Thе plaintiff corporation appeals from the trial court’s granting of the defendants’ motion for summary judgment. The plaintiff claims that the trial court improperly concluded that (1) the plaintiff failed to raise any genuine factual issue regarding whether the defеndants acted in bad faith, or waived or became estopped to assert the protection of the Home Improvement Act, General Statutes § 20-418 et seq. (the Act), (2) there was no issue of material fact regarding the existence of the notice оf cancellation that the Act requires, and (3) there was no factual issue regarding whether the defendants consented to work performed, thereby barring them from recovering under the Act. We affirm the trial court’s judgment.
On September 14, 1989, the plaintiff submitted the first of ten requisitions for payment, the first nine of which were approved by the defendants’ architect and paid to the plaintiff, minus the 5 percent retainage. On August 30,1990, the architect approved and certified for payment the tenth and final requisition in the amount of $64,000. A total of $35,676 of this sum consisted of the amounts retained from the first nine payments the defendants made. The defendants, however, did not issue final payment. They instеad asserted that sums due under the contract’s liquidated damages clause were to be set off against the plaintiff’s final requisition for payment. The defendants also did not agree to submit the dispute to arbitration.
Thereafter, the plaintiff caused a mechanic’s lien to be filed on the Greenwich land records, and commenced
The standards governing our review of a trial court’s decision on a motion for summary judgment are clear. Practice Book § 384 provides that summary judgment “shall be rendered forthwith if the pleadings, affidavits and any other proof submitted show that there is no genuine issue as to any material fact and that the moving party is entitled to judgmеnt as a matter of law.” See Connecticut Bank & Trust Co. v. Carriage Lane Associates,
We first consider the plaintiffs claim that the trial court improperly determined that no genuine issue of material fact existed as to whether the contract is viola-tive of the Act with respect to notice of cancellation. The plaintiff argues that the notice is contained in the contract’s provision that work was to commence seven days after the plaintiff obtained a building permit. The plaintiff contends that a genuine issue of material fact exists as to the notice requirement because the contract, as drafted by the defendants, states that the work to be performed shall commence seven days after a building permit is obtained and the contract is executed, a time period greatеr than the statutorily required three day cancellation period in which the agreement could have been rescinded.
General Statutes § 20-429 provides that “[n]o home improvement contract shall be valid or enforceable against an owner unless it . . . contains a notice of the owners’ cancellation rights in accordance with the provisions of the [Home Solicitation Sales Act, General Statutes § 42-134a et seq.].” General Statutes
We next turn to the plaintiffs claim that the trial court improperly determined that no genuine issue of material fact existed as to its claim that the defendants acted in bad faith in seeking to use the Act as a defense. The plaintiff contractor maintains that by virtue of its pleadings and affidavit in suрport of its opposition to the motion for summary judgment, it raised a genuine issue of a material fact as to the defendants’ alleged bad faith claim, which, if proven, provides an exception to the now established general rule that precludes recovery by a contractor who has failed to comply with the Act’s requirements.
In a series of related cases, our Supreme Court recently held that defective home improvement contracts are unenforceable under almost every imаginable theory of recovery. See Barrett Builders v. Miller,
Here, the plaintiff contends it has sufficiently raised a genuine issue of material faсt as to the defendants’ alleged bad faith claim that because the contract is invalid under the Act, the plaintiff may not recover. The essence of the plaintiff’s assertion seems to be that the defendants, by preparing the underlying defective contract through its sophisticated agents (their attorneys and architect), somehow prevailed upon the plaintiff contractor’s innocence and then, after certain work had been performed and payments made, relied on the same contract and the Act as a defense to the plaintiff’s action against them. The plaintiff contends that these allegations in its pleadings and supporting affidavits sufficiently raise a genuine issue of material fact so as to preclude the granting of summary judgment for the dеfendants. We disagree.
“It is not enough that one opposing a motion for a summary judgment claims that there is a genuine issue of material fact; some evidence showing the existence of such an issue must be presented in the counter affidavit.’ ” United Oil Co. v. Urban Redevelopment Commission,
In urging that we accept its arguments, the plaintiff directs our attention to those cases holding that issues involving motive or intent; Town Bank & Trust Co. v. Benson,
“Bad faith” is an indefinite term that contemplates a stаte of mind affirmatively operating with some design or motive of interest or ill will. New Amsterdam Casualty Co. v. National Newark & Essex Banking Co.,
Our examination of the plaintiffs evidence submitted in support of its allegation of bad faith leaves us unpersuaded as to its claim. Viewed in a light most favorable to the рlaintiff, the plaintiff’s affidavits in opposition to the motion for summary judgment deal very frugally with the issue of bad faith. The plaintiff’s
The remaining argument the plaintiff poses has no merit. In light of the clear expression of public policy establishing that the Act precludes a contractor’s recovery under an unenforceable home improvement con
The judgment is affirmed.
In this opinion the other judges concurred.
Notes
The complaint specifically sounded in three counts: foreclosure of mechanic’s lien, breach of the written construction contract and a claim in quasi contract.
General Statutes § 20-429 (a) provides in pertinent part: “No home improvement contract shall be valid or enforceable against an owner unless it . . . (6) contains a notice of the owner’s cancellation rights in accordance with the provisions of Chapter 740 [the Home Solicitations Sales Act]
It is noteworthy that subsequent to Barrett Builders v. Miller,
The bold print language of the contract provided in pertinent part, “THIS DOCUMENT HAS IMPORTANT LEGAL CONSEQUENCES; CONSULTATION WITH AN ATTORNEY IS ENCOURAGED WITH RESPECT TO ITS COMPLETION OR MODIFICATION.” Despite this language, the plaintiff’s president negotiated and signed the contract without the assistance of counsel.
