OPINION
Appellant RPC Properties, Inc. (RPC) brought a motion seeking enforcement of a settlement agreement with VoieeStream Minneapolis, Inc., d/b/a T-Mobile (T-Mobile). Although the district court granted RPC’s request for enforcement and for attorney fees related tо the motion, it remained silent as to RPC’s request for damages allegedly arising out of T-Mobile’s delay in performing under the settlement agreement. RPC appealed, asking for an explicit ruling on damages, and the court of appeals concluded that silence was equivalent to a denial of the request.
VoiceStream, Minneapolis, Inc. v. RPC Props., Inc.,
In November 2000, appellant RPC and respondent T-Mobile contracted to allow T-Mobile to place its transmission equipment on the roof of a building owned by RPC. In 2004 RPC demanded that T-Mobile remove its equipment, and in response T-Mobile filed a complaint in which it claimed that RPC had breached the parties’ lease contract. T-Mobile asked for a declaratory judgment determining the parties’ rights аnd interests under the contract and requested injunctive relief to prevent RPC from terminating the lease or removing T-Mobile’s equipment. In October 2004, the district court granted T-Mobile’s motion for a temporary injunction prohibiting RPC from evicting T-Mobile and removing its proрerty.
In April 2005, the parties entered into a settlement agreement that required T-Mobile to pay RPC a sum of money, to remove and relocate its equipment on RPC’s roof, to coordinate with RPC for selection of a roofing contractor to supеrvise this work, and to pay the costs related to the supervision. After the performance and repairs required under the agreement, the parties were “to enter into a Release that will release T-Mobile of any claim for damage to the entire roof of the Building up to and including the date of the Release.” The parties were to execute a “Stipulation of Dismissal with Prejudice” at the same time. The agreement did not specify a date for completion of performance.
As of early September 2005, T-Mobile had not yet performed this work, and RPC brought a motion to enforce the settlement agreement. RPC requested three forms of relief: (1) an order that T-Mobile remove and relocate its equipment within five days; (2) “monetary damаges, to be established in a subsequent evidentiary hearing,” for the breach of the settlement agreement; and (3) other relief including attorney, fees and costs.
A hearing on the motion was held on September 22, 2005. By that time, T-
In its September 29, 2005, order, the district court found that the parties intended that performance be completed within a reasonable time and that a five-month delay in рerformance under the settlement agreement was not reasonable. The motion to enforce the settlement was granted, as was the request for attorney fees and costs of bringing the motion. The order did not mention the request for damages. The court asked RPC to submit an affidavit setting forth the attorney fees and costs for the motion. RPC submitted affidavits relating to attorney fees and costs as well as to damages, to which T-Mobile objected by letter to the district court. RPC submitted another affidavit asking the court tо decide whether a hearing to determine damages would be held. T-Mobile objected by affidavit. RPC renewed by affidavit its request that the court “clarify its position as to whether [RPC] has the right to present evidence as to the damages caused by the delay on the part of T-Mobile.” T-Mobile again objected by affidavit.
On December 14, 2005, the district court issued an order awarding RPC attorney fees and costs in the amount of $2,550 “for work regarding breach of settlement agreement in this case,” but again did not address damages. On appeal by RPC, the court of appeals determined that failure to rule on the request for damages was equivalent to a denial of the request.
VoiceStream,
We are asked to decide whether a district court must explicitly grant or deny a claim for damagеs arising out of a breach of settlement agreement. T-Mobile argues that the record clearly shows the district court considered RPC’s request and implicitly denied it by not granting it. RPC concedes that the Minnesota Rules of Civil Procedure do not specifically address the issue in this case, but contends that it is a fair request to ask a court to make a decision regarding the requested relief. This case thus presents a purely legal question, which we review de novo.
See Modrow v. JP Foodservice, Inc.,
RPC proceeded by motion in the original lawsuit to enforce the settlement agreement and did not elect to file a separate action for breach of contract. A district court is not required to make written or recorded oral findings of fact and conclusions of law in decisions on motions. Minn. R. Civ. P. 52.01. This dоes not, however, address the issue of whether silence can itself be a decision. The court of appeals relied on our precedent in
Hughes v. Sinclair Mktg., Inc.,
Herr and Haydock have indicated that decisions on motions “which amount to a decision on the merits” do not require findings of fact and conclusions of law unless they also resolve factual issues. 2 David F. Herr & Roger S. Haydock,
Minnesota Practice
—Civil
Rules Ann.
§ 52.4 (4th ed.2004). Discussing the fact that Rule 52(a) specifically does not require findings of fact and conclusions of law when decisions are made on motions, Wright and Miller have said that “regardless of what the rule in terms requires, whenever decision of a matter requires the court to resolve conflicting versions of the facts, findings are desirable and ought to be made.” 9A Charles Alan Wright
&
Arthur R. Miller,
Federal Practice and Procedure
§ 2575 (2d ed.1995). They cite, among others, to an Eighth Circuit case,
Ackra Direct Marketing Corp. v. Fingerhut Corp.,
in which the court indicated that it could “remand when the lack of findings by the district court would substantially hinder our review.”
As we said in Johnson, the better practice is for the district court explicitly to rule on a motion, perhaps even more so when, as here, the moving party has repeatedly requеsted an evidentiary hearing and a factual determination by the court. We believe it is important to consider the nature of the motion in this case — is there something in the nature of a motion to enforce a settlement agreement and the procedural posture of this case that should inform the rule of law we adopt?
The motion in this case sought to enforce a settlement agreement. Settlement of claims is encouraged as a matter of public policy.
E.g., Minneapolis Star & Tribune Co. v. Schumacher,
As a general rule, the enforcement of a settlement agreement requires a hearing if thе issues are sharply conflicting and there are questions of fact for the fact finder to decide. 15A C.J.S.
Compromise and Settlement
§§ 70, 74 (2002). “Trial courts have[ ] ‘the inherent power to summarily enforce a settlement agreement as a matter of law when the terms of the agreement arе clear and unambiguous.’ ”
Lewis v. Benjamin Moore & Co.,
If, instead of proceeding by motion in the original lawsuit, RPC had brought a separate action for breach of the settlement agreement, either party could have moved for summary judgment. If summary judgment had been granted for either party, the district court would not have been required to make findings of fact or conclusions of law, Minn. R. Civ. P. 52.01, but the entry of judgment would at least have been an explicit ruling on RPC’s request. If the case had not been fully disposed of by a grant of summary judgment, the district court would have had to “ascertain what material facts exist without substantial controversy and what material facts are actually and in good faith controverted” and then “make an order specifying the fаcts that appear without substantial controversy.” Minn. R. Civ. P. 56.04. Again, this would have resulted in an explicit ruling such as RPC requests. If summary judgment had been denied to either party, the case would have gone to trial, and RPC would have had the opportunity to present its evidencе. Under any scenario, the district court could not have, by its silence, granted summary judgment to either party in the breach of contract action.
Another way to enforce a settlement agreement is to move for permission to amend the pleаdings based on a breach of the settlement agreement.
See
Minn. R. Civ. P. 15.01. Leave to amend should be freely granted unless it results in prejudice to the other party.
Fabio v. Bellomo,
In sum, if RPC had either moved for permission to amend the pleadings or brought a separate breach of contract action, the district court could not have, by silence, denied RPC’s claim for damages
We believе fairness requires the court to explicitly rule under the facts of this case. In light of the important public policy of encouraging (and enforcing) settlement of claims, we hold that a district court shall treat a motion to enforce a settlement agreement as it would a motion for summary judgment, and explicitly grant or deny each claim. The district court in this case must either grant a hearing on consequential damages or explicitly deny the claim for damages and indicate that no material facts arе in controversy. We leave it to the district court to determine whether T-Mobile’s unreasonable delay in performance under the settlement agreement caused any damages.
Reversed and remanded to the district court for further proceеdings consistent with this opinion.
Notes
.
Sanvik
cites to
Alsdorf v. Svoboda,
. Wright & Miller also cite to
Holly D. v. Cal. Inst. of Tech.,
