207 Mass. 318 | Mass. | 1911
This case was before this court after its first trial, and was reported in 202 Mass. 247, where the principal facts are stated. It is now presented on the defendant’s exceptions, which, as he says in his brief, relate to four subjects, namely: “First, the right of the plaintiff to recover; second, the right of the defendant to a credit of $3,000, the amount of certain notes given in payment and subsequently paid; third, the right of the defendant to a credit of $1,500 for certain other notes given in payment and subsequently dishonored; fourth, the right of the defendant to a credit of $1,600 as liquidated damages for the delay from March 6, 1903, to August 13, 1903, at $10 a day.”
The right of the plaintiff to recover upon the facts found by the jury was established, upon full consideration, by our former decision, and the defendant’s requests for instructions on this part of the case were rightly refused.
The various requests upon the second and third subjects to which the defendant’s argument was addressed were rightly refused.
The evidence to which the requests related was that the architect fraudulently delivered to the owner and contractor what purported to be duplicate contracts signed by the parties, for the construction of a bath house, in which the price to be paid was stated as $33,721 in the copy delivered to the contractor, and as $23,200 in the copy delivered to the owner, and afterwards volunteered to give the contractor certain notes, signed by himself,
The fifth, eighth and ninth requests on this subject called for an erroneous statement of the law. The judge told the jury that
The next subject to which the defendant’s argument relates arises under the tenth request for a ruling, that “ the defendant is entitled to a credit of at least $1,600 for late completion.” This is founded upon a provision in the supposed contract that the plaintiff should pay $10 per day for all time after the date at which the contract was to be completed until it was in fact completed. This contract never took effect between the parties, and there was no foundation for the defendant’s claim of this credit. The real question was what was the value of the labor and materials furnished by the plaintiff at the time and place when and where they passed to the ownership of the defendant. The instruction to the jury that they should allow to the defendant $10 for each day of unreasonable delay of the plaintiff, if they found that there had been unreasonable delay and no waiver on the part of the defendant, was too favorable to him.
Exceptions overruled.