103 Ky. 579 | Ky. Ct. App. | 1898
delivered the opinion of the court.
In June, 1S92, tlie appellee entered into a written contract with several parties (appellants) for the erection of a butter and cheese factory at Waddy, in Shelby county, Ky. The construction of that contract is one of the questions presented on this appeal. So much of the contract as bears on the question reads: “We, the subscribers hereto, agree to pay the above amount for said butter and cheese factory when completed, said building to be completed within ninety days or thereabout after the above amount, $3,950, is subscribed. Any portion of the amount subscribed not paid according to contract shall bear legal rate of interest. As soon as the contract price is subscribed, or in a reasonable time thereafter, the said subscribers, agree to incorporate under the laws of the State as herein provided, fixing the aggregate amount of stock at not less than the amount subscribed to be divided into shares of $100 each. Said share or shares, as above stated, to be issued to the subscribers hereto in proportion to their paid-up interest herein, and it is herein agreed that each stockholder shall be liable only for the amount subscribed by him. * * *
Names of subscribers. No. shares. Amount of stock
after incorporation.
J. T. Campbell, 3 $300 00
T. M. Waddy, 2 200 00, etc."
Appellee claims that this contract is joint and not several ; that is to say, that each subscriber is liable to the appellee for the full sum of $3,950.
After this factory was completed and accepted by appel
Appellee sought to recover this balance from the other subscribers as a joint liability. The lower court declined to so adjudge, and the cross appeal is taken.
After the factory was completed appellee filed a statement in the county clerk’s office as to the balance due on the contract, filing the contract as part of the statement, and by reason thereof a mechanic’s lien is claimed on the factory and ground on which same is situate.
This first contract was made June 14, 1892. The articles of incorporation of Waddy Blue Grass Creamery Co. were signed and filed November 9, 1892. The deed to the lot was executed November 12, 1892, and the statement for mechanic’s lien was filed November 18, 1892. This statement was swoyi to on November 16,1892, and it is therein stated that sixty days had not elapsed since appellee ceased to labor and furnish material, and that all the labor and material were furnished under the contract of June 14, 1892. The statement also includes the names of the subscribers to the June contract, as well as Waddy Blue Grass Creamery Co., as debtors in the account. The court below adjudged a mechanic’s lien, on the property, and it was sold and brought $700.
From the judgment declaring a mechanic’s lien and sale to satisfy the same this appeal is prosecuted. We afe
To make the contract joint would render nugatory this latter clause. This view of the contract was held to be correct in Davis & Rankin Co. v. Barber, 51 Fed. Rep., 148, by the United States Circuit Court for the district of Indiana. (Davis & Rankin Co. v. Vice, Indiana Appellate Court, 43 N. E., 889; Davis & Rankin Co. v. Hillsboro Creamery Co., Indiana Appellate Court, 37 N. E., 549; Same Company v. Booth, 37 N. E., 818; Same Company v. Cupp, 89 Wis., 673; and other cases where this contract in effect if not identical in words, was in issue.)
Appellee so construed the contract as is shown by the fact that on the completion of the building its agent collected from each subscriber the amount so subscribed, and gave him a receipt. From others who did not then pay appellee took notes, some with security, and to all who gave notes gave time in which to pay. It is shown that the time granted to J. T. Campbell to pay his note of $1,600 was six months after its date, September 20, 1892. There is no doubt that the contract of June 14, 1892, in so far at least as it agrees to pay appellee the sum of $3,950 is several and not joint. It only bound the subscriber to pay the amount subscribed and shown on the face of the contract as subscribed by him.
The question presented on the original appeal as to the
We are of opinion that the statement was filed within sixty days after the completion of the work. The question then presents itself, does the lien exist? At common law the lien of the mechanic or material man did not exist as to realty, but he had a lien on personalty. The statutory lien given the mechanic while in derogation to the common law'is still within its spirit, and is the outgrowth of the spirit of encouraging general improvement. Its history is that of enlargement and extension in the thing covered, the persons entitled to the lien as well as a liberality in construction of the statutes so as to pay the laborer his hire.
The statute under which this lien is asserted is section 1, article 1, chapter 70 of the General Statutes, and provides: “A person who performs labor, furnishes material in the erection, altering or repairing a house, building or other structure, or for any fixture or machinery therein, * * * of real estate, by contract with, or by the written consent of, the owner, shall have a lien thereon and upon the land upon which such improvement may have been made, or on any interest such owner has in the same, to secure the amount thereof, with costs.”
It will be noticed that while the work done or material furnished must be by contract with or written consent of the owner, there is nothing in the statute fixing the date of the contract as the date of the lien. It has uniformly been held, so far as we are advised, that the lien dates from the beginning of the work or the furnishing the material.
This corporation is composed of the same parties that made the original contract for the factory.
By taking the note of Campbell the lien was not waived. On this note no one became liable but him. (Gere v. Cushing, 5 Bush, 304.)
Finding no error the judgment is affirmed on both original and cross appeal.