152 F. 393 | 7th Cir. | 1907
after stating the facts, deliyered the opinion of the court.
The contentions of error upon this writ, except one assignment for the reception in evidence of certain letters, hinge upon the assumed meaning or inoperativeness of a clause of the contract in suit, which reads:
“The acceptance of this machinery, when delivered, is understood to constitute a waiver of all claims for damages by reason of any delay.”
As the contract terms were otherwise undisputed in their import— that the plaintiff below was to furnish the machinery specified for equipment of the defendant’s manufacturing plant and complete delivery on or before July 1st, for the prices stated — and performance on the part of the plaintiff is unquestionable, aside from delay in delivery, solution of the question raised is within narrow compass. In so far as the testimony is preserved, the record is conclusive that the machinery was made and delivered in conformity to the contract as to kind and quality,; that all was received and installed by the purchaser and retained,in its plant; that the amount awarded by the verdict and judgment is the unpaid balance of the purchase price; and that the judgment cannot be disturbed, if such acceptance of the machinery operated as a waiver of delay. The circumstances or causes of such delay do not enter into the inquiry; nor are they open to consideration in the absence of much of the testimony.
The object of this waiver provision in the agreement is plain; and it is expressed in terms which are not, as we believe, open to misunderstanding. The executory contract is positive and definite to deliver the machinery for the plant on or before July 1st, “unless delayed by unavoidable accidents or labor strikes.” In the event of failure to perform, the defendant was entitled thereunder to recover damages for the breach, unaffected by the waiver clause, except upon its exercise of the option to take’the machinery notwithstanding the delay. Under the general rule, in the absence of other agreement, the purchaser may elect either to receive the goods so delayed in delivery, or to reject them, and may sue for the breach in either case, unless the goods are accepted under circumstances which amount to discharge of the con
Whatever the cause of delay in furnishing the machinery, it is undisputed that the defendant received and installed it upon arrival, and thus waived “all claims for damages by reason of any delay,” as expressly provided in the contract. The defendant’s tenders, therefore, under the pleas of set-off and recoupment, to prove damages caused by the delay, were rightly overruled, if the provision referred to was operative and bound the defendant as such waiver.
The validity of the waiver clause is challenged upon various general propositions of law which do not call for discussion, as we discover no bearing of either upon these contract terms as above interpreted. The general rule is well settled and conceded that the purchaser under an executory contract of sale may elect, after default upon the part of the seller, to accept the goods notwithstanding, and waive-damages for the breach, either in express terms, or impliedly through his conduct in the acceptance; and that such waiver is binding.
Provision in advance to make the waiver certain in the event of acceptance, if delay occurs, is equally within the right of the contracting parties, and when fairly agreed upon is equally binding. While the contract remains executory, the obligations and remedies of the parties are unaffected by the proviso. The seller must perform all the terms, or answer in damages for his default; and the purchaser is required to accept the machinery only when all terms are performed on the part of the seller. All the common-law remedies for breach of the executory contract are preserved for each party; and the agreement is neither uncertain as to the time when delivery is required, nor unilateral in any executory provision. With or without this proviso, the seller may assume to deliver after the time limited by the contract,, although, under either form of contract, he cannot require the purchaser to accept it in satisfaction of the contract, nor can the purchaser
We are of opinion that this provision is not open to the objections urged, either for want of mutuality and consideration or as opposed to public policy, and that no error appears in the rulings thereupon which are complained of — in effect, that damages for the alleged delay were barred by acceptance of the machinery when delivered.
The remaining assignment of error rests upon.the introduction by the plaintiff below and reception of certain correspondence between the parties and their purported representatives, pending execution of the contract, which appears to have been offered as tending to excuse the delay in deliveries of the machinery. Under the final rulings of the trial court the issues raised as to delay in the performance were removed from consideration, and, if the admission of these letters were erroneous at any stage, which we do riot intimate, the error was not prejudicial, and the assignment thereupon is without force.
The judgment of the Circuit Court is affirmed.