181 Ky. 651 | Ky. Ct. App. | 1918
Opinion of the Court by
Affirming.
On the third day of January, 1916, the appellant instituted this action against appellee for the contract prico of the bridge, with interest at 6% per annum, from the completion of the bridge, and alleged, that, it had furnished the materials and erected the bridge, under and id
At the conclusion of the evidence; each party, moved the court, for a directed verdict in its favor, but, these motions were overruled. The appellant then offered several instructions and moved the court to give them to the jury, but all were overruled, and the court then gave five instructions to the jury, all of which were objected to by both appellant and appellee.
The first instruction, in substance, advised the jury, that the appellant had contracted to furnish all the ma
The second instruction directed, that although the jury did not believe that the bridge was constructed as! set out in instruction No. 1,'yet, if it believed from the evidence that appellee accepted the bridge, to find for appellant the contract price for the bridge, as set out in instruction No. 1.
The third instruction directed, that if the jury, did not believe, from the evidence, that the appellant had constructed the bridge as set out in instruction No. 1, or that appellee accepted it as set out in instruction No. 2,' to find for the appellee.
The fourth instruction advised the jury, under what' circumstances it should find for appellee upon his counterclaim, and the fifth instruction was the converse of the fourth, but, as the verdict of the jury denied to appellee any recovery upon his counterclaim, it is unnecessary to any further consider the fourth and fifth instructions.'
The jury found for appellee, specifically stating in its verdict, that it did so, in accordance with the third instruction. The appellant’s motion for a new trial was overruled, and it has appealed, and its complaint of the instructions will be first considered.
The objection urged to the first instruction, and, if the instruction was applicable to the facts of the case, it is the only objection, which could be urged, is, that the court did not construe the contract and tell the jury, what the contract was, fully, but, inasmuch as it advised the jury, that the contract required the bridge to be built, “in accordance with the plans and specifications in evidence,” and if it was built substantially “in accordance'
The plans and specifications for the building of the bridge, were by reference made a part of the contract, and there is no dispute between the parties as to the identity of the plans and specifications .referred to, with the ones in evidence. There is no claim by either party that any portion of the contract was left out of the writings and plans and specifications by fraud or mistake, or that anything found its way into the written memorial of the contract, by either fraud or mistake. The plans and specifications were a part of the contract. Culbertson v. Ashland Cement and Construction Co., 144 Ky. 614; 9 C. J. 694, 698. The contention of appellee was, that the bridge, as erected, did not conform, to the requirements of the contract, in certain particulars, only, and, except for the reasons hereinafter stated, the court should have instructed the jury, as to the requirements' of the contract with .reference to these particulars complained of, and then submitted to the jury, whether the bridge as' constructed was in accordance with, or substantially in accordance with the terms of the contract, as construed by the court, as to the particulars, in controversy. Culbertson v. Ashland Cement, etc., Co., supra. The instruction, however, as given,-did not prejudice the substantial rights of the appellant. The general rule which defines the right of a builder to compensation, for a structure, which he erects under a contract, is, that, if he constructs and completes the structure, in accordance with the terms of his contract, the owner must then accept same and pay to the builder the price agreed upon in the contract. If, however, the-builder, in good faith, endeavors to build the structure, according to the stipulations of the contract, but, fails to build it in literal compliance with the contract, but substantially does so, he will be entitled to recover the contract price, less such damages as the owner of the property may be entitled to, for a failure of the literal compliance with the contract, under the facts of the case. Taulbee v. Moore, 106 Ky. 749; Kiel v. Kline, 15 R. 158; Short v. Moore, 19 R. 1225; Culbertson v. Ash-
The third instruction is complained of upon the ground, that appellee had no right to refuse to accept the bridge. The court can not make a contract for the parties, and it is not authorized to compel one to accept and pay for something, which he has not contracted for. If the bridge had been constructed according to the contract, the appellee would have no choice, except to accept it, and whether he accepted it or not, he would be required to pay for it, the amount, he promised. If it had been constructed, not in literal compliance with the contract, but, substantially so, the law would consider, that appellee had received in fact, what he had contracted for, and would require him to pay the contract price, less the damages for failure of a literal compliance. Where the contractor in the erection of a structure does not build it as the contract requires, or substantially so, the one for whom it is built has a .right to refuse to accept it and to refuse to pay for it, and the contractor, having failed to furnish the article contracted for can not recover the price. Escott v. White, 10 Bush 169; 9 C. J., 737. The contract, in instant case, was an entire one and indivisible, and provided for the payment of the price agreed upon for the bridge, after it was completed and accepted. The character of the bridge was such, as there might be a total rescission of the contract, and the builder could remove his materials, by restoring the parties to the
The appellee could have, of course, accepted the bridge, as having been completed according to the contract, and this was alleged by appellant and denied by appellee, and under the evidence was the only issue in the case to be submitted to the jury. This issue was submitted by the second instruction, and the third was its converse. It is insisted, that the finding- of the jury, that appellee had never accepted the bridge as having been made in accordance with the contract, was contrary to the great weight of the evidence, and in fact, that the court should' have directed a verdict for appellant. The evi-j dence shows without contradiction, that appellee pro-’ tested from the beginning and before the construction of the bridge was ended, that it was not being built accord-1 ing to the contract, and declared that he would never' accept nor pay for it. The agent of appellant who made the contract, and who undertook to collect the price from1 appellee, was proven to have admitted that the bridge was not such as appellee had contracted for. It was also/ proven that he had occasionally passed over the bridge1 and had offered certain lots for sale, .representing, that he would have a steel footbridge built over the ravine, and that he had collected the price of a lot sold to ond individual, after the bridge had been erected. It however, does not clearly appear, what the nature of the arrangement between appellee and the purchaser- of the lot was, in reference to the bridge. The lot purchaser is. not now complaining. The appellee testified that appellant had promised, after he had refused to accept the bridge/ that it would make it conform to the contract. It seems,1 that after appellee’s wooden bridge, over the ravine, was torn down by appellant, that he had no practical way of
Several other alleged errors are complained of as being grounds for reversal, but they are not of such character as to have influenced the result of the trial, and will not be adverted to.
The judgment is affirmed.