WASHINGTON GROUP INTERNATIONAL, INC., Plaintiff-Appellant, v. BELL, BOYD & LLOYD LLC, Defendant-Appellee.
No. 03-2389
United States Court of Appeals For the Seventh Circuit
ARGUED OCTOBER 27, 2003—DECIDED SEPTEMBER 9, 2004
Before RIPPLE, DIANE P. WOOD, and EVANS, Circuit Judges.
Appeal from the United States District Court for the Northern District of Illinois, Eastern Division. No. 02 C 8974—James B. Zagel,
DIANE P. WOOD, Circuit Judge. While the technical issue before us concerns the relation between this litigation and an earlier bankruptcy proceeding, the underlying dispute alleges that the firm of Bell, Boyd & Lloyd (Bell Boyd) committed legal malpractice in conjunction with a mechanic‘s lien. Washington Group, the successor to Raytheon Engineers & Constructors, Inc. (Raytheon), claimed that Bell Boyd negligently handled both the drafting of certain liens and the litigation related to those liens. In response, Bell Boyd claimed that all the issues Raytheon was raising in this case had been resolved against it in an adversary proceed-ing before the Delaware bankruptcy court in a case between Raytheon and Acme, a client for whom Raytheon was building a plant. The district court agreed with Bell Boyd and dismissed all claims. We affirm.
I
In 1994, Raytheon entered into a contract with Acme Steel Company for the construction of a steel mill. Raytheon in turn signed a subcontract with United Steel Erectors, Inc. (USE) for construction of the buildings at the steel mill. USE enlisted Calumet Construction Corporation (Calumet) for the erection of the structural steel for the steel mill buildings. In 1996, Calumet filed a sub-subcontractor‘s claim for a mechanic‘s lien related to its work on the steel mill. It followed up on that action with a lawsuit in February 1997 to enforce its mechanic‘s lien against Acme, Raytheon, and USE (the Calumet litigation). In March 1997, USE filed its own mechanic‘s lien and then cross-claimed against Raytheon and Acme seeking to enforce that lien.
Faced with this array of disputes, Raytheon retained Bell Boyd to represent it in the Calumet litigation and to protect its rights vis-à-vis Acme. Over a year later, in September 1998, Acme voluntarily filed in the Delaware bankruptcy court for Chapter 11 relief. Later, on November 13, 1998, Bell Boyd filed a $12,006,799 mechanic‘s lien (the Acme Lien) on Raytheon‘s behalf in connection with its work on the steel mill. The property description Bell Boyd used in the Raytheon lien was the same description as the one that had been used in the Calumet and USE liens. Shortly after filing the lien, Bell Boyd withdrew from further representation of Raytheon because of a conflict of interest.
On February 7, 2000, Acme brought an adversary action in its bankruptcy proceeding seeking a declaration that Raytheon‘s Acme Lien was invalid because (1) the property description was incorrect; and (2) even if the property de-scription was acceptable, that the
On December 11, 2002, Raytheon‘s successor, the Washington Group (an Ohio corporation with its principal place of business in Ohio) brought this action under the diversity jurisdiction, alleging that Bell Boyd (an Illinois limited liability company, none of whose members are citizens of Ohio) had committed malpractice. Raytheon claimed that Bell Boyd should have discovered the incorrect property description in the Calumet and USE liens in 1997 and that Bell Boyd prepared Raytheon‘s 1998 lien negligently because it used that same incorrect property description. Raytheon also claimed that Bell Boyd was negligent in failing to advise Raytheon that the three-year rule might invalidate Raytheon‘s lien. In addition to damages, Raytheon sought reimbursement of the attorneys’ fees it spent litigating the bankruptcy and Calumet cases.
Ruling on Bell Boyd‘s 12(b)(6) motion, the district court held that the bankruptcy court‘s conclusion that the property description
Before this court, Raytheon makes two principal arguments: first, that the property description was indeed invalid and that it should not be bound by the bankruptcy court‘s conclusion on that point; and second, that an Illinois court might have interpreted the three-year rule differently than the bankruptcy court did, and the possibility of such a discrepancy proves Bell Boyd was negligent in not informing Raytheon of the rule‘s effect. We find it unnecessary to consider the first point in detail, because we conclude that Raytheon was bound by the bankruptcy court‘s ruling on the three-year rule, and that it is plain on the face of the pleadings that nothing Bell Boyd could have done, given its late entry into the fray, could have made a difference.
II
An action for legal malpractice in Illinois requires the plaintiff to prove five elements: “(1) an attorney-client relationship; (2) a duty arising out of that relationship; (3) a breach of that duty; (4) causation; and (5) actual damages.” Griffin v. Goldenhersh, 752 N.E.2d 1232, 1238 (Ill. App. 2001). Raytheon‘s malpractice claims against Bell Boyd thus depended upon, among other things, the possibility of finding that Bell Boyd‘s negligence with respect to the allegedly flawed mechanic‘s lien caused some harm to Raytheon. Raytheon believes that if Bell Boyd had discovered that the property description was incorrect earlier or if Bell Boyd had alerted Raytheon to the three-year requirement, Raytheon would have prevailed in the Calumet litigation and would never have been dragged into bankruptcy court—or at leastnot to the degree that it was. Instead, it asserts, Bell Boyd‘s negligence forced Raytheon to defend itself in the Calumet litigation and ultimately to suffer substantial losses.
Raytheon has argued that the bankruptcy court erred in its application of the three-year rule in the Mechanic‘s Lien Act. Bell Boyd responds that it is too late in the day to challenge that ruling, because it is entitled to preclusive effect in the present case. Because we are considering what effect should be given to the judgment of the Delaware bankruptcy court, which is a unit of the district court, see
1) the issue sought to be precluded must be the same as that involved in the prior action, 2) the issue must have been actually litigated, 3) the determination of the issue must have been essential to the final judgment, and 4) the party against whom estoppel is invoked must be fully represented in the prior action.
People Who Care v. Rockford Bd. of Educ., 68 F.3d 172, 178 (7th Cir. 1995); La Preferida, Inc. v. Cerveceria Modelo, S.A., 914 F.2d 900, 905-06 (7th Cir. 1990). Raytheon challenges only the first requirement—that the issue sought to be precluded in the present case is not the same as that decided in the bankruptcy court. (When Bell Boyd responded to the motion under
In order to resolve this element of issue preclusion, we examine first what was before the bankruptcy court, andthen what was before the district court. Raytheon filed two secured proofs of claim in the bankruptcy proceeding, each in the amount of $8,820,252. It asserted that its original mechanic‘s lien secured these claims. Acme responded that Raytheon‘s claims actually were unsecured because Raytheon filed the lien improperly. Acme offered three arguments in support of this position, one of which was that the lien was invalid because it failed to meet the three-year requirement of the
Raytheon has already had its day in court with respect to the question whether the lien complied with the three-year rule, and it lost. That much is therefore established for purposes of the liens at issue here. The only remaining issue is whether Raytheon has stated a claim against Bell Boyd for negligently failing to counsel it about the effects of the three-year rule. The district court pointed out that Raytheon did not even hire Bell Boyd until more than two years of the contract had passed. Raytheon failed to allege any facts suggesting that construction would be completed by the statutory three-year deadline, or that, had Bell Boydalerted it to that rule earlier, it could have sped up construction. Because Raytheon could take no action to stave off the effects of the three-year rule even had Bell Boyd told it about the rule, Bell Boyd‘s failure to do so could not have caused any damage to Raytheon.
III
We cannot improve on the conclusion that the district court succinctly stated: “. . . [A]ll of the elements of collateral estoppel are clearly met here, and there is no showing that the defendant‘s actions were the proximate cause of any damage to Raytheon . . . .” The same reasons are enough to defeat Raytheon‘s request for attorneys’ fees it paid allegedly because Bell Boyd was negligent. Finally, we deny Raytheon‘s motion to certify these issues to the Illinois Supreme Court, as we see no issues that meet that court‘s standards for certification. See
A true Copy:
Teste:
________________________________
Clerk of the United States Court of Appeals for the Seventh Circuit
USCA-02-C-0072—9-9-04
