71 Ind. App. 674 | Ind. Ct. App. | 1919
— The Strand Theater Company of Illinois and Ernest C. Divine were lessees of the Park Theater in the city of Indianapolis. On October 26, 1915, said lessees entered into an agreement with the appellant whereby they employed appellant, and the appellant agreed to furnish material and perform the necessary labor in overhauling and remodeling the theater building.
Appellant began this work in December, 1915, and continued the same in accordance with the specifications, except that by agreement one item was omitted and a credit of $60 was allowed therefor. Some extra work was done as provided in the contract of the value of $1,234. Said Strand Theater Company of
On June 24, 1916, appellant filed a notice in the office of the recorder of Marion county, Indiana, of its intention to hold a lien upon the real estate upon which said building is located, and upon the leasehold interest of said lessees in said real estate, for the sum of $5,159.20 for the work and labor done and material furnished under said contract. Carl H. Weyl was appointed receiver of all the property and assets of the Indiana company, and as such receiver took possession of said theater building and premises, and the leasehold estate of said company therein, and continued in the possession thereof until August 5, 1916, when, under the orders of the court, he sold and assigned said leasehold to one Shafer Zigler.
Appellant filed its petition in said receivership matter alleging the facts as hereinbefore stated, and asking that its lien oñ the premises be transferred to the funds in possession of the receiver, and that the amount due thereon be decreed to be á preferred debt and claim and a lien upon the funds in the hands of the receiver derived from the sale of said lease and leasehold estate.'
Appellant’s exception to the conclusion of law presents the only question for our determination. The only question presented by the record is: Was the notice of the mechanic’s lien filed within the sixty days after the furnishing of the materials and the performance of the labor as required by the statute? The court found the-facts in substance as herein-before stated. The court also found that all the materials and all of the work which was done and performed by appellant were fully completed by appellant during the last week in January, 1916, and before the first day of February; that said work and materials were accepted by the Indiana company through its duly authorized representative at- said time; that thereupon appellant removed all of its apparatus and material from said premises and turned said theater and work over to the Indiana company and rendered its statement for said labor and materials, and that said work at that time was completed in accordance with the contract between the Strand Theater Company of Illinois and appellant, and was done in a proper and complete manner; that during the early part of February, 1916, and when said bill for said work was submitted to the Indiana company, it, through its president, objected and urged that certain portions of the work were not properly done, but waived all objections, except the painting of the can
Appellee contends that, under the facts found by the court, the contract was completed by appellant in January, 1916, and that the work of repainting said
In Scheible v. Schickler (1896), 63 Minn. 471, 65 N. W. 920, furnaces were put in a building and were warranted as to their capacity. The contract was fully performed, and the work accepted, but the furnaces did not fulfill the warranty. Under a subsequent contract, the contractor, in satisfaction of all damages, agreed to substitute certain other furnaces, which he did. The notice of lien was there filed within ninety days after the completion of the last work, but more than ninety days after the completion of the first work, and was held filed in time. In Shaw v. Fjellman (1898), 72 Minn, 465, 75 N. W. 705, the court in discussing a similar question said: “After it was supposed that the work had been completed, and it was accepted or taken possession of by the owner, he or his agent might extend the time for filing a lien by requiring additional work to be done to remedy defects subsequently discovered, and the time for filing the lien would commence to run' from the completion of such additional work.” Citing St. Louis Nat. Stock Yards v. O’Reilly (1877), 85 Ill. 546; Jeffersonville Water Supply Co. v. Riter (1894), 138 Ind. 170, 37 N. E. 652; McIntyre v. Trautner (1883), 63 Cal. 429.
The Supreme Court of Minnesota, in Minneapolis
The appellant performed labor and furnished material under the contract of the value of $6,345, for which it had been paid $1,500. It also performed other labor, and suffered loss amounting to $313.75. Appellant does not claim that it was entitled to a lien on the funds in the hands of the receiver derived from the sale of the leasehold estate, on account of the said sum of $313.75, but does contend that it was entitled to have a lien on said funds for the balance of $4,845 with interest, due it on account of the labor performed and materials furnished under the contract/
The appellee is in no position to insist that the repainting of the canopy was a new arrangement wholly independent and separate from the original contract. There is no fact found which indicates that the item of repainting was not done by appellant in good faith for the purpose of completing its contract. "Where the contrary is not found, we will presume that both parties were acting in good faith, and that, when the theater company insisted that the contract was not completed, it honestly believed it was right in that contention. We hold that the repainting of the canopy was “the last item” performed under the contract, and that the time for filing notice of a mechanic’s lien dated from May 12, 1916. Conlee v. Clark (1896), 14 Ind. App. 205, 42 N. E. 762, 56 Am. St. 298; Whitcomb v. Roll (1907), 40 Ind. App. 119, 81 N. E. 106.
The court erred in its conclusion of law. The judgment is reversed, with direction to' the court to restate its conclusion of law in accordance with this opinion.