174 P. 156 | Or. | 1918
Lead Opinion
The plaintiff Wallace was bound only by the terms of his subcontract. He was not bound by the terms of the original contract except in so far as the original contract was incorporated into the subcontract. From that part of the subcontract above quoted, it appears that the original contract was referred to on account of the plans and specifications, for the purpose of providing. the manner in which the work should be done.
A reference in a subcontract to the general contract for a particular purpose makes it a part of the subcontract only for the purpose specified. Therefore, the other terms and conditions of the original contract, between the contractor and the owner, do not affect the subcontract: Guerini Stone Co. v. P. J. Carlin Construction Co., 240 U. S. 264 (60 L. Ed. 636, 36 Sup. Ct. Rep. 300); Myers v. Joseph A. Strowbridge Estate Co., 82 Or. 29 (160 Pac. 135); 9 C. J., p. 710.
If A should employ B to cut 100 cords of wood upon a certain quarter-section of land at a certain price, which B agreed in writing to do, if it should transpire that A did not own the land or wood, and had no right
It does not, however, appear from the evidence that there was any real objection upon the part of the Water Commission to the work being performed by plaintiff Wallace and Phelan Construction Company with whom he had made satisfactory arrangements. The evidence stands uncontradicted to the effect that the Oregon Engineering and Construction Company desired some excuse for not carrying out its contract with plaintiff, because he had made arrangements to have the work done at a profit of 4 cents per lineal foot of pipe.
*38 “In order to prevent disputes and litigation, the Engineer shall in all cases by the' referee to determine the amount, quality, acceptability and fitness of the several kinds of work and material which are to be paid for under these specifications, and to decide upon all questions which may arise as to the fulfillment of said contract on the part of the contractor, and his decisions and determinations shall be final and conclusive.”
It is contended by counsel for defendant that the engineer in charge of the work had authority to settle all disputes arising in regard to the fulfillment of the contract. This provision in the original contract pertains to questions that might arise in the execution of the work pursuant to the agreement. It does not give the engineer authority to decide whether or not the contract executed by plaintiff and defendant is a valid one, or oust the jurisdiction of the courts to try an action of damages for a breach of the contract. Such was not the purpose or intention of the stipulation in the original contract: Lauman v. Young, 31 Pa. St. 306. It was error to grant the motion for a nonsuit, and therefore the judgment of the lower court is reversed, and the cause will be remanded for such further proceedings as may be deemed proper, not inconsistent herewith. Reversed and Remanded.
Rehearing
On Motion roe Reheaeing.
(175 Pae. 445.)
Department 2.
Mr. Thomas Mannix and Mr. Grant B. BimicTc, for the petition:
Mr. J. Bean Butler and Mr. Joseph E. Hedges, contra.
Appellant’s counsel has cited respectable authorities from other jurisdictions, sustaining his position,, but with one or two exceptions, where a nonsuit has been granted by the lower court and the case has been reversed in this court, it has been the practice to remand the case for a new trial. It appears upon the
Overruled.