231 Mass. 138 | Mass. | 1918
This is an application under R. L. c. 51, § 16, by the owner of land abutting on a public way for the assessment of damages caused by the making of repairs thereon.
The material facts are that an earlier petition for the assessment of damages arising from this same cause was filed in the Superior Court and came on for trial in April, 1917. The judge then ruled that in such a proceeding “a certain notice” must be given to the mayor and aldermen and that the “actual notice which was given in this case was not a proper notice, and therefore this suit
When an owner of land sustains damage by any act done by way of repair upon a way, the first step which he must take in order to have his damages assessed is to file a “petition for compensation with the mayor and aldermen or selectmen or road commissioners, after the commencement and within one year after the completion of the work.” R. L. c. 51, § 15. Manifestly it is not accurate to speak of such a “petition for compensation” as a “notice.” It is in the nature of a proceeding and requires the board to which it is presented to undertake in the exercise of a gt¿ cm"-judicial function to determine the amount of the damages. No notice is required by the landowner who suffers damages by repairs upon a way. The filing of the “petition for compensation” is the first act to be done by him. Therefore, although the statement in the record is not clear, it seems fairly inferable that the ruling of the judge on the first petition, founded as it appears to have been upon the agreement of the parties as to want of “notice,” in substance and effect was the equivalent of a ruling that, no “petition for compensation” having been filed with the mayor and aldermen “ after the commencement and within one year after the completion of the work” which caused the damage complained of, as required by the statute, no application for a jury at the bar of the Superior Court for the assessment of damages could be maintained under R. L. c. 51, § 16. So construed the ruling was right and the agreement of parties intelligible; otherwise they have no meaning.
The petitioner on August 7, 1917, filed a new application for the assessment of her damages arising from the same repair of way described in the earlier petition. The respondent seasonably filed a plea in abatement setting out the pendency of the earlier application for the assessment of damages arising from the same cause, and also pleaded in bar the judgment in that proceeding, if it had gone to judgment. It is stated in the record that “After the trial on the first petition and before bringing the second petition, the plaintiff seasonably served sufficient notice on the proper officers of the city.” For the reasons already stated we construe this to mean that the petitioner seasonably filed a “petition for compensation with the mayor and aldermen.”
The judgment in the earlier proceeding did not constitute a bar to the bringing of the present proceeding. That judgment was not rendered upon the merits, but upon a preliminary matter. The filing of a “petition for compensation with the mayor and aldermen” and a grievance respecting the same either by an inadequate estimate of damages or a neglect and refusal for thirty days to make any estimate, were conditions precedent to the existence of a right in the petitioner to file an application under
Cases like Spear v. Coggan, 223 Mass. 156, to the effect that a defendant ought not to be twice vexed for the same cause of action, have no relevancy to the facts here disclosed.
In accordance with the terms of the report, let the entry be^
Judgment for the petitioner in the sum of $300.