204 Mich. 619 | Mich. | 1919
On December 10, 1915, M. Thomas Ward, plaintiff, by M. Thomas Ward, plaintiff’s attorney, commenced an action against defendant in the circuit court of Kent county by filing and serving a declaration charging defendant under the common counts in assumpsit with being indebted on the first day of November, 1915, to George LeVan in the sum of $200, which indebtedness was averred to have been assigned to plaintiff by said LeVan for a valuable consideration, on November 30, 1915, and defendant though often requested had not paid the same or any part thereof, to plaintiff’s damage one thousand dollars, and therefore he brought suit.
“1915, October, steel ............................. $170.00
1915, October, Cartage and unloading... ........... 6.00
1915, October, Hand Rail ................... m ...... 16.00
1915, October, Hauling Hand Rail.......... 2.00
$194.00”
After being thus advised, defendant pleaded the general issue, with a lengthy notice of special defense that the work, labor and material furnished for which plaintiff’s action was brought, if any, were done and furnished under a special contract in writing by which LeVan undertook to build a bridge for defendant, in which undertaking he failed miserably to defendant’s injury and damage in the sum of $300 for which it made claim by way of recoupment.
On the trial of the case before the court without a jury the testimony developed complications which led the court to offer the following reflection, with which we do not disagree:
“This entanglement involves a good many different-lines and ramifications. It probably would be difficult for a designing mind to get an entanglement with •more avenues of approach or more alleys of escape, if you were getting up a knotty question to see if you could not somewhere trip somebody who claimed to be untrippable.”
The court thereafter made a finding of facts with conclusions of law thereon holding that plaintiff could not recover. Proposed amendments by plaintiff to such findings were refused and defendant had judgment. Exceptions to the refusal to amend findings, conclusions, etc., were duly taken and the case re
Most of the facts out of which the litigation arose are not in dispute. The subject-matter of the litigation was a quantity of steel for concrete • reinforcement bought, but never paid for, by LeVan from the Concrete Steel Company óf New York to be used by him in performance of his contract to construct a small concrete bridge over Mill Creek in a highway of the defendant township of Alpine. The price of this steel as purchased by LeVan from the concrete company was $170 which did not include a steel hand rail procured by him from the same source for, as he testified, “in the neighborhood of $15, $18, $20, somewhere along there.” The plans and specifications for the proposed bridge were prepared and the contract let for its construction by a firm of civil engineers named Riser & Christ, representing the township in that ‘transaction, and LeVan secured the contract which was dated November 24, 1914, by which he was to furnish all necessary tools, labor and material and construct the bridge in. a good and workmanlike manner according to the plans and specifications, made a part of the contract, for $628 and complete the same before December 15, 1914. He thereafter entered upon the construction of the bridge and some time “during the winter of 1914-15” notified the township of its completion, just when is left to surmise. He testified that he built the bridge of cement, steel and gravel and said:
“I put this steel into the bridge and went on and finished up the bridge so that I thought it was finished. It could have a coat of whitewash in the spring; that is what it should have, is about all.”
The township by its officers and the engineers who designed the bridge then inspected it and determined
“4. In tearing down the present bridge span care must be taken to save as much as possible of the imbedded steel and the pipe railing, as it is the intention to use as much as possible of this material in the new bridge span.
“5. The concrete of the demolished span shall be broken up and deposited on the banks adjacent to the bridge as directed by the commissioner.
“6. The old steel must be thoroughly cleaned from all dirt and concrete, restraightened and if necessary rebent to the original shape.”
The abutments to this bridge were not put in by LeVan, but by the township, and in the opinion of
The trial court held defendant’s claim for recoup
“Under the testimony in the case the court finds that the defendant, having removed the first bridge, which was composed of steel and cement, from the place where plaintiff’s assignor built it, the steel being extracted from cement and laid near the place where the second bridge was built, and being used in the construction of the second bridge with the consent of defendant, and it being the intent of defendant from the time of the beginning of the removal of the first bridge to the time the second bridge was constructed*626 to use this steel in construction of the second bridge, that the conversion, if there was such conversion by defendant of the steel in question, was committed at the time defendant first handled the steel, which would be at the time defendant removed the steel from the cement bridge.”
Having so determined the time of conversion, if any, the court in conclusion held that not only had plaintiff failed to prove the market value of the steel at the time it was converted while yet imbedded in the cement of the LeVan bridge, but that it was shown by defendant’s evidence to be without value in its then condition; and on that theory entered judgment for defendant.
One of the “ramifications” in this “entanglement,” to which no reference appears in the court’s finding of facts and conclusions of law, is that soon after this action was brought and before issue was. joined defendant filed a bill of interpleader on the chancery side of the court giving at length its version of the history of this bridge matter up to and including the commencement of this action, alleging that LeVan himself, Gordon C. Dudley as his bondsman, M. Thomas Ward as his assignee, and the Concrete Steel Company, all of whom are made defendants, have each demanded from the township (“your orator”) pay for this steel, saying amongst other things.:
“Said steel that was put into the said bridge built by the said G. F. LeVan went into the second bridge constructed by the other contractor, and your orator received the benefit thereof, and your orator is ready and willing to pay to the proper person whatever sum said steel is reasonably worth, which steel your orator is informed and believes is worth at- a fair valuation the sum of one hundred and seventy-one ($171.00) dollars, and your orator is willing to pay this amount for said steel to whomsoever is entitled thereto.”
The bill contained the customary prayer for relief
M. Thomas Ward thereafter moved before the chancery court for dismissal of the bill and dissolution of the injunction against him, which motion was granted. The grounds of said motion and reasons of the court for dismissing the bill are not disclosed by this record, but the township took no appeal therefrom, and thereafter pleaded in this action as before stated.
Plaintiff filed proposed amendments to the findings of the court under Circuit Court Rule No. 45 embodying the salient facts as to defendant’s bill of inter-pleader and its contents, none of which were granted, exception was duly taken and error is assigned thereon. As those matters are of record and undisputed, plaintiff was entitled to his proposed findings to the extent any of them are material to the issue.
Plaintiff says of defendant’s rather peculiar and unsuccessful excursion info the field of interpleader that, “The township of Alpine had a right to file a plea with a notice of recoupment in this case or to file a bill of interpleader. But our contention is that he had no right to do both,” and it is argued that having by its attempted interpleader declared itself the innocent stakeholder of $171 for the value of this steel claimed by four different parties made defendants, of which plaintiff was one, it cannot thereafter file in this case a plea of denial and notice of recoupment, claiming that money and denying plaintiff’s right to it as assignor of the owner of the steel.
It seems self-evident that the theory upon both the
Thus relegated to its defense in this case it remained for defendant to plead herein as it might be advised. It had not before pleaded, issuably or otherwise, and, held to the issues tendered by plaintiff’s declaration in assumpsit under the common counts, it pleaded the general issue with notice of recoupment. Under the testimony in this case strengthened by the allegations in its dismissed bill of interpleader* which are competent evidence, it is not only manifest that defendant was not in a position to deny LeVan’s ownership of this steel, but that he had in fact bought and owned it at the time he put it into the rejected bridge he built for defendant. That his vendor had granted him credit and he had not yet paid for it was no legal concern of defendant so far as this record discloses.
Though adopting the conclusion that there was a conversion, qualified by the previously expressed view that LeVan had probably lost all rights in this steel by so building it into his bridge that it “became affixed to the land and a part of the highway,” and if so “plaintiff’s case must fail,” the trial court determined the conversion, if any, took place “at the time defendant removed the steel from the cement bridge,” which LeVan had constructed, and that it was without
To follow out the various arguments and theories as to when and how often this steel changed back and forth from personal property to real estate, or when and why or how. the conversion, if any, took place, as mooted by the contingent conclusions of the trial court might, as the court suggested, involve an “entanglement” of questions which, in the language of Imlac, have “long divided the wise and perplexed the good” and we see no reason to pursue them, for we think the court erroneously rejected defendant’s claim of recoupment and the exact time when defendant converted LeVan’s steel to its own use is of minor importance. He purchased this steel to use in the construction of a bridge for defendant over Mill Creek which he had contracted to build. He used it for that purpose. The township rejected the bridge he built because imperfect, unsafe and not according to contract, notifying him of the rejection and its reasons. After due demand that he perform and reasonable time therefor the township did what he under his contract should have done. It tore down the defective and unsafe bridge and built another of the same kind, according to the same plans and specifications as that he had agreed to build. In doing so it saved and used some of the old material which he had furnished for and used in the first bridge in part performance of his contract.
While plaintiff claims a tortious conversion he has waived the tort and sued in assumpsit founding his action upon a claim of quantum meruit, for the value of material furnished by his assignor under and used
“That term is expressive of a right of a defendant to deduct or abate from the plaintiff’s damages any-right of action which defendant may have, growing out of the same transaction, founded either in tort or in contract; but the right is the same, whether expressed by one term or another, or claimed by a plaintiff or defendant.” Bancroft v. Peters, 4 Mich. 619.
Recoupment is not strictly limited to the exact provisions of the contract involved, or sued upon, but is said in Waterman on Set-Off and Recoupment (2d Ed.), p. 480, to be contradistinguished from set-off in three essential particulars:
“1st. In being confined to matters arising out of, and connected with, the transaction or contract upon which the suit is brought; 2d. In having no’ regard to whether or not such matter be liquidated or unliquidated; and 3d. That the judgment is not the subject of statutory regulation, but controlled by the rules of the common law. * * * It is sufficient that the counter-claims arise out of the same subject-matter, and that they are susceptible of adjustment in one action.”
The scope of such defense was early recognized by this court in Ward v. Fellers, 3 Mich. 282, where recoupment is discussed at some length. The opinion, says of its application:
“It is sufficient that the counter-claims arise out of the same subject-matter, and that they are susceptible of adjustment in one action.”
In Allen v. McKibbin, 5 Mich. 449, which holds recovery might be had on quantum meruit for part performance of a non-apportionable contract, the basis
As assignee, plaintiff is entitled to recovery only and just as LeVan, his assignor, might had no assignment been made. Howell v. Medler, 41 Mich. 641.
The trial court found, with abundant supporting evidence, that the reasonable cost and expense to defendant in removing the defective LeVan bridge out of the way, and cleaning and straightening the steel found imbedded in it, was the sum of $200. This was distinctly an item of damages resulting to defendant from LeVan’s nonperformance of his contract, and exceeded the amount claimed in plaintiff’s bill of particulars, or any proven value of the steel used by defendant and for which it was holden. Clearly the counter claims of these parties arose out of the same subject-matter, or transaction, and were susceptible of adjustment in one action.
Though by different avenues of approach, which is immaterial, the right result was reached by the trial court and its judgment is affirmed.