161 Iowa 706 | Iowa | 1913
On November 19, 1908, Phillips & Yolquardsen entered into a written contract with the Davenport Hospital, a corporation, for the construction of a building to be used as a hospital. The price with extras amounted to $13,342.90, of which all but $3,120.80 was paid. Claim for a mechanic’s lien was filed, and suit to foreclose the same begun by Yolquardsen, to whom Phillips had assigned any interest he had in the claim. By way of counterclaim defendant demanded $1,680 as liquidated damages for delay in eompleteing the building, and $400 as damages because of defective cement work. Other items, not having been allowed, need not be mentioned.
*708 The specifications call for the topping of the floors and the base to be all of one job, so there would not be any connecting cracks. That could not be done because you could not keep the tile in line in order to get your cement base on, and it took too much time to 'set the tile and the concrete. The concrete for the Whole building is poured in one day. It is supposed to be poured in one operation. There were innumerable partitions throughout the building, and it was impossible to plaster up against there. The specifications provided for a construction that was impossible. I informed the architect. , . . I made the suggestion of putting on the cement topping at the time the floors were poured, and leave a space for the partitions to be put in afterwards, and set the base in and told him that would be the way to get a good job, and Mr. McLane objected to it, but said the proposition had considerable merit, but ordered us to go ahead and put it in the other way. ... I discovered that it was impossible to fill the contract we took from Volquardsen. My own firm took a contract that it was impracticable to fulfill— impossible. An experiment was made to discover what could be done to make the stuff bind after they objected to putting it on as I wanted to. I wanted to put the topping on when I poured, and leave a space for the tile partition and the cove. The architect objected to doing that. "We eventually put on a top coat.
The architect rejected the proposition of the engineer, and against his protest directed that, after the concrete had dried, the topping be poured on. It did not attach to , the concrete below, and, as a consequence, when dry, cracked. In that condition it was $400 less in value than had the work been performed according to the specifications. The architect- testified that the method exacted by the specifications'was difficult, but not impossible.
And the difficulties of the construction-were very greatly increased on account.-of the weather;conditions, because work done .in the winter must be done quickly, and with these partitions résting on- the floor it would take four or five days to put in a floor when otherwise it could be done in one day. So that the question of how to construct a floor was very*709 thoroughly discussed by Mr. Graham and myself. The question of putting in the floor first naturally brought up the question of topping; the question of topping could not be put in the same time unless the partitions were set. We discussed several methods by which the bases could be constructed, but all seemed impracticable for winter work, but it was understood the work was to be carried on during these cold winter months. , . . The difficulties of the construction were thoroughly gone into and it was mutually agreed— I recognized the difficulties as he presented them, and it was mutually agreed that under the circumstances it might be better to proceed in another manner. . . . It is the best practice to put it on at the same time. Good engineers do it in eases where it is necessary. I have seen jobs of that kind. It wasn’t put on out here the way they agreed to put it on.
.The other two witnesses on this subject, Volquardsen and Major, did not disclose knowledge on this issue entitling their opinions as to whether the method prescribed was possible to any considerable weight. The contractor as well as the subcontractor undertook to put the topping on in the manner specified, and we are not satisfied from the evidence that this was impossible. .Doubtless it would have been difficult, especially in the winter season, but this furnished no excuse for. noneompliance with what had been agreed upon, nor did the oral assent of the architect justify performing the work in a different manner.
Modified and Affirmed.