The plaintiff is the owner of land in Windsor on which there is a sand and gravel bank. The defendants are general contractors doing business under the name of Macari Brothers. In November, 1955, the plaintiff agreed to sell to the defendants their requirements of gravel and fill. In April, 1956, the parties entered into a second agreement, whereby the defendants were granted the exclusive right to withdraw gravel and fill from the plaintiff’s property. On November 13, 1956, the parties entered into a third contract, by which the defendants agreed to pay the plaintiff sixteen cents for each cubic yard of gravel and fill removed from the plaintiff’s property and loaded on trucks. Slips showing the yardagе removed by each truck were to be delivered to the plaintiff at the close of each day on which material was taken. The contract provided, as well, that the plaintiff was to receive credit for a sale of seven cubic yards of material for each load removed by any vehicle commonly
The defendants first began to remove gravel from the plaintiff’s premises in November, 1955, and they ceased operations on March 31, 1957, the termination date of the contract of November, 1956. Before the removal of any gravel by the defendants, a survey had been made of the gravel bank by a civil engineer, who prepared a map showing the topography of the land. On the termination of the contract, the engineer madе another survey to determine the extent of the area of excavation and the amount of material removed from the property. While the defendants were taking out material, the
The plaintiff brought this action to recover damages for breach of contract, and for an accounting. He relied, for relief, on his claim for damages for breach of contract. The trial court concluded that the plaintiff had failed tо prove, by a fair preponderance of the evidence, that he was entitled to damages resulting from any breach of the contract and rendered judgmеnt for the defendants.
The plaintiff’s right to recover for material removed from his property is limited to the period of time covered by the contract of Novеmber 13, 1956. The release signed by the plaintiff on the date of the execution of that contract bars him from recovery on any claim arising out of the relationship of the parties before November 1, 1956. In calculating the amount of material removed under the last contract, the plaintiff has ignored its provisions. The parties agreed on a formula for the measurement of the material taken, and they are bound by their agreement. Regardless of the amount of material removed by trucks of the type specified in the contract, the amount of material to
It is true, as the plaintiff claims, that the trial court accepted certain conclusions of the plaintiff’s engineer but did not accept all of the measurements and computations on which those conclusions were based. Even though the conclusion reached by the trial court that the plaintiff was not entitled to damages may have been based on a wrong theory, the plaintiff cannot complain so long as the decision is properly supported on other grounds.
Clark
v.
Shaw,
The plaintiff also contends that the defendants did not carry out their obligation under the eon-
The claim that the court erred in refusing to strike certain evidence is without merit.
There is no error.
In this opinion the other judges concurred.
