209 A.D. 365 | N.Y. App. Div. | 1924
The plaintiffs sued to recover damages for alleged breach of a written contract under which plaintiffs agreed with defendant corporation to lay out and grade certain streets and parts of streets on a tract of land owned by defendant.
Examination of the record of the trial before the referee shows the issues in this dispute depending almost entirely upon questions of fact. They involved the question of plaintiffs' performance of the work called for in the contract so far as it was performed, whether plaintiff contractor abandoned the contract or whether defendant owner and his new engineer in charge of the work insisted upon unreasonable additions and changes not called for in the contract and whether he refused to allow the plaintiff to go on with the work unless he assented to such unreasonable conditions. If the owner refused to allow the contractor to proceed under these circumstances the contractor was not barred from recovering future profits under Wharton & Co. v. Winch (140 N. Y. 287), and cases there cited. The referee found for the plaintiffs upon these issues and there appears to be ample evidence justifying his finding. Between August, 1921, and January, 1922, the engineers originally in charge of the work from time to time in accordance with the contract, certified to the completion of the work in various stages, and the defendant owner paid the amount called for in these certificates, aggregating $14,507.60. Defendant changed its engineer in charge of the work three times during this period, and the last engineer objected to the original plans and grades provided for in the contract, and to the work performed under his predecessors. Whether his objections were good or bad he could not so alter tne written contract between the owner and the contractor, and there was evidence that the owner refused to allow plaintiff to proceed with the additional work until he went back and did over the work which he had completed and for which he had been paid, in accordance with the new requirements. As to defendant’s claim that
The judgment should be modified by reducing plaintiffs’ recovery
This court reverses the findings of fact of the referee numbered IX, X and XI on the facts, and finds instead as matter of fact:
IX. That in or about the month of September, 1921, the defendant requested plaintiffs to grade the portion of Bennett boulevard between the westerly end of the black line on said boulevard shown on the map attached to the contract and the Jamesburg boulevard, a distance of 860 feet; that pursuant to said request the plaintiffs did the work of grading said 860 feet of Bennett boulevard, and thereafter rendered a bill to defendant for $349.75, which was the reasonable value of said work, and demanded payment of said sum, which was refused, and no part thereof has been paid.
This court reverses the 3d conclusion of law of the referee on the law, and finds instead:
3d. That plaintiffs are entitled to recover for the work done on the westerly 860 feet of the Bennett boulevard described in the 9th finding of fact, the reasonable value thereof, to wit, the sum of $349.75.
Rich, Jaycox, Manning and Young, JJ., concur.
Judgment modified in accordance with opinion, and as modified unanimously affirmed, without costs. Findings of fact and conclusion of law reversed in accordance with said opinion. Settle order on notice.