This is an action to enforce a mechanics’ lien. Plaintiff, as subcontractor, lathed and plastered a building erected on the premises of the defendant Midland Realty Company. Defendant Huggins was the original contractor. One of the defenses raised by the pleadings is that the work was not done according to the plans and specifications as required by the contract. The cause was sent to a referee who heard the evidence and reported his findings of fact and conclusions of law in which he found that the work was not done by plaintiff in compliance with the plans and specifications; that the reasonable cost of making it conform to the contract would be $800, but that since, the defendant owner had deducted only $500 from the contract price as compensation for the
The defect in the plastering was in the workmanship. It was left uneven and “wavy” on the surface. The contract required plaintiff to do the job in a workmanlike manner and to the satisfaction of the architect. The finding of the referee and trial court is that the job was not done in such manner and it appears the architect refused to accept it. The owner purposed renting the building and it was occupied by tenants as soon as completed. It is conceded the owner sustained no loss of rentals on account of the defect and it does not appear that the plastering will be any less durable than it would have been had it been finished in a workmanlike manner, i. e., with a smooth and 'even surface. Over the objections of plaintiff, defendant was allowed to introduce evidence tending to show that in order to make the work conform to the contráctil would be necessary to remove substantially all of the finishing coat and replace it and that the reasonable cost of such work would be about $800.
Defendant also offered to show by a competent witness “the difference in the value of that building with the plasterer’s job in the condition it was left by Mr. Walter and what would be the value of it had the plastering been first-class and the best of its kind called for by the specifications.” Plaintiff objected on the ground that such evidence is irrelevant and immaterial and the objection was sustained by the referee. The defendant owner occupied the building by its tenants from the date of its completion to the date of the trial,
This is on the theory that the owner of the building has a right to require that it be built by the contractor according to the terms of the contract and that where any part of the work is in defect of the contract the owner may repudiate it and have it replaced at the cost of the delinquent contractor. The soundness of this rule cannot be questioned in instances where the owner* insisting on an adherence to the terms of the contract, acts seasonably in having the defective work removed and replaced. In such cases he is entitled to compensation for his direct and consequential damages resulting from the breach of contract. But the applicability of the rule of which we are speaking to cases such as the present where the owner, without waiving the contract or acquiescing in its deficient performance takes possession of the building and by long continued use evinces a purpose to use work defectively performed as long as it may be used, is a serious question that calls for thorough investigation and analysis.
The rule contended for by plaintiff thus is stated in the brief of his counsel: “Where work is improperly done under a building contract and the owner, with .knowledge of the defect, takes possession of and uses the building without waiver, the amount of damages would be the difference between the value of the work as done and as it should have been done. This is the equitable rule and no other ought to prevail,
In Marsh v. Eichards,
In Wright v. Sanderson,
“The rule as to the measure of damages laid,down by the court is a correct one as to building contracts, in all cases where the contract price is a fair valuation for the work and it has been completed in general conformity to the requirements of the contract, but has been defectively executed in some particulars, and the suit is for the contract price, and defendant does not seek to recover any special consequential damages by way of recoupment.” But the court proceed to say that a different rule obtains in instances where the work has not been done in general conformity to the specifications but deviates from them either in plan or in the materials used. In such cases, and it was a case of that kind we considered in Wright v. Sanderson, supra, the rule for measuring the damages “is to as-, certain what it will cost to make the building conform to what the builder contracted it should be.”
“And cases might arise,” say the court, -“where the deviation from the terms of the contract would be so gross and reprehensible that the builder should not be’ permitted to recover anything for his work.
“Courts have no right to make contracts for the parties, and they cannot compel a man to pay for a building for which he did not contract, and which he does not want, and which he would rather have re
Hirt v. Hahn,
In Spink v. Mueller,
“Unquestionably the measure of plaintiff’s damages is the sum which he necessarily expended to make the varnishing of the wood work of Ms house to conform to the contract, whether such sum be more or less than the sum for which the defendants contracted to do the work.” Judge Biggs challenged this rule in
“I think the true measure of plaintiff’s damages is the difference in value between the work as done and as it ought to have been done. It must be kept in mind that we are dealing with a building contract, and the law as applicable only to such contracts must be considered. I do not for a moment question the correctness of the rule stated in Playsler v. Owen,
The Supreme Judicial Court of Massachusetts in White v. McLaren,
The Supreme Court of the Hnited States had before it a case where the plaintiff sued to recover the remainder of the purchase price of certain machinery installed in defendant’s mill in a manner to make the machinery a part of the mill and, therefore, a part of the land. The defense wás that the machinery which was being used by the defendant did not comply with the contract. Held, “In such a case, it would be most unreasonable to compel the defendant, in order to entitle him to avoid paying the whole contract price, or to recover damages for the plaintiff’s breach of contract, to undergo the expense of taking out the ma
In Davenport v. Freeman,
In its essential facts the case in hand more nearly resembles the case of Spink v. Mueller, supra, than any other we have reviewed. The rule applied in the majority opinion was borrowed from the leading case of Haysler v. Owen, supra, and is the rule which the Supreme Court says in that decision applies to cases where the building has been completed but the work in question “differs in plan of construction or in materials employed from that which the builder contracted
Paraphrasing what was said by the Supreme Court of the United States in Stillwell v. Phelps, supra, it would be most unreasonable to compel the owner in order to entitle him to avoid paying the whole contract price or to recover damages for the plaintiff’s breach of contract to undergo the expense of replacing the plastering and the loss of rentals while such work was being done. If the owner is willing to continue in the use of the defective work, that is its privilege,
The judgment is affirmed.
