677 F.2d 850 | Ct. Cl. | 1982
delivered the opinion of the court:
On March 23,1982, post at 835, we issued an order in this contract case, granting defendant’s motion for summary judgment and dismissing the petition, in which order we stated that this opinion would follow. In that order we ruled, on the basis of our opinion in Paul E. Lehman, Inc. v. United States,
Plaintiffs third contention, that it had in effect complied with the statutory certification requirements, was rejected in our order of March 23, 1982, with a statement that our rationale for that conclusion would be given in this opinion.
The facts necessary to our decision are as follows: plaintiff suggested certain changes in the performance requirements of a contract of January 31, 1978, it had with the Defense Logistics Agency and claimed that these changes entitle it to a monetary award based on the savings defendant realized from implementing the suggestions. Both parties agree that plaintiffs claim to the contracting officer was finalized well after the effective date of the act. There is no issue as to whether, if certification is not a barrier to plaintiffs claim, the claim meets the other prerequisites of the act.
Plaintiff argues that documents and letters submitted on its claim for the award, originally on June 15, 1979, and, in subsequent correspondence, including a supplementary memorandum and economic analysis, submitted on September 22,1979, taken as a whole, amount to a certification. In its original memorandum in support of its claim, plaintiff adverted to the economic evaluation attached thereto prepared by Dr. Mitchell, an economist, as follows:
The economic evaluation in support of said memorandum prepared by Dr. John W. Mitchell, an economist,*407 concludes with these words regarding his belief that the amount requested accurately reflects the amount for which the government is liable:
In this situation, the basic theory, the timing of events, actual rejection of low bids, the contrasts with other years, and the opinions of those in the industry would support the proposition that a savings resulted from the implementation of the Moseley Company suggestion. An average of the approaches would support a savings of about $1.87 million.
Section 605(c)(1) states that:
For claims of more than $50,000, the contractor shall certify that the claim is made in good faith, that the supporting data are accurate and complete to the best of his knowledge and belief, and that the amount requested accurately reflects the contract adjustment for which the contractor believes the government is liable.
To begin with, in light of our holdings above, and in Lehman, we must reject plaintiffs assertion that the statute leaves the determination of the adequacy of the certification to the contracting officer’s discretion.
Certification requires that the contractor certify that (a) the claim is made in good faith, (b) the supporting data are accurate and complete to the best of his knowledge and belief, and (c) the amount requested accurately reflects the contract adjustment for which the contractor believes the Government is liable. Because of the significant role certification plays in the statutory scheme, we hold that to properly certify a claim a contractor must make a statement which simultaneously makes all of the assertions required by 41 U.S.C. § 605(c)(1).
Furthermore, the language to which plaintiff adverts in the supporting documents and correspondence, even if it were not presented in a piecemeal fashion, would not meet these specific requirements. Most significantly, the fact that the language, which is supposed to indicate plaintiffs belief that the amount requested accurately reflects the contract adjustment, is written by Dr. Mitchell and not by the contractor invalidates any claim to a proper certification.
Finally, plaintiff argues that now that it has gone back to the contracting officer and certified the pertinent claim, it
Since plaintiff failed to certify its claim as required by section 6(c)(1) of the Contract Disputes Act of 1978, we are without jurisdiction to consider its direct appeal to this court. For this, and the other reasons set out above and in our order of March 23, 1982, and without hearing oral argument, we have granted defendant’s motion for summary judgment and have dismissed the petition.
Paul E. Lehman, Inc. v. United States, ante at 11.
41 U.S.C. § 605(c)(1) (Supp. III 1979).
Paul E. Lehman, Inc. v. United States, ante at 11.