223 P. 1072 | Idaho | 1923
Lead Opinion
— On January 2, 1903, the state of Idaho and the Twin Falls Land & Water Company entered into a contract by which the latter was to construct an irrigation project for the irrigation of certain lands under the Carey Act (U. S. Comp. Stats., sec. 4685) by means of 3,400 second-feet of the waters of Snake River appropriated for that purpose. The lands so proposed to be irrigated were partly on the north side and partly on the south side of Snake River. Thereafter a corporation known as the North Side Twin Falls Land & Water Co. (hereinafter
“4. It is further understood and agreed that if more than 32,000 acres are sold under what is generally known as the First Segregation, being the lands included in Segrega*77 tion List No. 6, in Lincoln County, together with other lands adjacent thereto, then storage shall be provided for such additional lands sold in excess of 32,000' acres to the same extent measured at the Milner Dam as is provided for lands on what is commonly known as the Second Segregation in Lincoln County, State of Idaho, being the lands included in Segregation List No. 13, but in case 32,000 acres are not sold on said First Segregation, then any water represented by the difference between the amount sold and the total acreage of 32,000 acres may be used on other lands under the canal system.
“8. It is anticipated that the said party of the second part will procure more water to be impounded at Jackson Lake than -is called for by the terms of this agreement and any additional water so impounded may be used for the irrigation of other lands, or for other purposes.”
More than 32,000 acres has not been sold under the first segregation. February 25, 1913, the United States and the Kuhn Irrigation and Canal Co. entered into a contract by which the latter was to pay the cost of increasing the height of the Jackson Lake Dam 17 feet, and was to receive 10,000 acre-feet below elevation “6572,” and the additional amount of water which could be delivered from the reservoir on account of the said increase in the height of the dam. The 10,000 acre-feet was acquired in exchange for a right owned by the Kuhn Company, known as the Perrine right, is used on the first segregation, and is not in question here, the controversy being solely as to the additional amount. The company was to pay the United States its proportionate share of the cost and expense of operating and maintaining the reservoir and delivering water therefrom. This contract was performed. On March 12, 1918', the Kuhn Irrigation and Canal Co. assigned and transferred to the construction company all its rights and interests in the said contract with the government. On March 12, 1918, the construction company assigned to the respondent North Side Canal Company (hereinafter designated as the operating company) all its rights and interests in said
The lower court held that the only contract holders under the first segregation entitled to receive Jackson Lake storage water are those who entered into the supplementary contract, and appellant Vinyard not being one of these, decided against him. The appeal is from the judgment. The many assignments of error may all be summed up in the one point that the court erred in finding and in holding that appellant Vinyard and others in his class have not the right to demand said storage water.
The main contentions of appellant Vinyard are as follows: (1) The furnishing of storage water to him in 1916, 1917 and 1918 placed an interpretation upon the contract in favor of appellant which should be recognized by the court; (2) that said acts constituted a dedication under the constitution; (3) that he has a right to said storage water under the various contracts pertaining to his water right. Respondents contend that the various contracts pertaining to appellant’s water right give him a right only to the natural flow of Snake River, and no right to any of the storage water, that, after delivering 10,000 acre-feet to the lands under the first segregation, 170,000 acre-feet to the lands under the second and third segregations, and a sufficient amount of water to the contract holders under the first segregation, who entered into the supplementary agreement, the operating company has a right to furnish the excess of the storage water, if any, to other lands within the project under new contracts to be let by the construction company.
We will consider appellants’ main contentions in the above order. The rule that a court will accept the inter
Const., XY, 4, reads as follows: “Whenever any waters have been, or shall be, appropriated or used for agricultural purposes, under a sale, rental, or distribution thereof, such sale, rental or distribution shall be deemed an exclusive dedication to such use; and whenever such waters so dedicated shall have once been sold, rented or distributed to any person who has settled upon or improved land for agricultural purposes with the view of receiving the benefit of such water under such dedication, such person, his heirs, executors, administrators, successors, or assigns, shall not thereafter, without his consent, be deprived of the annual use of the same, when needed for domestic purposes, or to irrigate the land so settled upon or improved, upon payment therefor, and compliance with such equitable terms and conditions as to the quantity used and times of use, as may be prescribed by law.”
The gratuitous distribution of water does not constitute a dedication under this section. The word “distributed” must be read in the light of the words “sold” and “rented” which precede it, and the words “upon payment therefor” which follow.
We come now to a consideration of the contracts. Under the contract between the state and the construction company, and the one between the construction company and appellant, the construction company was bound to furnish appellant 1/80 of a second-foot of water for each acre of land. This court has held that under a Carey Act contract the interest of the settler is a proportionate interest in the entire canal system and the water appropriation. (State v. Twin Falls Canal Co., 21 Ida. 410, at 439, 121 Pac. 1039,
Eespondents contend that paragraph 4 of the contract of March 27, 1913, between the state and the construction company prevents the use of any of the storage water in question on lands under the first segregation. We do not so construe it. It is apparent that the parties to that contract contemplated that the water right dependent on the natural flow of the river would be sufficient to satisfy the rights of the contract holders under the first segregation, if it was limited to 32,000' acres. The contract provides that a storage right shall be provided for lands sold in excess of 32,000 acres. It does not expressly provide that storage water shall never be provided for the first segregation if less than 32,000 acres are sold, and this is not a reasonable or just implication from the language used. We cannot construe this contract to prevent the application of excess storage water to lands under the first segregation in order to satisfy the rights of the contract holders, where no other prior rights have attached.
Eespondents contend that the court cannot grant the relief prayed for by appellant because to do so would adversely affect the rights of other parties who are not before the court in this action. Eespondents claim that the record in this case shows there are two classes of indispensable parties who have not been joined in this action, — first,
We come now to a question which seems to us to be raised by the record although it has not been referred to by counsel for either side. The contract between the state and the construction company, and the one between the construction company and the appellant Yinyard and the other contract holders provide that, wMle the construction company retains control of the operating company and system, it shall charge the purchasers of water rights not to exceed the sum of thirty-five cents per acre for each acre owned, for maintaining, operating, managing and keeping in repair the system, and that, if that sum is insufficient, the construction company will furnish the additional funds necessary to supply the deficiency. In the supplementary contracts which it made with many of the water users on the first segregation the construction company got them to waive this provision of the original contract, and to agree to pay it as maintenance their pro rata share of the actual cost
Rehearing
ON REHEARING.
— In the original opinion, we held that the judgment should be affirmed because appellants did not offer, in their complaint, to pay maintenance based on the actual cost of operation. In a petition for rehearing, they claim that the court has misconstrued the record in this regard. After re-examining the record, we are not convinced that we have misconstrued it. However, on re-argument, counsel for appellants stated, and counsel for respondents admitted, that appellants have been for some years paying the same maintenance as the contract holders who have been receiving the Jackson Lake storage water, i. e., maintenance based on the actual cost of operation. Regardless of the condition of the record, in the face of this admission we withdraw the last part of the original opinion touching appellants’ duty to offer to pay increased maintenance as a condition precedent to any relief.
Counsel for respondents, in a petition for rehearing, suggest that the court erred in saying:
“The 10,000 acre-feet was acquired in exchange for a right owned by the Kuhn'Company, known as the Perrine right, is used on the first segregation, and is not in question here, the controversy being solely as to the additional amount. ’ ’
This question not being in issue, and the facts not being exactly clear, we conclude that the original opinion should be modified by striking from the sentence above quoted the clause “is used on the first segregation.”
Respondents also contend that this court erred in concluding, first, that the second and third segregations are only entitled to 170,000 acre-feet of the Jackson Lake stor
“The original appropriation made for the first segregation turned out to be insufficient, and if the company after-wards made another appropriation, and acquired a further water right, to which no other contract holders have a prior claim, it would follow that the contract holders under the first segregation could force the construction company to apply this new water right for the purpose of supplementing their original water right, to the extent necessary in order to bring about a compliance with their contracts.”
The greater part of the argument and brief of respondents on the original hearing was taken up with this theory. The further point was suggested, though not emphasized, that the
We were not unmindful of what we said in Sanderson v. Salmon River Canal Co., 34 Ida. 145, 199 Pac. 999:
“Mandamus is not a proper remedy to decide conflicting interests. If third parties have rights or interests adverse to those of plaintiff, mandamus is not the proper remedy.”
This applies with almost equal force to an action like the present which, though not a mandamms proceeding in form, yet seeks the same object, to wit: the delivery of water by an irrigation company. Since the court found that the prior right of the second and third segregations was to 170,000- acre-feet, and it was admitted that there were 245,000 acre-feet in the Jackson Lake reservoir, we assumed that the rights of the second and third segregations could no'; be adversely affected. This was, perhaps, because this aspect of the matter was not emphasized. It is strongly emphasized in the petition for rehearing.
■Bespondents point out that, under the contract by which the state permitted the construction company to substitute the Jackson Lake storage water for water originally planned to be stored m Wilson Lake and Jerome reservoirs, it is provided that an amount of water in excess of 170,000 acre-feet shall be delivered at the intake of Wilson Lake and Jerome reservoirs. (Bespondents’ Exhibit “C.”) It is apparent from the record and is a matter of common knowledge that there must be a considerable loss of water in transit. The contracts between the construction company and the water users on the second and third segregations provide that water shall be measured to them at the place of diversion from the main laterals of the irrigation system. (Bespondents’ Exhibits “A,” page 15, and “B,” page 8.) In deciding how much water is necessary to insure them their contract amounts, it is necessary to make allowance for some loss in transit between the outlet of Wilson Lake and Jerome reservoirs and the place of delivery. If the
In view of the provisions in the several contracts, the finding's, the judgment and the argument, we assumed, on the original hearing, that 170,000 acre-feet had been dedicated to the second and third segregations and constituted the extent of their priority. In view of the turn the ease took on rehearing, we conclude that there may be some question as to the correctness of this assumption. The court’s findings support it, but it must be remembered that they are not binding on the contract holders under the second and third segregations who were not parties. The purpose of the contract by which the state permitted the construction company to substitute the Jackson Lake project for the original project was to fulfill the provisions of the original contracts. It is provided that the company shall procure in excess of 170,000 acre-feet. The water users on the second segregation are entitled, under their contract, to one-eightieth of a cubic foot per second for each acre, and those on the third segregation are entitled to one one-hundredth of a cubic foot for each acre. (Respondents’ Exhibit “A,” page 15.)
Questions arise as to whether the priority of the second and third segregations is confined to 170,000 acre-feet, or whether they have a prior right to whatever amount of Jackson Lake storage water may be necessary to give them the amount required by their contracts, and, if the latter, what that necessary amount is. These questions should not be decided without making them parties.
It would be useless and idle to enter a judgment to the effect that appellants are entitled to the use of surplus water after the rights of the second and third segregations are satisfied unless it is determined that there is such a
We conclude that the contract holders on the second and third segregations are interested in a determination of these questions and should be made parties.
The judgment is reversed and the cause remanded, with directions to permit appellants to join as parties defendant, within such reasonable time as the trial court may allow, the contract holders under the second and third segregations, and for further proceedings in accordance with the views herein expressed. If appellants do not join such additional parties within said time, it is ordered that the action be dismissed. No costs are awarded on this appeal. The original opinion is modified to the extent herein indicated; in all other respects it stands.
Rehearing
ON PETITION FOR MODIFICATION.
— We adhere to the views expressed in the original opinion as modified by the opinion on rehearing, except in that portion of the opinion on rehearing which holds that contract holders on the second and third segrega-tions are necessary parties to a complete determination of the issues presented in this cause and that such contract holders should be made parties. It .is our understanding that appellant Yinyard expressly disclaims any right to
It seems to us, therefore, that the question for determination by the trial court is quantity, if any, of such surplus water in Jackson Lake reservoir over and above that required to fill contracts outstanding conceded by appellant Yinyard and water users of his class or found by the court to be prior to their rights.
The contract holders are not necessary parties to a determination of this question.
Concurrence Opinion
— I concur in the conclusion reached by Mr. Justice Wm. E. Lee. However, my concurrence to the effect that no order should be made requiring the contract holders on the second and third segregations to be brought into the action as parties defendant is upon the ground that in the present state of the pleadings and the record, the question of whether they are necessary parties is not before us.