137 Wash. App. 751 | Wash. Ct. App. | 2007
FACTS
¶2 The Villas at Harbour Pointe is a 96-unit condominium development located in Mukilteo. Possession View,
¶3 T&G Construction, Inc. (T&G), was the siding subcontractor for the project. T&G’s contract required it to indemnify CAI and obtain a general liability and commercial excess liability policy naming CAI as an additional insured. As agreed, T&G obtained a policy from Mutual of Enumclaw (MOE).
¶4 Soon after construction was complete, homeowners began reporting water intrusion around the windows and the sliding glass doors. CAI concluded the water leaks were caused by defective siding installation and notified T&G. In early 2001, T&G returned to perform repairs. But after T&G’s repairs, homeowners continued to report problems with water intrusion. The association hired an independent construction expert to investigate the water intrusion. The expert’s report identified a number of construction and design defects, including improper installation of water resistive barriers and window flashing.
¶5 On June 11, 2002, the association sued the condominium developer, PVLLC, for $7.3 million in damages, alleging breach of contract and construction and design defects in violation of the Washington Condominium Act (WCA)
¶7 During discovery, MOE learned that T&G was administratively dissolved on October 23, 2000. T&G then filed a motion for summary judgment, arguing that the statutory two-year time limitation to file a claim against a dissolved corporation barred CAI’s claims against it.
¶8 The association filed a motion for summary judgment, claiming that the alleged construction and design work violated the Uniform Building Code (UBC) and the WCA. The court ruled that a number of the alleged defects violated the UBC and the WCA. As to T&G’s work, the court ruled that the improperly installed weather barriers and flashing violated the UBC and the WCA.
¶9 At mediation, the association settled with all parties except T&G for approximately $5.7 million.
¶11 The day before the hearing, MOE objected to the court’s authority to conduct a reasonableness hearing in a breach of contract condominium construction defect case. Over MOE’s objection, the court proceeded with the hearing. A number of witnesses testified on behalf of the association, T&G, and MOE. The court also reviewed extensive documentary evidence, including the experts’ scope and estimated cost of repair and a number of photographs depicting the damage.
f 12 In a memorandum decision issued on March 8, 2005, the court ruled that it had the authority to conduct a reasonableness hearing and the $3.3 million settlement between the Association and T&G was reasonable. On March 17, the court entered the $3.3 million stipulated judgment against T&G.
¶13 On April 12, MOE filed a motion asking the court to withdraw or correct its memorandum decision. Based on a recent decision of this court, MOE argued that the claims against T&G were barred by the two-year time limitation to file a claim against a dissolved corporation.
Authority To Conduct Reasonableness Hearing
f 14 MOE contends that under RCW 4.22.060, the trial court had no authority to conduct a reasonableness hearing in a breach of contract condominium construction defect case.
¶15 We review questions of law de novo. Dep’t of Ecology v. Campbell & Gwinn, LLC, 146 Wn.2d 1, 9, 43 P.3d 4 (2002); Stuckey v. Dep’t of Labor & Indus., 129 Wn.2d 289, 295, 916 P.2d 399 (1996). Whether a statute applies is also a question of law. Lobdell v. Sugar ‘N Spice, Inc., 33 Wn. App. 881, 887, 658 P.2d 1267 (1983).
¶16 As part of the 1981 tort reform act, Laws of 1981, ch. 27 (codified in chapters 7.72 and 4.22 RCW), RCW 4.22.060 creates a right of contribution between joint tortfeasors and procedures to enforce that right. Glover v. Tacoma Gen. Hosp., 98 Wn.2d 708, 717, 658 P.2d 1230 (1983), overruled on other grounds by Crown Controls, Inc. v. Smiley, 110 Wn.2d 695, 756 P.2d 717 (1988). Under RCW 4.22.060(1), the court’s determination that a settlement amount is reasonable establishes the offset for a nonsettling joint tortfeasor. RCW 4.22.060(2) requires the court to determine whether the settlement amount is reasonable and, if not, to set forth the amount that is reasonable.
¶17 In Glover, the Washington Supreme Court adopted a number of factors the court should consider in determining the reasonableness of a settlement under RCW 4.22.060. But according to the court, no one factor controls
¶18 When an insurer refuses to settle a claim, the insured, without the consent of the insurer, can negotiate a settlement with the claimant. Red Oaks Condo. Owners Ass’n v. Sundquist Holdings, Inc., 128 Wn. App. 317, 322, 116 P.3d 404 (2005). The insurer may be liable for the settlement amount to the extent reasonable. Red Oaks, 128 Wn. App. at 322. An insured’s assignment of its bad faith claims also allows the claimant to seek more than the policy limits. Besel v. Viking Ins. Co. of Wis., 146 Wn.2d 730, 49 P.3d 887 (2002).
¶19 In Chaussee v. Maryland Casualty Co., 60 Wn. App. 504, 803 P.2d 1339 (1991), this court adopted the Glover factors to evaluate the reasonableness of a settlement between an insured and the claimant for a stipulated judgment and an assignment of coverage and bad faith rights in exchange for a covenant not to execute and dismissal. Because of similar concerns regarding the impact of a settlement on other parties and the risk of fraud or collusion, we concluded the Glover factors should apply to a covenant judgment settlement agreement between an insured and the claimant. Chaussee, 60 Wn. App. at 512.
¶20 In Besel, the Washington Supreme Court approved of the procedure adopted in Chaussee and of conducting a reasonableness determination in the underlying action prior to a coverage or a bad faith action. The court also held that the settlement amount the court determines is reasonable establishes the presumptive measure of harm in a later bad faith action against the insurer. Besel, 146 Wn.2d at 738. According to the court, a reasonableness determination under the Chaussee criteria protects “insurers from excessive judgments especially where .. . the insurer has notice of the reasonableness hearing and has an opportunity to argue against the settlement’s reasonableness.” Besel, 146 Wn.2d at 739.
¶22 As in Chaussee, Besel, and Red Oaks, the association’s settlement agreement with T&G included a stipulated judgment in favor of the association with a covenant not to execute and an assignment of T&G’s coverage and bad faith claims against MOE. Based on Chaussee, Besel, and Red Oaks, we conclude the trial court has the authority in a contract condominium defect case to conduct a reasonableness hearing on a covenant judgment settlement agreement between an insured and the claimant.
¶23 MOE also argues the trial court did not have jurisdiction to conduct a reasonableness hearing because the association and T&G entered into the settlement agreement prior to the hearing. Specifically, MOE argues the court did not have jurisdiction because there was no case in controversy and T&G did not comply with the requirements of RCW 4.22.060(1).
¶24 For a court to exercise judicial power, there must be a justiciable case or controversy. U.S. Const, art. III, § 2; To-Ro Trade Shows v. Collins, 144 Wn.2d 403, 411, 27 P.3d 1149 (2001) (before the jurisdiction of a court may be invoked, the virtually universal rule is that there must be a justiciable controversy).
¶25 Relying on the requirements of RCW 4.22.060(1), MOE also argues that the court did not have jurisdiction because MOE did not receive notice before T&G and the association entered into the settlement agreement. RCW 4.22.060(1) provides that:
A party prior to entering into a release, covenant not to sue, covenant not to enforce judgment, or similar agreement with a claimant shall give five days’ written notice of such intent to all other parties and the court.
¶26 Under the plain terms of the statute, the claimant must provide five days notice of the intent to settle to all other parties. But here, there is no dispute that MOE was not a party and, therefore, was not entitled to notice under RCW 4.22.060(1). Nevertheless, even assuming MOE was entitled to notice as a party, MOE cannot establish a due process violation or prejudice. There is no dispute that MOE received notice of the settlement agreement before the reasonableness hearing or that MOE intervened and participated in the hearing. Red Oaks, 128 Wn. App. at 324.
¶27 The remainder of this opinion has no precedential value. Therefore, it will not be published but has been filed for public record. See, RCW 2.06.040; CAR 14.
Appelwick, C.J., and Cox, J., concur.
Reconsideration granted and opinion modified May 3, 2007.
The policy was in effect from October 26, 1997 to October 26, 2000.
Ch. 64.34 RCW.
Ch. 19.86 RCW.
T&G filed a fifth-party claim against its subcontractors.
In the alternative, T&G argued CAI’s contract claims were barred by the three-year statute of limitations.
The court also ruled that as a matter of law, the six-year statute of limitations applied.
The association also did not settle with the framing contractor, Burley Bear Homes, Inc.
On September 22, 2004, MOE filed a declaratory judgment action on coverage and its obligation to indemnify T&G under the policy.
Ballard Square Condo. Owners Ass’n v. Dynasty Constr. Co., 126 Wn. App. 285, 108 P.3d 818 (2005), aff’d on other grounds, 158 Wn.2d 603, 146 P.3d 914 (2006).
Although the court denied MOE’s motion to withdraw or correct the memorandum decision, the court concluded $3 million, instead of $3.3 million, was reasonable “based on risks Construction Associates/Association would have incurred at trial.” The parties do not challenge the court’s $3 million determination.
RCW4.22.060(2) provides:
A release, covenant not to sue, covenant not to enforce judgment, or similar agreement entered into by a claimant and a person liable discharges that person from all liability for contribution, but it does not discharge any other persons liable upon the same claim unless it so provides. However, the claim of the releasing person against other persons is reduced by the amount paid pursuant to the agreement unless the amount paid was unreasonable at the time of the agreement in which case the claim shall be reduced by an amount determined by the court to be reasonable.
The association contends MOE waived the right to argue jurisdiction based on its participation in the reasonableness hearing. But the right to challenge
The cases MOE relies on to argue that the court did not have jurisdiction are either inapposite or distinguishable. In National School Studios, Inc. v. Superior School Photo Service, Inc., 40 Wn.2d 263, 242 P.2d 756 (1952), the court declined to accept review because the time limitation in a covenant not to compete had expired. In Rosling v. Seattle Building & Construction Trades Council, 62 Wn.2d 905, 907, 385 P.2d 29 (1963), the court declined to review a case concerning picketing at a construction site because construction was complete, making the question “purely academic.” In Tosco Corp. v. Hodel, 804 F.2d 590 (10th Cir. 1986), while the appeal was pending, the parties settled. When third parties moved to intervene, the court ruled that it lacked jurisdiction because there was no case or controversy.