from you. Please advise us whether this will be satisfactory to you as you will be a party to the assignment." The letter is dated March 16, 1931, and has endorsed on it the approval *355
of the subcontractor. The builder assented to it and in turn notified plaintiff thereof, and told plaintiff that future payments to it would be made by defendant, as provided in that letter, upon the terms stated and upon those only, and after plaintiff assented thereto, the builder agreed to pay to defendant, as specified in the letter, and ten days later the contemplated formal assignment (Exhibit C to the statement of claim) was executed by the subcontractor to defendant and the builder by writing endorsed on it, agreed to pay to defendant "all sums that become due [to the subcontractor] in the course of said contract" between the builder and subcontractor. It does not appear who drew the assignment but, judging from the previous letter, it was probably prepared by defendant against whom, therefore, any doubt regarding its meaning must be resolved: Coates et al v. Cotteral,
In such circumstances it is clear that plaintiff has a cause of action. The learned court below was of opinion (citing Greene County v. Southern Surety Company,
Plaintiff was not a creditor of the builder. If, therefore, the builder, as a condition of assent to the assignment of the subcontractor's account, chose to require defendant to agree to make the payments in question to plaintiff, and defendant agreed, as plaintiff avers, defendant should be required to perform, because plaintiff is clearly within the class of cases permitting suit by the third party in his own name. In Greene County v. Southern Surety Company,
The learned court below was also of opinion that, as the written assent of the builder at the foot of the assignment was silent concerning the promise now declared on, plaintiff could not recover because proof of its averment would change or add to the written assent, and that such proof could not be offered in the absence of averment that it was omitted by fraud, accident or mistake. If that question were involved, it would have been wrong to enter final judgment for defendant because, conceivably, the omission might be amendable, and, in such circumstances, the court should always afford plaintiff opportunity to amend: Rhodes v. Terheyden,
The statement would seem to set forth the familiar transaction in which one who has received money for the payment of a debt to another, is held liable to the party to whom payment was to be made at the suit of such party in his own name: Stoudt v. Hine,
The judgment is reversed and record remitted for further proceedings.