118 Cal. 676 | Cal. | 1897
Action to foreclose a mechanic’s lien. The defendants employed .Kelley to do the carpenter work hereinafter specified at an agreed compensation of two dollars and fifty cents per day. His labor amounted to one hundred and five dollars, of which forty dollars has been paid, leaving due the sum of sixty-five dollars, for which he filed a lien.
Kelley died after the cause was tried, and his administrator was substituted. Findings and judgment were for the plaintiff, and this appeal is from an order denying defendants’ motion for a new trial, which motion is based upon the alleged insufficiency of the evidencé to justify certain findings, and that the court erred in receiving in evidence the claim of lien filed by the plaintiff.
1. It is contended by appellants that the finding that plaintiff performed the labor, for which a lien is claimed, in the “erection” of a house, is not justified by the evidence.
There is no controversy as to the amount and value of the labor performed by Kelley, but it is said this work was done in “the alteration and repair of an old house,” and not in the “erection” of a house, as alleged in the complaint and stated in the notice of lien. The answer of defendants is a denial that the work was performed in the “erection” of any house. As to the character of the work done by him Mr. Kelley testified: “The work was done upon the house of the said Cranes in Pasadena. We tore away the south, east, and west sides of the old house, and put up an addition ten feet wide on the south side. The roof of the old building was removed and a new one put on over the old part and the addition, but the floor was not taken up, but was enlarged and raised by putting in underpinning. I made the new house twenty-five feet in width instead of fifteen; added a kitchen eight feet by twelve feet in the rear, and a porch twenty feet by eight feet on the front. All the partitions were new. The ceiling joists were all new. It was lathed and plastered, and the old house was not.”
Mr. With am, a contractor and builder, said: “The building was an old building remodeled.”
George Anderson testified that plaintiff “tore away all of the old house except the north side and a part of the back side and floor. I think all of the front side was removed.” The evidence •for the defendants was substantially the same. We think the finding that the work was performed in “the erection of a dwell
What we have said above disposes of appellant’s second point, viz., that the court erred in admitting in evidence plaintiff’s notice of lien, the objection being that it claimed a lien for labor performed “in the erection of said .dwelling-house,” instead of in the repair of the house.
It is further contended that the fifth finding, to the effect that the lien was filed within thirty days after the completion of the building, is not justified by the evidence.
In the fourth finding it was expressly found that the building was completed on the eleventh day of January, 1894, and the fifth finding also finds that the notice of lien was filed on January 31, 1894
As to the date at which the building was completed there is a material conflict in the evidence. The plaintiff testified that* “The building was substantially finished when I left [January 11, 1894], and was completed by the middle of January, 1894.”
The plaintiff further testified in substance that when he quit work they were out of lumber, and there was only a few feet more
Such discharge, under the circumstances stated, was an acceptance of the work as a completed contract for the erection of the building, and the notice of lien might be properly filed at any time within thirty days thereafter.
Appellants further contend that their motion for a new trial should have been granted because the court found that “all of said realty is necessary for the convenient use and enjoyment of said building.”
The property is described as irlot forty-two (42) of a resubdi-vision of E. Turner’s tract, according to a map of said tract.” The complaint, by inadvertence, doubtless, used the expression “convenient use and enjoyment,” instead of the language of the statute, “convenient- use and occupation.”
No issue was taken by the answer upon this allegation of the complaint, nor was there any evidence as to the size of the lot.
It is argued that there is a wide difference between the words “enjoyment” and “occupation”; that a much larger parcel of land might be required for the former than the latter, and that hence the finding and decree may embrace more land than is authorized by the statute.
We see no material distinction between the two words in this connection. In Tunis v. Lakeport etc. Assn., 98 Cal. 286, it was said: “'The expression, 'the land upon which any building .... is constructed, together with a convenient space about the same, or so much as may be required for the convenient use and occupation thereof/ should be construed to mean such space or area of land as is necessary to the enjoyment of the building for the purpose in view in its construction”; thus using the word “enjoyment” as synonymous with occupation. Besides, in the ab-
The order denying a new trial should be affirmed.
For the reasons given in the foregoing opinion the order denying a new trial is affirmed.