74 Wash. 253 | Wash. | 1913
— This is an appeal by the intervener, Bratnober Lumber Company, from a judgment denying a lien upon certain property belonging to the defendants Pierano, for the value of materials delivered at the request of the defendant Lanning, their contractor. Materials for the construction of the building on the property were delivered by the lumber company between May 6, 1911, and September 30, 1911. Eor the materials delivered between May 6th to and including June 6th, the lien was allowed. But for the material delivered between June 7th and September 30th, the lien was refused, on the ground that the new law as to notice, which went into effect on June 7,1911, was not complied with, in that the notice of the contemplated furnishing of the subsequently delivered materials was given on June 6, 1911, before the new law went into effect, and was hence premature. Whether this notice, confessedly prematurely mailed, was sufficient basis for a lien is the sole question presented for our consideration.
The lien law of 1909, Rem. & Bal. Code, § 1133 (P. C. 309 §55), required successive notices to be sent to the owner at the time of each delivery of materials. The act of 1911, Laws 1911, page 376, which went into effect on June 7, 1911, amended the law of 1909, by requiring a single notice to be delivered or mailed “not later than five days after the first delivery of such material.” It is admitted that the owner received the written notice in due course of the mail and retained it. On that circumstance the appellant bases its contention that, the spirit of the statute having been met, the lien should be sustained. It seems plain, however, that unless the notice was given while the law under which it purports to have been given was in force, there was no compliance with that law either in letter or in spirit. • There can be no compliance with a nonexistent law. The real inquiry is, when
In that case we held under the prior statute, Rem. & Bal. Code, § 1133 (P. C. 309 § 55), requiring a duplicate statement of all materials to be delivered or mailed to the owner “at the time” when such material is delivered, that a notice mailed at a subsequent time a few days, a week or a month after the delivery of the materials, furnished no basis for a lien. The
“Until the time arrives when it is to take effect and be in force, a statute which has been passed by both houses of the legislature and approved by the executive has no force whatever for any purpose, and all acts purporting to have been done under it prior to that time are void.” 36 Cyc. 1192.
See, also, State ex rel. Atkinson v. Northern Pac. R. Co., 53 Wash. 673, 102 Pac. 876; Harrison v. Colgan, 148 Cal. 69, 82 Pac. 674; Santa Cruz Water Co. v. Kron, 74 Cal. 222, 15 Pac. 772; Miller v. Kister, 68 Cal. 142, 8 Pac. 813.
The notice in this instance, giving it its utmost effect by reason of its retention by the owner of the property, was no more than actual notice. It will not do to say that the obj ect of the notice is merely to give notice and that any notice which serves that purpose is a substantial compliance with the law. This would nullify the statute. It would make actual notice, however acquired or given, take the place of statutory notice. We have held to the contrary. Robinson Mfg. Co. v. Bradley, 71 Wash. 611, 129 Pac. 382.
We have been cited to no authority, and have found none, sustaining the appellant’s contention.
The judgment is affirmed.
Main, Morris, and Puxxerton, JJ., concur.