224 Conn. 240 | Conn. | 1992
The principal issue in this case is whether the plaintiff contractor produced sufficient evidence of the defendant homeowners’ alleged bad faith so as to survive their motion for summary judgment under the Home Improvement Act (act), General Statutes § 20-418 et seq. The plaintiff appeals from the judgment of the Appellate Court affirming the decision of the trial court granting the defendants’ motion for summary judgment. We affirm.
The plaintiff, Wadia Enterprises, Inc., brought an action to recover damages against the defendants, Carolyne Hirschfeld, also known as Caroline Hirschfeld, and Robert B. Machinist, under theories of breach of contract, quasi contract and foreclosure of a mechanic’s lien. The defendants filed an answer and special defenses asserting, inter alia, that the contract violated General Statutes § 20-429 (a) (6) of the act and was therefore unenforceable.
The opinion of the Appellate Court discloses the following facts. On August 21,1989, the parties entered into a detailed, written contract for the renovation of and addition to the defendants’ house in Greenwich. The defendants’ architect and New York attorneys prepared the contract before presenting it to the plaintiff for execution. The contract provided that a total contract price of $599,314.80 would be payable in ten installments and that the defendants could retain five percent of each installment payment until the architect’s certification of the completion of the job. The contract further provided for substantial completion of the project 170 week days after the building permit was obtained, a liquidated damages clause of $500 per day for failure to complete the project within the time provided in the contract, supervision of the project by the defendants’ architect, and for additional work to be performed at the request of the defendants by means of “change orders.” The contract was a home improvement contract within the meaning of the act. The contract did not, however, provide the notice of the right of cancellation required by § 20-429 (a) (6) of the act. Id., 164.
The plaintiff subsequently worked on the defendants’ house pursuant to the contract and to additional change
On September 9,1990, the plaintiff filed a mechanic’s lien on the Greenwich land records, and subsequently commenced this action to foreclose that lien, and to recover damages for breach of contract and quasi contract. In their answer and special defenses, the defendants denied the existence of an outstanding balance in favor of the plaintiff, and alleged, inter alia, that the contract failed to contain the notice of the right of cancellation as required by § 20-429 (a) (6), and therefore was invalid and unenforceable against the defendants.
The defendants moved for summary judgment with supporting affidavits and a memorandum of law, claiming that the underlying contract was unenforceable pursuant to § 20-429 (a) (6). The plaintiff filed affidavits and a memorandum of law in opposition to the defendants’ motion, contending that there was a genuine issue of material fact as to the defendants’ bad faith. In granting the defendants’ motion for summary judgment, the trial court stated that although bad faith on the part of the homeowner would appear to preclude the homeowner from asserting the protection of the act under Barrett Builders v. Miller, 215 Conn. 316, 328, 576 A.2d 455 (1990), the plaintiff had not provided any evidence that would raise a genuine issue relating to the bad faith of the defendants. The trial court further ruled that waiver was not applicable to this action because Barrett Builders made it clear that a homeowner does not waive the protection of the act simply by making payments and invoking certain provisions of the contract.
The Appellate Court affirmed the judgment of the trial court. Recognizing that Barrett Builders “suggested that bad faith on the part of a homeowner might preclude use of the [a]ct as a defense”; Wadia Enterprises, Inc. v. Hirschfeld, supra, 168; the Appellate
We granted certification limited to the following issue: “Was the Appellate Court correct in upholding the Superior Court’s finding that no genuine issue of material fact was raised by the plaintiff relating to bad faith, waiver, estoppel and/or consent on the part of the defendants?” Wadia Enterprises, Inc. v. Hirschfeld, 222 Conn. 904, 606 A.2d 1330 (1992). We conclude that the Appellate Court’s decision was correct.
I
The plaintiff first contends that the trial court improperly concluded that no genuine issue of material fact existed as to its claim that the defendants had acted in bad faith in invoking the act as a defense. We disagree.
“The standard of review of a trial court’s decision to grant a motion for summary judgment is well established. Pursuant to Practice Book § 384, summary judgment shall be rendered forthwith if the pleadings,
In Barrett Builders v. Miller, supra, A. Secondino & Son, Inc. v. LoRicco, 215 Conn. 336, 340, 576 A.2d 464 (1990), Liljedahl Bros., Inc. v. Grigsby, 215 Conn. 345, 350, 576 A.2d 149 (1990), and Sidney v. DeVries, 215 Conn. 350, 354, 575 A.2d 228 (1990), we stated in dictum that, in the absence of bad faith, a homeowner is privileged to repudiate a home improvement contract that violates the act. In Habetz v. Condon, 224 Conn. 231, 618 A.2d 501 (1992), decided today, we have more fully addressed the bad faith exception and held that proof of a homeowner’s bad faith will preclude that
The plaintiff claims that it has raised a factual issue as to the defendants’ bad faith attempt to use the act as both a sword and a shield to avoid final payment to the plaintiff. The plaintiff directs our attention to the following evidence that it submitted in opposition to the defendants’ motion for summary judgment: the defendants prepared the underlying defective contract through their New York attorneys and architect and then relied on the same contract as a defense to its enforcement; the defendants certified payments and retained five percent; despite certification by their agent, the defendants refused to make final payment, alleging rights in the contract they now seek to repudiate; the defendants withheld one half of the payments pursuant to the contract; the defendants forced the plaintiff to extend credit for change orders under provisions of the contract they now seek to repudiate; and the defendants enforced the delay damages clause and alleged breach of specific parts of the very contract they seek to repudiate.
None of these facts, however, indicates a dishonest purpose. The fact that the defendants had their architect and New York attorneys draft the contract does not in and of itself indicate bad faith on the part of the defendants. There is no allegation or proof that the attorneys intentionally omitted this requirement in order to have an escape hatch. At most, the New
The essence of the remainder of the plaintiff’s allegations is that the defendants acted in bad faith by initially enforcing the contract and subsequently asserting the contract’s invalidity as a defense to a suit by the contractor. This contention does not, by itself, present a claim of bad faith. There is nothing dishonest or sinister about homeowners proceeding on the assumption that there is a valid contract, enforcing its provisions, and later, in defense to a suit by the contractor, upon learning that the contract is invalid, then exercising their right to repudiate it. See Caulkins v. Petrillo, 200 Conn. 713, 720, 513 A.2d 43 (1986). As noted above, the plaintiff did not allege that the defendants knew of the violation earlier, or that they purposely drafted the contract in violation of the act in order later to avoid their obligation to pay. On the contrary, the plaintiff did not even challenge the defendants’ statements in their affidavits that they had been unaware of the act prior to the commencement of this lawsuit. Farrell v. Farrell, supra, 39-40.
II
The plaintiff next claims that the defendants impliedly consented to the work performed and thus cannot now assert the protection of the act. We disagree.
Ill
The plaintiff’s final claim is that the defendants impliedly waived the protection of the act by enforcing certain provisions of the contract and making payments pursuant to the contract. Specifically, the plaintiff claims that by retaining five percent of the payment due, requesting extensions of credit, and certifying payments, the defendants waived the right to raise the invalidity of the contract. We are unpersuaded.
Waiver is the intentional relinquishment of a known right. Dragan v. Connecticut Medical Examining
In this opinion the other justices concurred.
General Statutes § 20-429 provides in pertinent part: “required contract PROVISIONS; ENFORCEABILITY. NEGATIVE OPTION PROVISIONS PROHIBITED. OWNER TO RECEIVE COPY. CONTRACTS CONSIDERED HOME solicitation sales, (a) No home improvement contract shall be valid or enforceable against an owner unless it: (1) Is in writing, (2) is signed by the owner and the contractor, (3) contains the entire agreement between the owner and the contractor, (4) contains the date of the transaction, (5) contains the name and address of the contractor, (6) contains a notice of the owner’s cancellation rights in accordance with the provisions of chapter 740, (7) contains a starting date and completion date, and (8) is entered into by a registered salesman or registered contractor. Each change in the terms and conditions of a contract shall be in writing and shall be signed by the owner and contractor.”
See footnote 1, supra.
The defendants also alleged the following: (1) the contract violated the Home Solicitation Sales Act, General Statutes § 42-134a et seq.; (2) the plaintiff failed to perform all of its obligations under the contract, and has performed certain obligations in a defective manner; (3) the plaintiff abandoned its contractual obligations; and (4) the quantum meruit count of the complaint fails because the existence of an express contract defeats an action of quantum meruit.
In their second answer, the defendants also denied that the liquidated damage clause was a penalty and admitted the extension of the completion date.
Moreover, in their answer, the defendants stated that they had relied on the act for the first time after suit had been brought. This statement was relied upon by the plaintiff at oral argument in connection with the
We reserve the question, as we did in Barrett Builders v. Miller, 215 Conn. 316, 327 n.5, 328, 576 A.2d 455 (1990), of whether the homeowner can recover “a down payment or progress payments made during the performance of home improvements but prior to the discovery of the invalidity of the contract. . . . Arguably, a homeowner who has made such progress payments has impliedly consented to the work performed. The issue raised by a suit to recover partial payments differs substantially from that raised by refusal to pay sums alleged to be due on an invalid contract.”
We conclude, without deciding the applicability of the plaintiffs equitable estoppel claim, that the plaintiff has failed to demonstrate the factual predicate necessary to sustain an action under the doctrine of equitable estoppel. “[Equitable] estoppel is predicated on proof of two essential elements: the party against whom estoppel is claimed must do or say something calculated or intended to induce another party to believe that certain facts exist and to act on that belief; and the other party must change its position in reliance on those facts, thereby incurring some injury.” (Internal quotation marks omitted.) O’Sullivan v. Bergenty, 214 Conn. 641, 648, 573 A.2d 729 (1990). Additionally, “it is the burden of the person claiming the estoppel to show that he exercised due diligence to ascertain the truth and that he not only lacked knowledge of the true state of things but had no convenient means of acquiring that knowledge.” (Internal quotation marks omitted.) Id., 650; Spear-Newman, Inc. v. Modern Floors Corporation, 149 Conn. 88, 91-92, 175 A.2d 565 (1961). Even if the defendants, by-drafting the contract, induced the plaintiff to believe that the contract was valid and the plaintiff relied on the validity of the contract, the plaintiff cannot show that he exercised due diligence in ascertaining the act’s requirements and yet still failed to be familiar with the provisions of the act. As a licensed home improvement contractor, he certainly had the means