26 S.C. 80 | S.C. | 1887
The opinion of the court was delivered by
The plaintiff brings this action for
At the close of plaintiff’s testimony, a motion was made for a non-suit substantially upon the grounds: 1st. That under the charter of the company, the board of directors was charged with the general management of the affairs of the company, and there being no evidence that the board had ever delegated any of their powers to said Walker, he had no power to make any contract binding on the company. 2nd. That the alleged contract, having been made prior to the sale of the road and the organization of the new corporation, could not be binding upon it. The motion was refused, because, there being some evidence that the plaintiff had furnished materials under the contract, both before and after the reorganization of the company, which were received and used
The defendant offered testimony tending to show that James Anderson, by whose authority, as general superintendent of the old company, it was claimed the contract sued upon had been made, never had any connection with or authority over the affairs of the new company, and also offered in evidence the certificate under which the new corporation was formed, together with testimony to the effect that under the regulations of the new company all contracts, to be binding on the company, must be in writing signed by the president, and that no subordinate officer had any authority to make any contract for the company. At the clos^ of all the testimony, the defendant moved to strike out all of the testimony adduced by the plaintiff as to any contract with the old company, and all testimony as to any contract with Anderson, or by his authority, upon two grounds : 1st, because the new company is not bound by any contract made with the old corporation; 2nd,' that no authority has been shown in Anderson, the general superintendent, or Walker, the road master, to make any such contract. The motion was refused, the court saying that the jury would be instructed that the questions for their decision were : 1st. Were the articles furnished by plaintiff under the original contract with the road master of the old corporation ? 2nd. Did the road master of the new company recognize that contract and direct a continuance of it? The defendant then renewed the motion for non-suit, upon the ground that the contract sued upon, not being in writing, is null and void under the statute of frauds, which was refused.
The Circuit Judge then charged the jury, substantially, as follows : that the questions for them to determine were whether the plaintiff furnished the material mentioned under the contract with R. M. Walker, which was to continue until he was ordered to stop, and did Walker, after he became road master of the new company, continue that contract; did Freeland, the person who succeeded Walker as road master of the new company, recognize that contract and direct the furnishing of the material? If the jury found that the plaintiff ■ continued to furnish the material under the contract with R. M. Walker, as road master, and not
The jury having found for the plaintiff, and judgment having been entered on the verdict, defendant appeals upon the several grounds set out in the record.
As to the first and second grounds of appeal, which assail the competency of the testimony of R. M. Walker as to the making of the original contract with the plaintiff, and as to his conversations and transactions with Anderson, the superintendent of the old company, it is quite clear that this testimony was adduced, not as evidence of any contract with the new company, for which it would not, by itself, have been competent, but simply to show the origin of the contract which was afterwards made with the new company, for which purpose it was competent. The new company, having succeeded to all the rights and privileges of the old company, might or might not have continued a pre-existing contract made with the plaintiff for the supply of materials necessary to its operations, and the allegation on the part of the plaintiff, to prove which he had offered testimony, being that his contract rvith the old company had been recognized and continued by the neAV corporation, it was, of course, competent to prove
The third ground of appeal is disposed of by the explicit terms in which the jury were instructed as to the measure of damages, the language of which instruction is quoted above. So that, even assuming that the testimony as to the plaintiff’s transactions with his factor, and his loss of interest, &c., by the failure of the railroad company to comply with the alleged contract, was improperly received, yet it was practically stricken out and the jury directed to disregard it, as they were expressly instructed that they could not give any damages for the loss of credit, the charge of interest on advances and loss of crop, but must confine themselves to “the actual damage of the plaintiff by the loss of material.”
The fourth and fifth grounds complain of error in refusing defendant’s motion for non-suit, on the ground that there was no evidence of any contract binding on the defendant. It is a mistake to suppose that the Circuit Judge held that the new company was bound by the contract with the old corporation, as seems to be implied by the language of the fifth ground. On the contrary, the Circuit Judge, finding that there was some evidence tending to show that the new company had, by its road master, Walker,
It is urged, however, by the appellant, that after it had been made to appear that, under the regulations of the new company, no contract binding upon it could be made unless it was in writing, signed by the president, all the testimony relating to the verbal contract made with the plaintiff by the road master, Walker, should have been stricken out, leaving the case without any testimony whatever as to any contract binding on the new company. Assuming that, under the rules and regulations of the new company, no subordinate officer or agent of the company has any authority to make any contract which will bind the company, but that such contract can only be made by writing, signed by the president (though it is difficult to conceive how such a regulation can be practically carried out, when the multiform operations of such a company are considered, and the numerous occasions in which it becomes necessary for subordinate officers and agents to act for the company), yet we agree with the Circuit Judge, that such rules and regulations are intended for the government of the officers and agents of the company, and cannot be allowed to affect third persons unless brought to their attention. It is true that in earlier days it was held that a corporation, under the common law, could only bind itself by its corporate seal, but this doctrine has long since been exploded, and now it is well settled that a corporation may contract and be contracted with through an agent whose authority may be implied from facts and circumstances showing recognition or ratification by the corporation. Indeed, it seems that the same presumptions are applicable, in this respect, to corporations as to natural persons. See Ang. & Ames Oorp., ch. IX., §§ 283, 284; Bank v. Bivingsville Manufacturing Company, 10 Rich., 95, and other cases cited in respondent’s “Brief.”
In this case there was testimony tending to show that R. M. Walker, the road master, entered into a contract with the plaintiff to furnish just such material as it was necessary for him to have for the proper performance of his duties; that such contract was sanctioned by the general superintendent of the old corporation;
What has already been said, sufficiently disposes of the seventh ground of appeal. The point raised by the sixth ground was very properly not pressed at the hearing, as it is clear that it could not be maintained.
It only remains to consider the question raised by the eighth ground, which is whether the contract is void under the statute of frauds, as being an agreement “that is not to be performed within the space of one year from the making thereof.” The proper construction of these words just quoted from the statute has been the subject of consideration in several cases in this State. In Thompson v. Gordon (3 Strob., 199), they are declared to mean “an agreement not to be performed in the space of a year, and expressly so stipulated. A contingency is not within the statute; it must appear, within the agreement, that it is not to be performed until after the year, to make a note in writing necessary.” So it is said by Johnson, Oh., to be well settled, “that when the agreement, is to be performed on a contingency which may or may not happen within the year, a note in writing is not necessary.” Gadsden v. Lance, McMull. Eq., 92. This seems to be the rule in New York, also, for in Moore v. Fox (10 Johns., 245), it is said: “To bring the case within the statute of frauds, there must be an express and specific agreement not to be performed within the space of a year; and if the thing may be performed within the year, it is not within the act.” The same doctrine is found in the case of Fenton v. Emblers (3 Burr., 1278),
The case of Jones v. McMichael (12 Rich., 176), relied on by •the appellant, does not qualify this doctrine, except, perhaps, in so far as the requirement that it must appear within the agreement that it is not to be performed within a year. In that case, A and B made a verbal agreement, wfiereby A was to erect a steam saw mill on the lands of B, and carry on the same at his own cost, while B was to deliver at the mill, at his own cost, all the timber growing on a certain tract of land belonging to B, and they were to divide the profits between them. It did not appear that any time was specified within which the contract was to be performed. The court said: “The agreement contains no express reference to time; but under it the business was carried on for more than a year, and not 'half the timber was sawed or even felled. If it appeared, as we assume it did, from the quantity of the timber and the capacity of the mill, that the parties, in their agreement, contemplated the lapse of a longer period than one year before the enterprise could be fully executed, then the agreement was obnoxious to that portion of the 4th section of the statute which speaks of an agreement that is not to be performed within the space of one year from the making thereof.”
It will be observed that there was no element of contingency in that contract. On the contrary, by its express terms B was bound to deliver all the timber from the tract of land specified, and if the fact was, as the court assumed it to be, that the amount of timber on that tract of land was more than could be delivered and sawed within a year, then the parties must necessarily be regarded as contemplating an agreement which was not intended to be performed, and could not be performed, within a year. So, that while that case may be regarded as relaxing so much of the rule as requires that it shall expressly appear in the agreement itself that the parties contemplated a contract which was not to be performed within a year, but that such a purpose may be inferred from other circumstances, to wit, from the circumstance, in that case, that, looking to the amount of timber on the land
Testing the contract in this case by the rule as established by the foregoing cases, we think it clear that it does not come within the provisions of the statute. There ivas not only no specified time fixed for the performance of the contract, but it manifestly rested wholly on a contingency. The railroad company had authority to terminate it whenever it pleased by simply notifying the plaintiff to stop delivering the material. It depended wholly upon the will of the company whether the contract should terminate at the end of a month or two months or at the end of a year. Such a contract surely cannot be regarded as an agreement not to be performed within a year from the making thereof.
But even if the contract, when originally made, was obnoxious to the statute, yet, after it had been fully performed by the plaintiff, the defendant could not then avail itself of the statute. Bates v. Moore, 2 Bail., 614; Gree v. Hieks, Rich. Eq. Cas., 17; Carter v. Brown, 3 S. C., 298. If, as we must conclude after the verdict of the jury, the plaintiff continued to furnish material to the railroad company under the original agreement, which was afterwards recognized and continued by the road masters of the defendant company, without any notice to stop, then the plaintiff, having fully performed his part of the contract, is entitled to recover, under the authority of the cases last cited, even if the contract, when originally made, could be regarded as within the statute.
The judgment of this court is, that the judgment of the Circuit Court be affirmed.