111 F. 695 | 8th Cir. | 1901
The Warren-Scharf Asphalt Paving Company, the plaintiff in error, sued the Eaclede Construction Company, the defendant in error, upon a contract dated March 14, 1899, whereby the former company agreed with the latter company to furnish tlie materials and perform tlie necessary work and labor in the construction of a railroad from Peoria, 111., to East Clinton, in the state of Illinois. In one count of the petition it was alleged that the defendant company was indebted to tlie plaintiff company in the sum of $11,159.12 for work actually done and performed in the execution of said contract, for wdiich sum the plaintiff prayed judgment. In another count of the petition ,it was alleged, in substance, that after work to the value of $11,159.12 had been performed, and on or about May 27, 1899, the defendant company, without any default on the plaintiff’s part, abrogated the contract and refused to allow the plaintiff to proceed further in the performance of the same; that, if the plaintiff had been allowed to perform its said agreement, it would have realized a profit in the stun of $130,000, for which latter amount it prayed judgment in addition to a judgment for tlie value of the work actually performed at the time the contract was /abrogated. The defendant company pleaded, in substance, that tlie contract in question contained the following provision, known as “Paragraph 12”:
“Tlie party of tlie second, part (namely, tlie Laclede Construction Company) shall have tlie right at any time, and for any reason which may appear satis*696 factory to said party, to suspend the prosecution of the work embraced in this contract, either temporarily or permanently, upon giving ten days’ notice to the party of the first part (namely, the Warren-Scharf Asphalt Paving-Company) of his intention so to do, in which event said party of the first part shall be entitled to payment in full for the work done by it up to the time of such suspension, subject to such deductions as are herein elsewhere provided for; but such suspension shall not give 'to the party of the first part any claim for damages therefor against said party of the second part.”
The defendant company further pleaded that on May 27, 1899, by virtue of the aforesaid provision of the contract, it notified the plaintiff to permanently suspend the prosecution of the work embraced in the contract upon the expiration of 10 days from said date, and that the plaintiff then and there agreed that it would suspend the prosecution of the work, and agreed to waive the 10 days’ notice required by the provisions of the contract.
On the trial of the case the defendant company admitted an indebtedness to the amount of $11,159.12 on account of work actually done at the time the contract was abrogated, and made a tender of that amount, whereupon a judgment was entered therefor on the second count. Upon an inspection of the contract' the trial court ruled that the provision of the contract above quoted empowered the defendant company to abrogate the contract on 10 days’ notice without liability ,for damages, and, in accordance with that view of the case, directed a judgment to be entered in favor of the defendant company on the first count of the petition, wherein the plaintiff sought to recover unearned profits. The case was brought to this court upon a writ of error by the plaintiff company. The sole question, therefore, which the record presents, is whether the trial court "“óperly construed the twelfth paragraph of the agreement. We are of opinion that the clause of the contract in question was properly interpreted and enforced by the trial court. Indeed, the meaning of the clause is too plain to admit of any controversy. The parties to the agreement had in mind both a temporary and a permanent suspension of the work, and, in language which cannot be misunderstood, stipulated that the defendant company might suspend operations under the contract, either temporarily or permanently (that is, abrogate the contract altogether), on 10 days’ notice. And as if to make their purpose and intent more clear, and to put the matter beyond dispute, they further agreed that, if operations under the contract were suspended, the party of the first part should not have any claim for damages. In other words, the right was reserved by the defendant company to put an end to the agreement at any time on 10 days’ notice, without liability for damages. It was entirely competent for the parties ■to enter into such an agreement, and such stipulations are sometimes found in contracts for the construction of railroads, and for the doing of other work of a like character, where unforeseen events may occur to render a temporary or permanent suspension of the work both desirable and necessary, We perceive no reason whatever for indulging in the assumption that, when the parties agreed that the work might be suspended permanently at the election of the defendant company, they did not mean what they said, but used the word “permanently” in some new and strange sense. Nor do we perceive that
Finding no error in the record, the judgment below is accordingly affirmed.