305 Mass. 349 | Mass. | 1940
The plaintiff brought this action of contract upon a declaration which alleges, in substance, that the parties entered into a contract whereby thé defendant agreed to pay to the plaintiff a sum equal to eighty-five per cent of all materials and labor furnished by one of the defendant’s subcontractors, one Wilgoren, “up to and including the tenth day of July, 1937, less certain payments previously made by the defendant to the plaintiff; that said payment was to be made on the eighteenth day of July, 1937,” but that the defendant had failed to pay as agreed. The answer contains a general denial, plea of payment, and, further, an allegation that if there was a contract between the parties, it was “predicated” upon the performance of “the contract of . . . Wilgoren by” him, and that he “breached his contract with the defendant and did not perform the same.” The case was referred to an auditor and thereafter was tried by a judge of the Superior Court upon the report of the auditor and other evidence. The judge found the facts as found by the auditor to be true, except as stated in his findings, denied certain requests for rulings of the plaintiff, made certain rulings, and found for the defendant. The plaintiff seasonably excepted to his refusals to rule, to two of his rulings, “and to the court’s finding for the defendant.”
On February 12, 1937, the defendant had a written contract for the erection of a theatre and stores in West
The agreement, executed in triplicate, recites the existence of the contract between Wilgoren and the defendant, its partial performance, and that “certain material and labor still remains to be furnished and performed in order to complete” the subcontract. There are further recitals of the amount due the plaintiff from Wilgoren; that the plaintiff “has agreed and hereby does agree to furnish under the terms and conditions hereinafter set forth” additional material required by Wilgoren to complete his contract “up to but not exceeding $2,000”; that the defendant desires “said additional material be furnished by” the plaintiff and that the contract between it and Wilgoren “be performed and completed in accordance with its provisions and without unnecessary delay”; that Wilgoren assigns and transfers to the plaintiff “all sums now due and hereafter to become due from the . . . [defendant], whether for material and labor heretofore furnished and hereafter to be furnished by . . . [Wilgoren] in the performance of the . . . [subcontract] or otherwise due or to become due under said . . . [subcontract]”; that it “is hereby agreed by all parties hereto that the balance which will be due . . . [Wilgoren] upon completion of said . . . [subcontract] will be not less than $7,503”; and that Wilgoren “further agrees to complete said . . . [subcontract] forthwith, in accordance with its terms and provisions,” and to prepare and submit to the defendant forthwith a requisition for material and labor furnished by him “up to the 25th day of June, 1937 and similar requisitions for material and labor furnished up to the 10th and 25th day of each month hereafter.” Following this, the clauses appear in the contract that seem to have caused the trouble: “3. The General Contractor [defendant] agrees to pay to the Assignee [plaintiff] on the 3rd day of July a sum equal to 85% of all material and labor furnished
The plaintiff contends that the quoted paragraph 3 amounts to a separate, independent and unconditional agreement by the defendant to make certain payments to the plaintiff, and “that the total amount to be paid to the plaintiff by the defendant shall be at least $7,503, which amount, so far as appears, has no connection whatever with the amount of the contract between the defendant and Wilgoren.” The defendant contends that it was not the intention of the parties on June 24, 1937, that when the initial payment became due under the contract there was to be a review of all the labor and materials furnished from the beginning of the work, but that the payment called for in paragraph 3 of the contract in question was to be for labor and materials, if any, furnished since the date on which Wilgoren had been paid or was entitled to be paid under the subcontract, that is, since June 14.
In our opinion this three-party contract, although confusing, unsatisfactory and difficult of construction, is not unintelligible and is susceptible of interpretation. “So far as reasonably practicable it should be given a construction which will make it a rational business instrument and will effectuate what appears to have been the intention of the parties.” Bray v. Hickman, 263 Mass. 409, 412. “Where the contract is in writing, there is no fixed and unyielding rule for disposing of contentions touching its meaning except the general one that the intention of the parties drawn from the entire instrument is to be ascertained and applied to the adjustment of the dispute. It is wholly a matter of construction and each contract is to be interpreted according to its own tenor. Resort may be had to certain presumptions or to the circumstances as aids in cases of doubt, but every other rule yields to the purpose of the parties
We cannot adopt the plaintiff’s contention. Prior to the execution of the contract, the defendant had paid Wilgoren on account of the subcontract $7,875.15. The contract that was executed on June 24 has to do with the attempted securing of Wilgoren’s indebtedness to the plaintiff and to the completion of Wilgoren’s subcontract. It speaks of “material and labor [that] still remains to be furnished and performed in order to complete the aforesaid” subcontract, which contract Wilgoren agreed to complete. He assigned “all sums now due and hereafter to become due from” the defendant under that contract. It was agreed that if he completed his contract, there would be due “at least $7,503 less whatever amounts” might thereafter be paid by the defendant to the plaintiff under the contract. When we add this sum to the $7,875.15 that had already been paid, the total, $15,378.15, is very close to the contract price of $15,750 in the subcontract. The last payment to which Wilgoren was entitled under the subcontract, prior to June 24, was due on June 18, and there is nothing to show that it was not made on that date. The next payment would be due on July 3. It is true that Wilgoren, in the contract in question, agreed to prepare and submit to the defendant forthwith a requisition for materials and labor furnished up to June 25, 1937, and similar requisitions for materials and labor furnished up to the tenth and twenty-fifth days of each month thereafter. His contract with the defendant provided for semimonthly payments, in accordance with which he was entitled to be paid on June 18 eighty-five per cent of the value of the labor and materials furnished between the last day of May and June 14, said value to be determined by the defendant. As already pointed out, the defendant had made substantial payments to Wilgoren, presumably upon valuations determined by it. In these circumstances, it hardly
We think that the third paragraph of the contract by which the defendant agreed to pay the plaintiff eighty-five per cent of "all material and labor furnished by . . . [Wilgoren] up to and including the 25th day of June 1937,” relates to the payment of such labor and materials as had been furnished between June 14 and June 25 less what was advanced by the defendant for the payroll due on June 25. "Similar payments” were to be made on July 18 and on the third and eighteenth days of each month thereafter. Such a construction of the contract is in harmony with the "further” agreement of the defendant as to the final payment, by which it agreed to pay the plaintiff “at least” $7,503 less whatever amounts had been paid in the meantime. That the parties so understood the contract finds support in the absence of evidence that the defendant paid the plaintiff anything except for payrolls, with the possible exception of $50 paid on July 6. The evidence does not disclose the reason for this payment. The phrase “less whatever amounts may hereafter be paid by the . . . [defendant] to the . . . [plaintiff] under the terms of this agreement” is explained in paragraph 4 of the contract whereby the defendant “further” agreed to pay the plaintiff the amount of Wilgoren’s payrolls on June 25 and on each Friday thereafter, and in paragraph 6 (a) whereby the plaintiff agreed to apply "all payments” received from the defendant to the payment of Wilgoren’s weekly payrolls "up to but not exceeding a total of $2,000.” It was over these payroll payments and their application that the parties came to grief.
The payroll that was due on July 9 apparently was not met until July 12, when the defendant gave the plaintiff a check for its amount. Notwithstanding this, however, the auditor found, and the judge adopted this finding, that the defendant complied to the letter with the provisions of
By the terms of paragraph 2 of the contract, Wilgoren agreed to prepare and submit requisitions for materials and labor. He did not do this beyond requesting the defendant to furnish checks for the payrolls due on June 25 and July 1. The defendant contends that the furnishing of these requisitions was a condition precedent to any payments by it to the plaintiff, and that because of Wilgoren’s failure to comply it was unable to determine the value of the labor and materials that had been furnished.
Where payment under a contract depends upon some act to be performed by the payee that is a condition precedent
The plaintiff sues upon a contract, by the terms of which, it says, the defendant agreed to pay it a sum equal to eighty-five per cent of all materials and labor furnished by Wilgoren “up to and including the tenth day of July, 1937, less certain payments previously made . . . ; that said
In construing paragraph 3 in connection with paragraph 1, which contains the details of the assignment by Wilgoren to the plaintiff, the agreement that, upon completion of Wilgoren's contract, the balance due will be not less than $7,503, and Wilgoren's agreement to complete his contract in accordance with its terms and provisions, the judge ruled that “the values to which reference is made are the values to be determined in accordance with the provisions of the aforesaid separate contract between the defendant and Wilgoren.” We think this was error. Although the subcontract provided that the defendant was to determine the values, and although Wilgoren agreed to complete his contract, we are of opinion that it was not the intention of the parties to the new contract that the defendant should determine the values. It is true that the subcontract is
This court on this record has power to direct the entry of judgment for the plaintiff. G. L. (Ter. Ed.) c. 231, § 124. The plaintiff paid on account of payrolls $2,000.22, and furnished materials amounting to $991.55, a total of $2,991.77. The unpaid balance of Wilgoren’s payroll due July 9 is $227.27, and there is a finding that an additional sum of $176 was paid for Wilgoren’s payroll for July 8 and 9. The total of these sums is $3,395.04, eighty-five per cent of which is $2,885.78. The defendant paid $2,667.73, and this deducted from the last figure leaves $218.05, for which amount the plaintiff is entitled to judgment with interest from July 19, 1937, the date of the writ.
It is unnecessary to consider the other exceptions of the plaintiff.
Exceptions sustained.
Judgment for the plaintiff.