98 Ct. Cl. 519 | Ct. Cl. | 1943
Lead Opinion
delivered the opinion of the.court:
Plaintiff contracted with the defendant to build some thirteen officers’ quarters at Bolling Field in the District of Columbia for $142,046.00. Plaintiff was to furnish all labor and materials to complete the job, except common bricks, which were to he furnished by the defendant. According to the specifications, the basement walls were to be constructed of common bricks, and the walls above the basement were to have a facing of facing bricks backed with common bricks. Before plaintiff submitted its bid, its representatives visited the site and asked to see the common bricks which the defendant intended to furnish for the job. The defendant’s Constructing Quartermaster, who was to be the defendant’s representative in dealing with the contractor,
Plaintiff subcontracted the labor of laying the bricks for $11,400. The bricklaying began September 12, 1932, and bricks from the stock pile were used for about a month. Then the defendant’s agents directed plaintiff to use no more bricks from the stock pile, but to use bricks salvaged from a dismantled steel plant near the site and cleaned. Plaintiff asked for and obtained the contract to clean these bricks. The steel plant bricks were irregular in size and shape, many of them being fire bricks, which are considerably larger than common bricks, and are pemus and absorb the water from the mortar and thus create difficulties in laying them. The larger size of the steel plant bricks made the walls thicker and thus required the use of more mortar.
Plaintiff’s subcontractor protested to plaintiff at the change in the kinds of bricks, and plaintiff agreed to pay him extra compensation for his extra labor: Plaintiff protested orally to the defendant’s representative, the Constructing Quartermaster, who entered into an oral agreement with plaintiff that plaintiff would continue to use the steel plant bricks and would later present its extra costs to the Constructing Quartermaster for audit.
September 25, 1933, after the completion of the contract, plaintiff submitted a claim to the then Constructing Quartermaster for its additional costs, but nothing has been paid plaintiff in that regard. Plaintiff’s increased cost of mortar was $1,649.26, and plaintiff paid its bricklaying subcontractor $4,000.00 to settle a law suit brought against plaintiff by the subcontractor for the increased cost of laying the irregular bricks.
Plaintiff, no doubt for the purpose of by-passing obstacles in the shape of non-compliance with formal requirements of the contract, plants its case upon the theory that the defendant breached the contract as written, when it ordered the
We think that plaintiff’s theory is not supportable. We think that the Contracting Quartermaster’s direction to plaintiff was, except for the form in which it was given, a modification which the defendant had the power'to make, under the terms of the contract. It was either an order for extra work or material within the provisions of Article 5 of the contract and Section 27 of the specifications, or a change order under Article 3 of the contract, which provisions are quoted in finding 15. We are therefore obliged to determine whether the obstacles to recovery which plaintiff by its theory sought to avoid are insuperable, as the defendant urges.
We think that Article 5 of the contract is the applicable article. The Constructing Quartermaster’s direction to use the steel plant bricks was, in effect, an order to use whatever extra labor and extra mortar it 'would take to make walls out of such bricks. So Article 5 fits the situation quite precisely. If neither Article 5 of the contract nor Section 27 of the specifications were present, Article 3 might be made to apply, but that is not necessary with these other provisions present.
When one party writes a contract in its own language, as the Government did here, and inserts in it two separate provisions, either of which might apply to a given state of facts, but different legal consequences would result if one, rather than the other, of the two provisions was applied, the other party to the contract is, in the absence of evidence of a contrary intent, entitled to have applied the provision which would be least burdensome to him.
The defendant urges that, even though Article 5 is the applicable article, and it contains no requirement of approval by the head of the department of an order for extra work or material, yet such a requirement should be read into Article 5 by implication. The defendant argues that the contract is not very rational unless these two articles are read as being consistent with each other. We are inclined to agree. But it was the defendant’s writing, its standard
•We coiné now to the question whether the• Constructing Quartermaster's failure to write his order for the extra work and materials prevents plaintiff from recovering for them.
It would have been impracticable for either plaintiff or the Government to have followed strictly the injunction of Article 5 in this case. The right price for the extra work and mortar could only have been guessed at when the order was first given. Ordinary prudence on the part of each •would have required what was done here, viz, the deferment of consideration of the cost to a later time. Our observation of cases litigated here tells us that this kind of prudence is frequently practiced in such situations. If the Constructing Quartermaster had done here what was agreed to be done, and had given plaintiff a written order after the extra cost had been determined, the bill would quite certainly have been paid, though Article 5 would not have been strictly complied with. If the Constructing Quartermaster had, at the time he gave his order, said in writing what he said orally, that would not have been a compliance with Article 5, which requires that the “price (be) stated in such order.” Strictly, plaintiff could not have protected itself against what has here happened to it except by refusing to obey the order and demanding that the Constructing Quartermaster do, in writing, what was impossible to do at all, viz, fix a price which could not prudently be fixed at that time. Perhaps that would have been correct practice.
Our question is, however, not what would have been correct practice when the extras were ordered, but what to do with a case in which the responsible representative of the
The law as it relates to persons other than governments has frequently encountered the same problem, and has usually succeeded in vindicating the purpose of the formal requirement, without at the same time leaving one man’s money in another man’s pocket. For example, the Statute of Frauds, setting up a formal requirement by statute, and not by mere contract, and threatening the unwritten transaction with such ominous consequences as that it should be “void,” has not, in effect, been permitted to do more than to nullify unperformed agreements, leaving the parties, in general, where they would have been if the informal transaction had not occurred. Likewise the omission of a seal, if in fact there is a consideration paid, only demotes the deed to the position of a contract, fully enforceable in equity.
Even in the sphere of government dealings, the neglect to advertise for bids, though such advertisement was required by statute, has not been permitted to justify the Government in receiving property manufactured for it and using it without paying what it was reasonably worth.
If the law has been able to accomplish so much justice, in the face of apparently forbidding statutes, without impair
There is not a word in the record to show that thé order of the Constructing Quartermaster, by which he saved some hundreds of thousands of bricks of good quality and diverted them to a more economical use for the Government, was in fact given without consultation with and sanction of his superior officers in the department. There is no evidence that the department was not pleased at and benefited by the result accomplished by the order. There is no evidence that the Constructing Quartermaster was disciplined or even reprimanded for having, in violation of the mandate of the defendant’s standard contract, ordered this extra work, the consequence of which was, unless we give relief, to cheat this plaintiff out of a large amount of money, and involve the department in an act of repudiation which, if done by anyone other than a government, would be. regarded as dishonorable, even if legally permissible. ■
What we have said leads us to this conclusion: when the contracting officer orally directed plaintiff to use the steel plant bricks, and promised it that an adjustment would be made when the work was completed and the fair amount determined, and when that direction was performed by plaintiff by doing the work and using the required material, a contract to pay plaintiff the reasonable cost of the work resulted.
We recognize that the-decision of the Supreme Court of the United States in Plumley v. United States, 226 U. S. 545, is contrary to what we have said. We see no distinction,
Plaintiff is entitled to recover $6,835.61.
It is so ordered.
See Douglas Aircraft Company, Inc., v. United States, 95 C. Cls. 140.
Dissenting Opinion
dissenting:
I cannot agree with the majority opinion.
Article 3 of the contract provides for orders of the contracting oflicer involving changes to be in writing and when the order for a change is over $500.00 the written approval of the head of the department shall be necessary. Article 5 of the contract provides that no charge for any extra work or material will be allowed unless the same had been ordered in writing by the contracting officer and the price stated in the order.
The substitution of firebrick for common brick was a change from one thing to the other, and I do not see how it can be said not to be a change. However, it required more of mortar to lay firebrick than common brick, and in that respect the change did involve an “extra.”
But the “extra” clause of the standard contract is not exclusive; it does not have the effect of converting a change into an extra. If the thing done is a change, it is subject to the provisions covering changes.
The situation is made clearer perhaps by supposing the contract to have required the use of firebrick, for which thereafter common brick was substituted. Common brick requiring less work and material than firebrick, there would then admittedly be no “extra.” The change from firebrick to common brick would have to be considered just that — a change. Being a change it would be subject to all the provisions in the contract relating to changes. As far as any practical concept of “change” is concerned, there is no difference between the passage from common brick to firebrick, and the passage from firebrick to common brick.
I can find no case in this court or the Supreme Court which gives even a semblance of sanction to the interpretation of Articles 3 and 5 of the contract which would justify their total avoidance.
Bemedy is with the Congress and not the court.
I am of the opinion that the provisions of Articles 3 and 5 of the contract are equally binding on both parties, and plaintiff is not entitled to recover. Ferris v. United States, 28 C. Cls. 332; Hawkins v. United States, 96 U. S. 689, 697; McLaughlin v. United States, 36 C. Cls. 138; Plumley v. United States, 226 U. S. 545, 547; United States v. John McShain, Inc., 308 U. S. 520, 521; Dravo Corporation v. United States, 94 C. Cls. 270, 280; Reediger, Inc. v. United States, 94 C. Cls. 120, and Callahan-Walker v. United States, decided by the Supreme Court November 9, 1942, 317 U. S. 56.
Concurrence Opinion
concurring:
I concur in the result, but on the ground that the defendant, in refusing to furnish and permit plaintiff to use the brick which it had agreed in writing to furnish, breached the contract as written and became liable for damages and excess costs directly flowing from such breach. I do not think either Article 3 or Article 5 is involved. If the point were reached where either of these articles could be invoked I think the Plwmley Gase, sufra, would govern. However, in view of the outright breach of the contract by the defendant I do not believe that point has been reached.