289 N.W. 154 | Mich. | 1939
Prior to and on August 1, 1929, plaintiff was in the contracting business, and had in his employ a certain Mr. Paxton. Paxton desired to have plaintiff build a house for him, and having no lot, they entered into an arrangement with defendant whereby the house in question was built on a lot owned by him. Plaintiff claims that as the work progressed he financed the construction costs, although it appears that a portion of the cost was supplied by defendant. Plaintiff also claims that defendant agreed to give him a "good bankable note" in satisfaction of the sums expended by him in erecting the house on defendant's lot.
Defendant claims that after the original discussion with Paxton he left on a trip and upon his return found the house completed; and that at the request of plaintiff he paid some outstanding lumber bills. *264
Despite the confusion of the testimony, it is reasonably clear that the house was constructed for Paxton on a lot owned by defendant; that defendant paid for materials; and that he was to pay plaintiff the balance the latter had invested in the enterprise.
On August 1, 1929, a land contract for the sale of the property was executed between defendant as vendor and Paxton as vendee. Subsequently defendant executed and delivered to plaintiff the following instrument in satisfaction of his claim, dating the same to correspond with the date of the land contract.
"Flint, Mich. Aug. 1, 1929
"$1143.79 Eleven Hundred and forty three seventy nine
__________ After date, I, we, or either of us, promise to pay to the order of Criss Wagner, having an equity of same in a land contract on south 60 feet of lot 228 Atherton Homestead No. 2, that on sale of same must pay this noot, I being deed holder of this lot, at Industrial Savings Bank, Flint, Mich.
Value received, with interest at the rate of seven per cent per annum.
I must pay interest on this noot as long as it runs % 7 per.
P. O. __________ Due __________ No. __________ (signed) THOMAS KINCAID"
The foregoing instrument is the subject matter of this action. The trial court found it to constitute a note, payable on demand, and entered judgment in the sum of $1,294.63, the total of the unpaid principal and accrued interest.
Defendant appeals, claiming that the instrument in question is not a promissory note payable on demand "but a promise to pay on the happening of a *265 certain contingency," the contingency being a sale of the land contract existing between defendant and Paxton, and that inasmuch as the contingency has not happened, the time of payment has not yet arrived.
Although crudely worded, a reasonable construction of the instrument sued upon leads to the conclusion that it was not to become payable until such time as the land contract between defendant and Paxton might be sold. It does not contain the elements essential to a promissory note. See First NationalBank of Port Huron v. Carson,
The obligation was dated August 1, 1929. Action was instituted in October, 1937. A reasonable time had elapsed and the obligation had become payable at the time the action was brought. The statute of limitations* had not run as the record shows that payments had been made on the obligation at various times between September 1, 1929 and March 23, 1932.
Defendant cites Brooks v. Hargreaves,
Judgment affirmed, with costs to plaintiff.
BUTZEL, C.J., and WIEST, BUSHNELL, SHARPE, POTTER, NORTH, and McALLISTER, JJ., concurred.