2 Mo. App. 254 | Mo. Ct. App. | 1876
delivered the opinion of the court.
This is an action on a penal bond in the sum of $5,070, -conditioned for fulfillment of the terms of a building contract. The contract is set out in the petition, showing that defendant Dette agreed to build a house for plaintiff, according to plans and specifications referred to, with stipulations, among others, that the house was “to be completed and delivered to the plaintiff on or before the 15th day of May, 1871, and that the said building should be free, and should be kept free, from all liens, claims, or incumbrances whatever, for, or on account of, the erection of the same.” Two breaches were assigned : the first alleging a failure to conform to the plans and specifications, and the second charging that the defendant had permitted the enforcement of a mechanic’s lien in favor of one Rogge, upon which plaintiff was compelled to pay $346.10, and also of another, in favor of Wright & Breckenridge, upon which plaintiff was compelled to pay $651.44. The petition prayed judgment “ for said 5,070 dollars debt, and for 1,500 dollars damages.”
The answer admitted the contract and bond, but denied.
The answer further avers ‘ ‘ that, when said building was nearly finished, said plaintiff' told said Dette to give orders to all material men for such amounts as they might be entitled to when their work was completed, and that he would accept and pay such orders, which would then constitute credits against said Dette’s account with said Wagner ; that, in accordance therewith, he gave orders to certain material men when their claims became due, and, among the rest, to the firm of Wright & Brcckenridge, which order-said Wagner duty accepted, and paid thereupon the sum of $300 on account thereof, whereupon said Dette duty credited said Wagner with the amount of said, accepted order in his bill against him, and said Wright & Breckem-idge duly receipted to him, said Dette, for the amount of the same;.
‘ ‘ These defendants state that there are no liens or incumbrances of any kind now existing, or due or unpaid, created by any act of said Dette under said contract, against said building; that the amount of eight hundred and ninety-five 69-100 dollars is now due him on account of work done and performed by him on said building for said plaintiff, and which plaintiff refuses to pay ; wherefore they ask to be discharged with their costs.”
Plaintiff’s reply put in issue the new matters set up in the answer. The verdict was in defendants’ favor, upon the first breach assigned in the petition, and hence we need not notice the points saved relating to that. The bill of exceptions informs us that, on the trial, “the defendants offered to prove that at the time that plaintiff paid the respective sums — the mechanics’ liens, to liogge and to Wright & Breckenridge — there was then due and owing to said defendant, by plaintiff, on account of the contract mentioned in the petition, more than enough to cover the said two amounts so paid, and, further, to prove that there was money in his (plaintiff’s) hands,-owing to defendant Dette, on account of said contract, more than sufficient to discharge the amounts so paid by him; which being objected to by the plaintiff, such objection was sustained by the court, to which the defendant excepted at the time.”
Cax*rying out the theory upon which, apparently, this testimony was excluded, the court instructed the jury for the plaintiff as follows:
“The court furtherinstructs the. jury that it is admitted, by the- pleadings in this cause, that the defendant Dette suffered Louis Rogge and Messrs. Wright & Breckenridge, resjiectively, to fasten material-men liens upon the building mentioned in the pleadings, for materials furnished in and about the construction of said building — Rogge for the sum of 846 dollars and 10 cents, and Wright & Breckenridge for the sum of 651 dollars and 44 cents. And it is further admitted by said pleadings that said lienors respectively recovered judgment in-this court for the enforcement of their respective liens against the defendant Dette, as contractor, and this plaintiff, as owner, of said building.
“ And the court further instructs- the jury that the suffering of said liens and the recovering of said judgments was, and is, a breach of the condition of the bond sued on. And the jury are further instructed that, if they believe from the evidence in the cause that the plaintiff, prior to the institution of this suit, paid and satisfied said -liens, they should find for the plaintiff on the second breach assigned, and assess his damages therefor; and that the measure of the plaintiff’s damage, in that case for said second breach, is the- amount paid by him in discharge of said liens, and 'interest on the sums paid, computed at the rate of six per cent, per annum, from the time or times of paymént until the present time.”
Defendants asked for several instructions which the court refused to give. Among them was the following :
“ The court instructs the jury that, as this action is based upon the breach of a bond for faithful performance of a contract for building, given by defendant to plaintiff, and
. It Avould thus appear that, in the opinion of the Circuit 'Court, the plaintiff, as the case stood, Avas entitled to recover for a technical breach of the bond sued on, though no injury to him resulted therefrom; and that the measure of his recovery would be the sums Avhich he had paid, even though he justly owed every dollar of them, and their payment necessarily went to the diminution or extinguishment of his indebtedness. Such a proposition should be supported by some rule of positive laAv, direct, unequivocal, and absolute, whose authority will override every suggestion of common justice and fairness among men.
Plaintiff’s counsel justify the exclusion of the testimony on the ground that it was ,££ not pertinent to any issue in the •cause.” We think that the passages above quoted from the answer, upon each of which a distinct issue was taken in plaintiff’s reply, furnish a sufficient refutation of this assumption. These specific statements of fact were' perhaps objectionable, or rather unnecessary, as presenting •the evidence Avhich was to prove the conclusions whereon defendants relied. But they undoubtedly presented the conclusions also, to wit: that, as to the Rogge lien, when
Plaintiff’s counsel insist that defendants cannot avail themselves of the fact of indebtedness by plaintiff to defendant Dette, under any circumstances, because it is not pleaded as a set-off. We do not perceive either the fact assumed or the logical result which counsel would infer. It seems-to be supposed that, without a prayer for affirmative judgment in defendant’s favor, there cannot be a defense of set-off. But no such rule exists. Suppose that A sues B upon a promissory note for $1,000. B admits the execution of the note and the sufficiency of the consideration, but, averring that he holds a note executed in his favor by A for $500, asks that this sum be applied in reduction of the amount which A would otherwise recover. Is this defense any less a set-off, because B cannot ask for a judgment against A upon the $500 note?
But let us suppose that, for some technical reason, the counter-indebtedness here pleaded cannot be called a set-off. Is there no other name or description under which it
The manifest object of the stipulation concerning mechanics’ liens was to secure the plaintiff and his property against liability for work or materials after he had once paid the contractor for everything done or furnished about the building. If liens should arise, compelling further payments to third parties, after he had finally settled with the builder, surely the plaintiff’s loss would be greater than it would be if he might deduct the amount of such payments from a balance still due and unsettled. Yet the Circuit 'Court refused to recognize any difference between the two cases. Here was a striking departure from the rule by which a plaintiff, whatever may be his abstract right of recovery, can yet recover only so much money as will indemnify his losses or restore his rights. It is clear that, upon every principle by which courts assume to administer justice between contending parties, the defendants were entitled to prove that the amount of damages actually sustained by the plaintiff was not truly represented by the sum which he had paid in discharge of the liens.
The exclusion of defendants’ testimony, and the action of the court upon the instructions given and refused, were