27 Conn. App. 162 | Conn. App. Ct. | 1992
The plaintiff corporation appeals from the trial court’s granting of the defendants’ motion for summary judgment. The plaintiff claims that the trial court improperly concluded that (1) the plaintiff failed to raise any genuine factual issue regarding whether the defendants acted in bad faith, or waived or became estopped to assert the protection of the Home Improvement Act, General Statutes § 20-418 et seq. (the Act), (2) there was no issue of material fact regarding the existence of the notice of cancellation that the Act requires, and (3) there was no factual issue regarding whether the defendants consented to work performed, thereby barring them from recovering under the Act. We affirm the trial court’s judgment.
On September 14, 1989, the plaintiff submitted the first of ten requisitions for payment, the first nine of which were approved by the defendants’ architect and paid to the plaintiff, minus the 5 percent retainage. On August 30,1990, the architect approved and certified for payment the tenth and final requisition in the amount of $64,000. A total of $35,676 of this sum consisted of the amounts retained from the first nine payments the defendants made. The defendants, however, did not issue final payment. They instead asserted that sums due under the contract’s liquidated damages clause were to be set off against the plaintiff’s final requisition for payment. The defendants also did not agree to submit the dispute to arbitration.
Thereafter, the plaintiff caused a mechanic’s lien to be filed on the Greenwich land records, and commenced
The standards governing our review of a trial court’s decision on a motion for summary judgment are clear. Practice Book § 384 provides that summary judgment “shall be rendered forthwith if the pleadings, affidavits and any other proof submitted show that there is no genuine issue as to any material fact and that the moving party is entitled to judgment as a matter of law.” See Connecticut Bank & Trust Co. v. Carriage Lane Associates, 219 Conn. 772, 780-81, 595 A.2d 334 (1991); Lees v. Middlesex Ins. Co., 219 Conn. 644, 650, 594 A.2d 952 (1991); Trotta v. Branford, 26 Conn. App. 407, 409, 601 A.2d 1036 (1992). While the burden of
We first consider the plaintiffs claim that the trial court improperly determined that no genuine issue of material fact existed as to whether the contract is viola-tive of the Act with respect to notice of cancellation. The plaintiff argues that the notice is contained in the contract’s provision that work was to commence seven days after the plaintiff obtained a building permit. The plaintiff contends that a genuine issue of material fact exists as to the notice requirement because the contract, as drafted by the defendants, states that the work to be performed shall commence seven days after a building permit is obtained and the contract is executed, a time period greater than the statutorily required three day cancellation period in which the agreement could have been rescinded.
General Statutes § 20-429 provides that “[n]o home improvement contract shall be valid or enforceable against an owner unless it . . . contains a notice of the owners’ cancellation rights in accordance with the provisions of the [Home Solicitation Sales Act, General Statutes § 42-134a et seq.].” General Statutes
We next turn to the plaintiffs claim that the trial court improperly determined that no genuine issue of material fact existed as to its claim that the defendants acted in bad faith in seeking to use the Act as a defense. The plaintiff contractor maintains that by virtue of its pleadings and affidavit in support of its opposition to the motion for summary judgment, it raised a genuine issue of a material fact as to the defendants’ alleged bad faith claim, which, if proven, provides an exception to the now established general rule that precludes recovery by a contractor who has failed to comply with the Act’s requirements.
In a series of related cases, our Supreme Court recently held that defective home improvement contracts are unenforceable under almost every imaginable theory of recovery. See Barrett Builders v. Miller, 215 Conn. 316, 576 A.2d 455 (1990) (quasi contract); A. Secondino & Son, Inc. v. LoRicco, 215 Conn. 336, 576 A.2d 464 (1990) (quantum meruit and unjust enrichment); Liljedahl Bros., Inc. v. Grigsby, 215 Conn. 345, 576 A.2d 149 (1990) (implied contract). Although the court clearly stated that defective home improvement contracts are invalid and unenforceable as a matter of public policy so as to afford protection to consumers, it also recognized that disallowing all of these invalid contracts “may lead to a harsh result.” Barrett Builders v. Miller, supra, 326. The court stated that
Here, the plaintiff contends it has sufficiently raised a genuine issue of material fact as to the defendants’ alleged bad faith claim that because the contract is invalid under the Act, the plaintiff may not recover. The essence of the plaintiff’s assertion seems to be that the defendants, by preparing the underlying defective contract through its sophisticated agents (their attorneys and architect), somehow prevailed upon the plaintiff contractor’s innocence and then, after certain work had been performed and payments made, relied on the same contract and the Act as a defense to the plaintiff’s action against them. The plaintiff contends that these allegations in its pleadings and supporting affidavits sufficiently raise a genuine issue of material fact so as to preclude the granting of summary judgment for the defendants. We disagree.
“It is not enough that one opposing a motion for a summary judgment claims that there is a genuine issue of material fact; some evidence showing the existence of such an issue must be presented in the counter affidavit.’ ” United Oil Co. v. Urban Redevelopment Commission, 158 Conn. 364, 377, 260 A.2d 596 (1969). Further, “[i]t is not enough . . . merely to assert the existence of such a disputed issue . . . [instead] the genuine issue aspect requires the party to bring forward before trial evidentiary facts, or substantial evidence outside of the pleadings, from which the material
In urging that we accept its arguments, the plaintiff directs our attention to those cases holding that issues involving motive or intent; Town Bank & Trust Co. v. Benson, 176 Conn. 304, 309, 407 A.2d 971 (1978); or good faith and bad faith; United Oil Co. v. Urban Redevelopment Commission, supra, 381; like negligence cases, should not be resolved by summary judgment. It is clear, however, that this proposition does not relieve the plaintiff from presenting a requisite factual predicate for its claim of bad faith. Multi-Service Contractors, Inc. v. Vernon, 193 Conn. 446, 452, 477 A.2d 653 (1984).
“Bad faith” is an indefinite term that contemplates a state of mind affirmatively operating with some design or motive of interest or ill will. New Amsterdam Casualty Co. v. National Newark & Essex Banking Co., 117 N.J. Eq. 264, 277, 175 A. 609 (1934). Good faith performance of a contract “emphasizes faithfulness to an agreed common purpose and consistency with the justified expectations of the other party. . . .” (Internal quotation marks omitted.) Warner v. Konover, 210 Conn. 150,155, 553 A.2d 1138 (1989), quoting 2 Restatement (Second), Contracts § 205, comment (a).
Our examination of the plaintiffs evidence submitted in support of its allegation of bad faith leaves us unpersuaded as to its claim. Viewed in a light most favorable to the plaintiff, the plaintiff’s affidavits in opposition to the motion for summary judgment deal very frugally with the issue of bad faith. The plaintiff’s
The remaining argument the plaintiff poses has no merit. In light of the clear expression of public policy establishing that the Act precludes a contractor’s recovery under an unenforceable home improvement con
The judgment is affirmed.
In this opinion the other judges concurred.
The complaint specifically sounded in three counts: foreclosure of mechanic’s lien, breach of the written construction contract and a claim in quasi contract.
General Statutes § 20-429 (a) provides in pertinent part: “No home improvement contract shall be valid or enforceable against an owner unless it . . . (6) contains a notice of the owner’s cancellation rights in accordance with the provisions of Chapter 740 [the Home Solicitations Sales Act]
It is noteworthy that subsequent to Barrett Builders v. Miller, 215 Conn. 316, 576 A.2d 455 (1990), the legislature has not amended the Act.
The bold print language of the contract provided in pertinent part, “THIS DOCUMENT HAS IMPORTANT LEGAL CONSEQUENCES; CONSULTATION WITH AN ATTORNEY IS ENCOURAGED WITH RESPECT TO ITS COMPLETION OR MODIFICATION.” Despite this language, the plaintiff’s president negotiated and signed the contract without the assistance of counsel.