5 N.Y.S. 319 | N.Y. Sup. Ct. | 1889
This action was commenced in equity to obtain relief from a-so-called “penalty” provided in a contract between the parties, and to recover a sum of money. The first, and perhaps the controlling, element in the case is whether or not the sum against which relief was sought was a penalty or fixed and liquidated damages. The facts are quite complicated. A statement of the material facts is necessary to a proper understanding of the case. The undisputed evidence was that the parties made four agreements in writ-' ing. The first one was made' April 28, 1887, and provided that plaintiff should do and finish certain work on, and furnish materials for, two houses-for defendant, at Hill View, South Yonkers, N. Y., on its plots 9 and 27 on the map, under the direction and to the satisfaction of an architect, according to drawing and specifications,—the work to be wholly finished on or before October 1, 1887; and defendant agreed to pay therefor $10,800, in three installments, as the work progressed, provided the architect certified that the work had been done upon which the installments respectively depended. The second contract was made in June, 1887, and contained like provisions respecting the building of two other houses for defendants at same place, on its plots 17 and 19 on said map, for which defendant was to pay $10,100,—in installments upon the architect’s certificates,—the work to be completed on or before January 1, 1888. Each of these contracts provided that plaintiff should pay the defendants $10 per day for every day’s default after the dates fixed for completion of the work, as and for liquidated damages. It seems that plaintiff was to build two other houses for defendant on plots 11 and 45 on said map. The plaintiff was in default under all these contracts on the 5th of March, 1888, and on that day the parties entered into a further contract in writing. This third contract recites the first two contracts above noted, and refers to the provision for the $10 per day as “a penalty.” It then recites that plaintiff desired an extension of time to complete his work, viz., until Marph 25, 1888, on the four houses to be built under the two contracts, dated, one in April, and the other in June, (on plots 9, 17, 19, and 27,) and until August 1st on those to be built on plots 11 and 45. It also recites that the so-called “penalties for default” on the four houses (plots 9, 17, 19, and 27) would amount to $1,540. There would have been 'due to plaintiff from defendant a payment under the two contracts amounting to $1,210 on the houses on plots 17 and 19. The instrument tlien attests a mutual agreement that “the sum or penalty” which would become due March 25, 1888,—the date of the desired extension on houses,—“shall be $1,540 by way of liquidated damages, unless said four houses and all extra work are then entirely finished in accordance with the plans and specifications under the original contracts,” and that no further payments should be made on the houses on plots 9, 17, 19, and 27 until the same are entirely completed on or before March 25, 1888, and that if they were completed on that day the defendant would wTaive all claim to the $1,540, and plaintiff would waive all claim for certain contemplated extra work; and in that event defendant would then pay the $1,210, etc.
Before proceeding to the fourth agreement it will be well to state the intervening facts. Plaintiff claims that they constitute the ground on which he should be relieved from the so-called “penalties.” His evidence shows-that on Wednesday, March 6th, the houses were completed with the Exception of the cess-pools and cisterns, and that three or four days would have been sufficient time in which to have finished them; that on Sunday night, March 10th, the remarkable snow-storm called “the blizzard” set in, and continued until Wednesday morning, the 18th, to such an extent that it was impossible to work in these cess-pools and cisterns; that it was warm and fair
The parties have been most persistent in referring to the so-called “penalty” by two utterly inconsistent and irreconcilable names. In both their original contracts they refer to the $10 per day for default as liquidated damages. The expression in each is the same,—“as and for liquidated damages.” This, then, is the starting-point. The $10 per day was not as a penalty. There was a definite and distinct agreement that it was “as and for liquidated damages.” Then, singularly enough, in their third agreement, which provides for the extension, they talk about the accumulation—the $1,540—in their recitals as a penalty. But when they came to the contractual clauses they varied their description of it, referring to it as “the sum or penalty;” thus showing that there may have been some dispute between them with respect to its exact legal character. But they“settled it. They “mutually agreed that the sum or penalty due under said contract on March 25, 1888, shall be one thousand five hundred and forty dollars ($1,540) by way of liquidated damages. ” They use this precise expression twice during the course of that contract, and then they afterwards refer to it again by the phrase “as liquidated damages.” They here use the latter as distinguished from the former,—the idea of penalty. They could not have made their agreement clearer if they had used the not infrequent phrase, “as and for fixed and liquidated damages, and not as a pen