202 A.D. 10 | N.Y. App. Div. | 1922
Plaintiff was erecting at No. 11 Central avenue in the city of Albany a five-story building to be used as an automobile salesroom and garage. It contracted with the defendant for the sum of $4,000 to install in the building an automobile freight elevator. The plaintiff was to prepare a suitable shaft or hatchway for the elevator, prepare a place for the machinery, make a pit in the bottom of the hatch, and remove all obstructions which might interfere with the installation of the elevator. The defendant agreed to complete the installation three weeks after the hatchway was in readiness on condition that it “ have the uninterrupted use of same.” April 17, 1920, plaintiff notified the defendant that the hatchway was ready. Defendant did not complete the installation of the elevator until July twelfth following. Plaintiff brings this action for a breach of contract by the defendant alleging as damages that it was deprived of the rental value of the building because of the defendant’s delay. The defense is that the defendant did not have the uninterrupted use of the hatchway and that the defendant in the prosecution of the work met with obstructions and interference by reason of other building operations going on at the same time.
It appears that the contractor in the construction of the building was continuing the building operations after April seventeenth. The contractor had a hod hoist in the elevator shaft and there is
There is considerable evidence it is true that the defendant did not prosecute the work with the diligence it might have exercised. It did not have its material promptly at the building; it did not always have as many men there as it might have provided. Perhaps it might have completed its contráct much earlier than July twelfth. It may have been more interested in the performance of another contract. All that avails the plaintiff nothing if it failed on its part to observe its contract by furnishing the defendant the uninterrupted use of the hatchway for the three
The verdict directed was for $1,332.96. In arriving at this amount the court evidently made a computation based on a lease in evidence which the plaintiff had executed to be operative from the first of June if the building was in suitable condition on that date. The lease recited a rental of $14,000 annually. The court considered that the plaintiff had been deprived of such rent from June first to July twelfth, when the elevator was completed. But the lease covered not only the building in question but another building. It consequently constituted no evidence as to the rental value of the building in question and could not properly be made a basis for damages. No other evidence of damage appears in the case which can sustain a verdict for the amount directed.
It follows that the judgment and order should be reversed and a new trial granted, with costs to the appellant to abide the event.
All concur.
Judgment and order reversed and new trial granted, with costs to the appellant to abide the event.