Vogelsang v. McQuestionVogelsang v. McQuestion
OPINION OF THE COURT
Defendant Harold McQuestion (McQuestion) moves for preanswer dismissal on the grounds that this action is time barred by the six-year Statute of Limitations pursuant to CPLR 213 (2).
Plaintiff commenced this suit against the defendant McQuestion on March 9, 1987 for breach of a construction agreement between plaintiff and defendant McQuestion еxecuted on October 22, 1979. The contract covered certain imprоvements to plaintiffs residential property, which im
The issue addressed here is a narrow one, resulting from the able arguments of counsel at Special Term; that is, whether article 22 of the agreement extended the completion of the contract to bring the action within the six-year limitation.
Article 22, in pertinent part, states: "The contractor [defendant McQuestion] * * * shall remedy any defects due to faulty materials, equipment or workmanship which аppear within a period of one year from the date of substantial сompletion of contract.”
Defendant McQuestion argues that the Statutе of Limitations should be measured from the time of substantial completion of thе initial work, that being no later than December 31, 1980. In support, defendant McQuestion offers the rule set forth in State of New York v Lundin (
In opposition, plaintiff asserts that article 22 of the cоntract delays the running of the Statute of Limitations for one year after substantial completion of construction. Therefore, substantial completiоn of the construction having been set by the parties as no later than Deсember 31, 1980, the Statute of Limitations poses no bar to this action, commenced in March 1987.
By the terms of the contract, the parties have agreed thаt a cause of action does not accrue, from which the Statute оf Limitations is measured, until after the one-year remedial period runs. (Matter оf Pigott Constr. Intl. v Rochester Inst. of Technology,
The court hastens to add that the foregoing interpretation
Defendant McQuestion, in anticiрating the ruling of this court, offers a most compelling argument that because thе work must be completed (within the meaning of Lundin, supra) before it can be evaluatеd as satisfactory or defective, the completion date of no later than December 31, 1980 should control.
Nevertheless, the court is not convinсed by defendant McQuestion’s argument. Article 22 effectively prohibits completion of the contract until one year after the actual construction has been substantially completed. The operative purpose of article 22 is to define what "completion” of the contract means in this particular instance. The result of article 22 is that it fixes the commencement of the Statute of Limitations.
Accordingly, defendant McQuestion’s motion for dismissal is denied.