97 Cal. 58 | Cal. | 1892
This is an action for the foreclosure of a mechanic’s lien for materials furnished in the alteration of a building.
Appellant contends that the liens were filed too late. For the purpose of establishing the date of completion, respondent offered in evidence the following certificate of the architect: —
“San Francisco, Jan. 23, 1889.
“ Mr. H. Kahler.
“ Dear Sir,—Your building, No. 11 Guerrero Street, is now finished as per contract dated September 6, 1888,*61 by Ivory Wells, contractor, who is now entitled to the last and final payment, viz., $325.
“You will therefore please pay same to him, and this shall be your receipt therefor.
“Provided, however, that all bills and receipts are satisfactory to you.
(Signed) “ R H. Daley.”
This certificate was issued in compliance with a provision of the contract that provided for a payment to the contractor, to wit, “ when all the work is complete and accepted by the architect, $325. ‘Provided, that at the making of any payment the said contractor shall produce receipted bills for all materials and labor furnished by him (the said contractor) to the architect before any certificate is given for the said payment.” It is thus apparent that the date of the certificate of the -architect is no evidence of the time of the completion of the building. Such was neither its object nor purpose. The certificate was provided for in the contract for the purpose of indicating when the final installment was payable to the contractor. The time for the payment of this installment was dependent upon the issuance of the certificate, and the issuance of the certificate was dependent not alone upon the completion of the building, but also upon the condition precedent that receipted bills should be presented to the architect. The receipted bills may have been presented upon the day of completion, but their presentation may have followed weeks subsequent to that event, and from the face of the certificate it is impossible to determine the date of completion. The contractor, who was offered as a witness for the respondent, testified, upon cross-examination, that the building was completed January 13th. This evidence, taken in connection with the architect’s certificate, comprises all that was presented upon this matter, and upon such a state of facts the finding that the building was completed upon the twenty-third day of January must be set aside as without support in the evidence.
Harrison, J., and Paterson, J., concurred.