Orkin Exterminating Company and Terminix Service Company both appeal from the trial court’s order denying their motions to compel arbitration. We affirm with respect to Orkin and reverse with respect Terminix.
FACTS
This case arises from a lawsuit filed by the Church of the Holy Cross after it discovered termite damage within the church building. 1 In 1975, the church contracted with Terminix for the installation of a termite protection system within the church building. To this end, Terminix drilled holes through the church’s interior concrete floor and installed pipes into which pesticide could be injected. This contract did not contain an arbitration clause. In June 2000, after the church discovered termite damage, the church entered into a new contract with Terminix for a baiting system to be used outside of the church building. This 2000 contract contained an arbitration clause.
From 1976 until 1985, the church contracted with Orkin for the inspection and treatment of termites within the church building. 2 When treating for termites, Orkin utilized the system installed by Terminix. Orkin terminated this service contract in 1985, after the church inadvertently failed to make two annual payments. In 1987, the church entered into a new contract with Orkin for the continued inspection and treatment of the church building. This contract also did not contain an arbitration clause. In 1998, the Church and Orkin entered into a separate contract for the inspection and treat *206 ment of the parish hall. 3 This contract contained an arbitration clause; however, it did not incorporate or reference the 1987 contract for Orkin’s treatment of the church building.
After termites were discovered in the church building, the church sued both Orkin and Terminix for damages. 4 Orkin and Terminix each filed a motion to compel arbitration. Orkin argued that the arbitration clause in its 1998 contract with the church is broad enough to compel arbitration of disputes arising from the prior contracts. Terminix raised the same argument with respect to its 2000 contract with the church.
The trial court denied both Orkin’s and Terminix’s motions to compel arbitration. The trial court held there was nothing in the 1998 Orkin contract or the 2000 Terminix contract signifying a retroactive effect. Thus, the trial court held arbitration was not required for causes of action arising out of the prior contracts.
STANDARD OF REVIEW
Whether a claim is subject to arbitration is an issue for judicial determination, unless the parties have agreed otherwise.
Stokes v. Metro. Life Ins. Co.,
LAW/ANALYSIS
In South Carolina, the test for determining whether a particular issue is subject to arbitration is articulated in
Zabinski v. Bright Acres Assocs.,
The issue before this court is whether the church’s claims against Orkin and Terminix fall within the scope of each party’s arbitration clause. In this case, the claims asserted by the church arose prior to the execution of the contracts which contain the arbitration clause. It is therefore necessary for this court to determine whether the arbitration clauses in Orkin’s and Terminix’s contracts were sufficiently broad so as to embrace disputes arising under prior contracts. Because this issue has received little discussion in South Carolina, we look to the federal courts for instruction as to the scope of the clauses at issue in this case. It is necessary to understand fully the scope of the clauses in order to effectively determine whether either is capable of an interpretation which covers the claims asserted by the church.
Courts have retroactively applied arbitration clauses to disputes arising under prior contracts, but in doing so, the courts have generally found the existence of a broadly worded clause which governed the overall relationship between the
*208
parties.
6
See, e.g., Cara’s Notions, Inc. v. Hallmark Cards, Inc.,
Where the language of the arbitration clause is not as broad, courts have refused to mandate the arbitration of
*209
disputes unrelated to the contract containing the clause. In
Sec. Watch, Inc. v. Sentinel Sys. Inc.,
In
In re Hops Antitrust Litig.,
We derive from these cases that the mere fact that an arbitration clause might apply to matters beyond the express scope of the underlying contract does not alone imply that the clause should apply to every dispute between the parties. For example, a clause compelling arbitration for any claim “arising out of or relating to this agreement” may cover disputes outside the agreement, but only if those disputes relate to the subject matter of that agreement.
See Zabinski,
A. Orkin’s appeal
The pertinent language in the arbitration provision of the 1998 Orkin contract is as follows:
ANY DISPUTE ARISING OUT OF OR RELATING TO THIS AGREEMENT OR THE SERVICES PERFORMED UNDER THIS AGREEMENT OR TORT BASED CLAIMS FOR PERSONAL OR BODILY INJURY OR DAMAGE TO REAL OR PERSONAL PROPERTY SHALL BE FINALLY RESOLVED BY ARBITRATION ADMINISTERED UNDER THE COMMERCIAL ARBITRATION RULES OF THE AMERICAN ARBITRATION ASSOCIATION.
Orkin argues the arbitration clause applies to claims for damage to real property, and thus applies to this dispute as a result of the church’s allegation of damages to the church building. We disagree.
We do not construe Orkin’s arbitration clause so broadly as to encompass any and all disputes arising out of the relationship of the parties.
See, e.g., Cara’s Notions,
At the time the church and Orkin entered into the 1998 contract, the church had not yet discovered the termite dam
*211
age, which forms the basis of its claims. Accordingly, the church could not have intended to submit to arbitration specific claims for which it had no knowledge, unless the church intended to arbitrate every claim of this nature. We recognize the broad policy in favor of arbitration; however, we do not broadly construe Orkin’s arbitration clause as applying to every incident of property damage, irrespective of the time in which the claim arose or the property upon which the damage was suffered. Even assuming,
arguendo,
that the clause may be construed to apply to property which is not thé subject of the 1998 contract, the words chosen by Orkin in no way evince an intention to apply the clause to claims which had accrued at a time prior to the execution of the 1998 contract. Although the arbitration clause does not expressly limit its application to the parish hall, it contains no language expanding its application to other properties either. As was noted in
Hendrick v. Brown & Root, Inc.,
[T]he supreme court has never held that an intent to arbitrate can be found from the absence of contractual language evincing an intent to arbitrate a particular kind of dispute. Rather, the court has held that only doubtful interpretations of contractual language respecting the scope of the agreement to arbitrate certain kinds of disputes are to be resolved in favor of arbitration. To convert that principal into a rule that a [party] may insulate itself from pre-existing claims by failing to say so in explicit terms is a fundamental distortion of the principle.
We find no correlation between the factual allegations underlying the church’s complaint and the subject matter of the 1998 contract, and thus we hold the church’s claims do not fall within the scope of Orkin’s arbitration clause. The terms chosen by Orkin to define the scope of its arbitration agreement are wholly ineffective to broaden its application to preexisting claims involving unrelated real property. Accordingly, we hold the trial judge properly denied Orkin’s motion to compel arbitration.
B. Terminix’s appeal
Terminix argues that, because the arbitration clause in the 2000 contract required arbitration for all disputes *212 between the parties, the trial court erred in denying its motion to compel arbitration.
The pertinent language in the arbitration provision in the 2000 Terminix contract is as follows:
The [Church] and Terminix agree that all matters in dispute between them, including but not limited to (i) any controversy or claim between them arising out of or relating to this Agreement, (ii) any wood destroying insect report with respect to the described property or (iii) the described property in any way, in any such case whether by virtue of contract, tort or otherwise, shall be settled exclusively by arbitration.
Applying Zabinski, we look to the factual allegations of the church’s claim against Terminix to determine whether there is a substantial relationship of the allegations to the subject matter of the 2000 contract. The church contends that there is no relation between the dispute and the 2000 contract because the dispute concerns defective services to the inside of the church building while the 2000 contract was for the installation of a termite baiting system in the ground on the outside of the church building. We are not persuaded by this distinction. Whether the treatment was to the inside of the building or to the earth outside the building, the common purpose was the prevention of termite infestations in the budding structure. At the hearing on the motion to compel arbitration, counsel for the church stated the purpose of the 2000 contract was as follows:
[T]he church called Terminix in the year 2000 and said we have got a grand problem out here. We’ve got termites that have eaten up the church. We need to get them stopped. So Terminix comes out, enters a separate contráete ] ... to [install] these bait stations.... And that was solely for the purpose of mitigating the damage that had been by the termites coming in, inside the church.
It is clear from these statements that the 2000 contract was executed as a direct result of the damage caused by Terminix’s alleged failure to perform under its prior contract. Therefore, we find the church’s current allegations against Terminix substantially relate to the subject matter of the 2000 contract considering the 2000 contract concerns the treatment
*213
(albeit by different methods) of the same building in an effort to mitigate the very damages complained of in the present dispute. The church was aware of the termite damage (and thus the existence of a cause of action against Terminix) at the time the church executed the contract containing the arbitration clause. In light of the purpose for which the 2000 contract was entered, we cannot find that the claims at issue in this case were not within the parties’ contemplation at the time the contract was executed. Moreover, the express terms of the clause provide that
“all matters in dispute
between [the parties] ... shall be settled exclusively by arbitration.” This language is very broad, and it is more akin to the language generally held to reflect an intention to apply to matters arising out of the relationship of the parties. The fact that the dispute accrued prior to the execution of the 2000 contract is not dispositive where, as here, the terms of the agreement are susceptible to an interpretation which covers any dispute existing between the parties.
See Zabinski,
CONCLUSION
Because the scope of Orkin’s 1998 arbitration clause does not encompass the church’s claims, which arose under prior, unrelated contracts, we affirm the trial court’s denial of Or-kin’s motion to compel arbitration. Terminix’s arbitration agreement is much broader, however, and we hold its clause is susceptible to an interpretation that covers the claims asserted by the church. Accordingly, we reverse the trial court’s decision to deny Terminix’s motion to compel arbitration.
AFFIRMED in Part and REVERSED in Part.
Notes
. There are two buildings on the Church property: the church building and a separate parish hall.
. None of the parties can locate a copy of this first contract between the Church and Orkin, although its existence is not contested.
. The parish hall is referred to as the "parsonage” in the 1998 Orkin contract.
. The Church also filed suit against both the architect and the contractor responsible for the restoration of the church building. However, the circuit court granted tírese defendants' motions to compel arbitration, and they are not involved in this appeal.
. The applicability of the Federal Arbitration Act, 9 U.S.C. § 1 et. seq., is not in dispute.
. An arbitration provision will also cover disputes arising under prior contracts where the clause contains retroactive, time-specific language mandating its application to previously executed contracts.
See Merrill Lynch, Pierce, Fenner, & Smith, Inc. v. Kirton,
