Wagner v. St. Peter's Hospital

32 Mont. 206 | Mont. | 1905

ME. COMMISSIONER CLAYBERG

prepared the opinion for the court. Appeal from a judgment.

The suit was to recover a balance alleged to be due on a contract for repairing and altering St. Peter’s Hospital, in the city of Helena. The full contract price was $4,748, of which the defendant had paid the sum of $4,348, but refused to pay the balance of $400, because it claimed that plaintiff had failed to fully complete his contract.

Plaintiff alleges that he entered into a subcontract with one Burley R. Streets to do the painting according to the specifications, and under the directions and to the satisfaction of the architects, and “which painting was thereafter done and performed by said Streets”; that thereafter Streets commenced *211an action against plaintiff to recover the contract price- of $350; that appellant had full notice of such suit; that Streets recovered a judgment against plaintiff for $371.50 damages and $26.80 costs of suit; that by said judgment it was in effect decided and determined that Streets had fully and completely performed his said subcontract for painting according to the specifications for said work; tbat plaintiff bad paid sucb judgment; tbat be bad furnished all materials and performed all tbe work under and in pursuance of said contract, and bad duly completed tbe same, and in all respects fully performed all tbe conditions of said contract on bis part to be performed; wherefore be prayed judgment for $400, tbe balance due on tbe contract, and tbe further sum of $26.80 which Streets bad recovered against him for costs, together with interest. It is apparent from this complaint tbat plaintiff relied on tbe Streets judgment as being res adjudicata against appellant on tbe proposition tbat plaintiff bad fully performed bis contract.

Tbe appellant filed its answer, and denied tbat tbe judgment of Streets against tbe plaintiff was res adjudicata against it at all; and for further answer alleged, after setting forth a portion of tbe contract between it and plaintiff, tbat be failed to complete tbe painting specified in tbe contract and specifications, and tbat it bad demanded of him tbat be do sucb painting; tbat be bad refused, and tbat it bad caused tbe same to be completed at a cost of $305. Tbe answer further alleged tbat plaintiff bad entered into a subcontract with one Gust G. Minter for placing a roof on tbe building, at a price of $159.25, and tbat plaintiff failed to pay Minter any amount other than tbe sum of $110; tbat Minter filed a mechanic’s lien for tbe balance of $49.25, which tbe appellant paid in order to release tbe lien, and alleged tbat under tbe terms of tbe contract it was entitled to retain tbat amount out of any moneys due plaintiff on tbe contract. It was then alleged tbat there was only a balance of $44.75 due tbe plaintiff, which it was ready and willing to pay, and admitted that plaintiff was entitled to a judgment for tbat amount. In tbe replication a *212portion of this new matter was denied, and a portion admitted. The cause came on for trial before a jury. After the presentation of plaintiffs testimony, counsel for defendant requested the court to instruct the jury to find a verdict for plaintiff for the sum of $44.75, which request was refused. Defendant offered no testimony. The court, upon request of plaintiff, instructed the jury to bring in a verdict for him for the sum of $400. Such verdict was rendered, and a judgment entered thereon, from which this appeal is taken.

The main question presented in the briefs of the respective counsel, and on their argument before this court, was as to the effect of the Streets judgment, counsel for appellant contending that said judgment was not res adjudicata against it for any purpose, and counsel for respondent contending that said judgment was res adjudícala as to the proposition that the contract between the appellant and respondent had been fully performed.

Counsel for respondent cite to the court and rely very strongly upon, the case of Hoppaugh v. McGrath, 53 N. J. L. 81, 21 Atl. 106, as being conclusive upon tbis proposition in tbeir favor. An examination of tbis decision leaves us of tbe opinion tbat it has no bearing upon tbe case at bar. In tbat case A, tbe owner of property, let a contract to B to erect certain buildings tbereon. B subcontracted witb 0 to do tbe masonry work. A sued B for breach of contract because of defective masonry work. B notified C of tbe pendency and object of tbis suit, and called on bim to come in and help defend it, wbicb C disregarded. A recovered a judgment. B then sued C for breach of contract because of defective masonry work,- and tbe court held tbat tbe judgment of A against B was conclusive against C. We are of tbe opinion tbat tbis decision is correct, on tbe principle tbat C, by failing to perform bis contract witb B, to B’s damage, and having notice of A’s suit, was liable therefor. A recovered a judgment against B for a breach of the contract between them. Tbis breach was caused by tbe act of C, and be was clearly *213liable over to B for whatever damages A sustained because of such breach. The case comes clearly within the principles uniformly adopted and enforced in cases where a city is held liable for negligence occurring through the fault or act of some third person, and other cases of similar character. In such cases such third- party is always liable over, upon the principle that, except for his act, no liability whatever would have existed. The same court which decided the Hoppaugh Case afterward held that a judgment procured by a subcontractor against the principal contractor, for which the subcontractor sought to enforce a lien against the owner of the premises, was not conclusive upon such owner, and says: “Nor do we think the owner is bound by the fact that a judgment has been recovered against the contractor by the claimant. The recovery of such judgment is evidential of the amount due upon his claim, and, without other proof, may be conclusive. But this does not prevent the owner from showing that the claim is' excessive, and the judgment thereon is likewise so, or that it is fraudulent.” (Taylor v. Wahl, 69 N. J. L. 471, 55 Atl. 40.) Counsel for respondent says that this opinion does not refer to the Hoppaugh Case, and therefore does not overrule it. There was no occasion to refer to that case or overrule it. These decisions are entirely consistent with each other, and, in our judgment, properly announce the law.

There is a vast difference between the Hoppaugh Case and the one under consideration, as is recognized in Taylor v. Wahl, supra. Here the appellant has done nothing by which the subcontractor was wronged or injured. No contract relation existed between them, either express or implied. By virtue of the contract between appellant and respondent, and the statutes of this state, Streets, the subcontractor, by a proper proceeding might have made appellant’s property liable for his claim against respondent, if it was not paid or liquidated, but under no circumstances could Streets make appellant personally liable to him for any amount. There was no liability over to respondent. Appellant could not have legally inter*214vened in, become a party to, or entitled to say or do anything in the suit of Streets against respondent, because it had no interest therein, and was and could not be made liable thereon. It was a stranger to that suit, and not privy to either party, or in any way or manner interested therein.

> Suppose, by the contract between respondent and Streets, he was only to paint the outside of the building; suppose Streets performed such contract; his work would not include all the painting provided for by the contract between appellant and respondent. Could a judgment in Streets’ favor against respondent, upon the theory that he (Streets) had fully performed his contract, be binding upon appellant ? It could not have the effect of concluding appellant to the extent that respondent had fully performed his contract with appellant. If not, upon what theory could a judgment of Streets against respondent be binding upon appellant, if the contract between Streets and respondent was identical with the contract between appellant and respondent? Appellant would have no more to do with the contract between respondent and Streets in one instance than in the other. Appellant could not enforce any contract between respondent and Streets, and could have no action against Streets for a breach thereof. Streets’ breach of such contract could not relieve respondent from a judgment for damages in favor of appellant for a breach of his contract with it, even though such breach was occasioned by Streets. Appellant might sue respondent and recover from him damages for such breach. Respondent would be bound under his contract with appellant to fully perform its terms before he could maintain an action upon it.

In order to enable Streets to enforce a lien upon appellant’s property, he would be compelled to make respondent a party to that suit, and litigate with him the correctness of his account, if respondent disputed it. As well said by this court in the case of Missoula Merc. Co. v. O’Donnell, 24 Mont. 74, 60 Pac. 594, 597: “The O’Donnells were not made parties. Under the proof in the record, E. 0. O’Donnell contracted the debt *215for the materials furnished by the plaintiff and became personally liable to pay it. This debt is the only foundation there is for this suit. If there is no debt, there can be no lien. The existence of the lien depends upon the existence of the debt, for which it stands as security. It cannot be enforced until the fact of the indebtedness be shown. This fact cannot be shown except in proper judicial proceedings for that purpose, to which proceeding the debtor is made a party. In other words, no judgment can be rendered or enforced in any case until the debtor is made a party to the proceeding, and the fact and amount of his liability are judicially ascertained. (Gilliam v. Black, 16 Mont. 217, 40 Pac. 303; Kerns v. Flynn, 51 Mich. 573, 17 N. W. 62; Vreeland v. Ellsworth, 71 Iowa, 347, 32 N. W. 374; Lookout Lumber Co. v. Mansion Hotel etc. Ry. Co., 109 N. C. 658, 14 S. E. 35; Simickson v. Lynch, 25 N. J. L. 317; Estey v. Lumber Co., 4 Colo. App. 165, 34 Pac. 1113.) The lien is not in any sense the, or any, cause of action. It is merely an incident, ancillary or subsidiary to the main fact — which is the debt. The creditor may waive his lien — the incidental right — and pursue the debtor upon his personal liability, but he cannot enforce the lien without ascertaining both the fact of indebtedness and the amount of it in the only way recognized by law; that is, by making the debtor a party, and litigating the question of indebtedness with him.” Even then, appellant would not be personally liable (Gilliam v. Black, 16 Mont. 217, 40 Pac. 303), but the lien could only be enforced against its property.

If appellant could not be made personally liable by a direct proceeding, such liability could not be imposed upon it by any collateral one. We are clearly of the opinion that the judgment of Streets against respondent was not res adjudícala against appellant in any respect, and was only evidence that respondent owed Streets that amount on their contract. In order for plaintiff to recover the balance due on his contract from appellant, he was bound to show full performance thereof. It seems to be conceded that the contract specified that he should *216paint the rooms in the second and third floors. He admitted in his testimony, when called as a witness in his own behalf, that he was requested by appellant “to paint these two floors,”' and that he refused to do so. Therefore, according to his own uncontradicted testimony, he had not fully performed his contract. The action being upon the contract, and plaintiff showing that he had not fully performed the same, he would not ordinarily have been entitled to any judgment' thereon. But appellant admits he is entitled to a judgment for $44.75.

Respondent’s position in regard to the Minter labor and lien is that he let a subcontract to one Krigbaum for placing the roof on the building for the sum of $110; that the architects of the building told him that appellant wanted the -roof constructed by one Minter, of Great Palls, and directed respondent to cancel his contract with Krigbaum, and cause the roof to be constructed by Minter; that he canceled the Krigbaum contract, but entered into no contract with Minter, who constructed the roof; that he paid Minter the sum of $110, which he-agreed to pay Krigbaum for the same work; that at the time-the architects directed this change they informed him that if there was any extra charge by Minter the appellant would pay it. The only proof of the authority of the architects to make-such an arrangement, if one was made, is that one or two of' the trustees of appellant told them that the appellant would pay the difference.

It must be remembered that the appellant is a corporation,, and, before it could be bound by what one or two of its trustees, may have told the architects, the burden was upon the plaintiff to show that said.trustee or trustees had authority to so bind the corporation, or that the corporation ratified it. No evidence of this character was presented on the trial of the case.

The contract, as alleged in the answer, provides that appellant might protect itself against any lien which might be filed upon the building by withholding from respondent a sum sufficient to liquidate the same, and the answer alleges that Minter filed a lien for the sum of $49.25, which was discharged upon *217payment by appellant. Neither of these allegations is- denied in the replication. We are therefore of the opinion that appellant had the right to liquidate this lien, and deduct the amount thus paid over from any amount due respondent upon the contract.

We are of the opinion that the court below should have ordered a judgment for plaintiff in the sum of $44.75, and we advise that the judgment appealed from be reversed, and the district court be directed to enter a judgment for plaintiff in the sum of $44.75.

Per Curiam. — Por the reasons stated in the foregoing opinion, the judgment is reversed, and the cause remanded to the district court with directions to enter a judgment for plaintiff, in the sum of $44.75.

Reversed and remanded..